Resolved
The Committee agreed to note the spending forecasts summarised at Table 1 of the report.
Business Support Overview and Scrutiny Committee agreed this item on Thursday 30 November 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee agreed to note the spending forecasts summarised at Table 1 of the report.
2.1The approved capital programme for 2017/18 is £92.002million. This report consolidates the capital expenditure forecasts prepared by each directorate. Appendix 1 gives the full programme by programme detail. The notes in section 3 and 4 of this report below represent a commentary on areas of concern or items of particular interest. 3. Forecast Position at Quarter 2 3.1 Table 1 summarises the overall capital programme and the latest forecast position: Current 2017/18 2018/19 2019/20 2020/21 Forecast Round Forecast Forecast Forecast Forecast Variance Budget £000s £000s £000s £000s £000s £000s Business Support 787 782 5 0 0 0 Children and Adults 23,459 16,042 5,252 2,240 0 76 Housing Revenue 6,080 5,957 123 0 0 0 Account Members Priorities 253 253 0 0 0 0 Regeneration, Culture, 56,237 24,823 18,204 6,636 6,575 2 Environment and Transformation Digital Transformation 5,187 2,544 2,643 0 0 0 Total 92,002 50,401 26,227 8,876 6,575 78
3.2Table 2 shows how the current programme is funded:
Digital Member C&A RCET HRA BSD Trans- Total Funding Source Priorities formation £000s £000s £000s £000s £000s £000s £000s Borrowing 0 5,952 0 0 5,187 0 11,139 Capital Grants 14,946 44,495 0 31 0 0 59,472 Capital Receipts 0 2,254 0 532 0 253 3,039 S106 8,213 2,028 0 0 0 0 10,241 Contributions Revenue / 300 1,507 6,080 224 0 0 8,111 Reserves 23,459 56,236 6,080 787 5,187 253 92,002
3.3The projected overspend of £76,000 on Children and Adults relates to adaptations to social care buildings, and officer discussions on actions to reduce this overspend are ongoing. The overspend of £2,000 on Regeneration, Culture, Environment and Transformation relates to the Parking Services IT System.
4. New Schemes and Virements
4.1The following schemes were approved via the Capital Additions Report at Full Council on 20 July 2017: Civic Centre flood mitigation measures; £3.5million. Innovation Park Medway Zone A; £3.7million. Civic Centre demolition; £0.550million.
4.2Brookhill and Hillyfields Greenspace Improvements S106 funding has been vired to revenue schemes and improvements to Eastgate House Garden. The Strand budget has been reduced so that the funding can instead be used for the Strand Play Area scheme. £57,000 of Greenspace Initiative S106 has been used to fund revenue schemes and the Strand Play Area.
5. Risk Analysis
5.1The report provides detailed information regarding individual schemes and no significant risks have been identified to the current programme.
6. Financial and Legal Implications
6.1The financial implications are fully analysed in the report. There are no direct legal implications to this report.
7.1The Committee is asked to note the spending forecasts summarised at Table 1 of the report.
Lead officer contact Katey Arrowsmith, Head of Finance Strategy, Gun Wharf [email protected] Appendices Appendix 1 – Capital Budget Monitoring details
Background papers Capital budget approved by Council 23 February 2017 https://democracy.medway.gov.uk/mgAi.aspx?ID=15427
Council approved additions to the Capital programme https://democracy.medway.gov.uk/ieIssueDetails.aspx?IId=20081&Opt=3
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix 1Appendix 1 | 147 KB | Download |
PDF |
Capital Budget Monitoring 2017/18: Quarter 2Report | 170 KB | DownloadRead as text |
Follow Business Support Overview and Scrutiny Committee at Medway and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Jul 2023 | Work programmeDecision a) The Committee agreed the Committee’s provisional work programme at Appendix 1 to the report. b) The Commi... | Agreed | Open |
| 30 Mar 2023 | Annual Review of the Council's Petitions SchemeThe Committee noted the 2022 annual review of the Council’s Petitions Scheme. | Noted | Open |
| 30 Mar 2023 | Work programme and review of the Committee's work, 2019/231) The Committee agreed the Committee’s provisional work programme at Appendix 1, subject to the following and the vi... | Agreed | Open |
| 25 Jan 2023 | Contract Procedure RulesThe Committee: a) noted the comments of the Audit Committee on the draft revised set out in Appendix 2 to the report;... | Noted | Open |
| 25 Jan 2023 | Work programmeThe Committee: a) agreed the committee’s work programme at Appendix 1 to the report; b) noted the work programmes of ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.