Resolved
The Committee agreed to note the result of the third round of capital monitoring for 2017/18 and also the forecast position and proposed management action.
Business Support Overview and Scrutiny Committee agreed this item on Thursday 12 April 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee agreed to note the result of the third round of capital monitoring for 2017/18 and also the forecast position and proposed management action.
This report presents the results of the Council’s capital monitoring for Quarter 3 of the 2017/18 financial year and includes out-turn forecasts and reference to any new schemes for approval.
1. Budget and Policy Framework
1.1Cabinet is responsible for ensuring that expenditure for each capital scheme remains within the budget approved by Council.
2.1The approved capital programme for 2017/18 is £92.002million. This report consolidates the capital expenditure forecasts prepared by each directorate. Appendix 1 provides the detail by individual scheme. The notes in section 3 and 4 of this report below represent a commentary on areas of concern or items of particular interest.
3. Forecast Position at Quarter 3
3.1Table 1 summarises the overall capital programme and the latest forecast position:
Current 2017/18 2018/19 2019/20 2020/21 Forecast Round Forecast Forecast Forecast Forecast Variance Budget £000s £000s £000s £000s £000s £000s Business Support 787 625 160 0 0 (2) Children and Adults 23,459 14,266 7,579 1,690 0 76 Housing Revenue 6,080 6,042 38 0 0 0 Account Members Priorities 253 253 0 0 0 0 Regeneration, Culture, Environment and 56,237 22,852 19,616 8,186 5,583 0 Transformation Digital Transformation 5,187 2,447 2,740 0 0 0 Total 92,002 46,484 30,133 9,876 5,583 74 3.2 Table 2 shows how the current programme is funded: Digital Member C&A RCET HRA BSD Trans- Priorities Total Funding Source formation £000s £000s £000s £000s £000s £000s £000s Borrowing 0 5,952 0 0 5,187 0 11,139 Capital Grants 14,946 44,495 0 31 0 0 59,472 Capital Receipts 0 2,254 0 532 0 253 3,039 S106 8,213 2,028 0 0 0 0 10,241 Contributions Revenue / 300 1,507 6,080 224 0 0 8,111 Reserves 23,459 56,236 6,080 787 5,187 253 92,002
3.3The projected overspend of £76,000 on Children and Adults, as set out in Appendix 1 relates to adaptations to social care buildings, and officer discussions on actions to reduce this overspend are ongoing.
3.4The modest underspend against the Business Support programme relates to an underspend on the Legal Case Management System.
4. New Schemes and Virements
4.1£55,000 has been vired from the Strood Riverside LGF budget to fund completion of the Innovation Studios, which are integral to the regeneration of Strood Riverside.
4.2The following Member Priority schemes have been approved since Quarter 2: Allhallows Village Hall Kitchen. Symonds Avenue/Magpie Hall Road.
5.1The report provides detailed information regarding individual schemes and no significant risks have been identified to the current programme.
6. Financial and Legal Implications
6.1The financial implications are fully analysed in the report. There are no direct legal implications to this report.
7.1It is requested that the Committee notes the result of the third round of capital monitoring for 2017/18 and agrees the forecast position and proposed management action.
Lead officer contact
Katey Arrowsmith, Head of Finance Strategy, Gun Wharf [email protected] Appendices
Appendix 1 – Capital budget monitoring returns
Capital budget approved by Council 23 February 2017 https://democracy.medway.gov.uk/mgAi.aspx?ID=15427
Council approved additions to the Capital programme https://democracy.medway.gov.uk/ieIssueDetails.aspx?IId=20081&Opt=3
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix 1Appendix 1 | 308 KB | Download |
PDF |
Capital Budget Monitoring 2017/18: Quarter 3Report | 171 KB | DownloadRead as text |
Follow Business Support Overview and Scrutiny Committee at Medway and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Jul 2023 | Work programmeDecision a) The Committee agreed the Committee’s provisional work programme at Appendix 1 to the report. b) The Commi... | Agreed | Open |
| 30 Mar 2023 | Annual Review of the Council's Petitions SchemeThe Committee noted the 2022 annual review of the Council’s Petitions Scheme. | Noted | Open |
| 30 Mar 2023 | Work programme and review of the Committee's work, 2019/231) The Committee agreed the Committee’s provisional work programme at Appendix 1, subject to the following and the vi... | Agreed | Open |
| 25 Jan 2023 | Contract Procedure RulesThe Committee: a) noted the comments of the Audit Committee on the draft revised set out in Appendix 2 to the report;... | Noted | Open |
| 25 Jan 2023 | Work programmeThe Committee: a) agreed the committee’s work programme at Appendix 1 to the report; b) noted the work programmes of ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.