Resolved
The Committee agreed to note the spending forecasts summarised at Table 1 of the report.
Business Support Overview and Scrutiny Committee agreed this item on Thursday 29 November 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee agreed to note the spending forecasts summarised at Table 1 of the report.
2.1The approved capital programme for 2018/19 is £227.773million. This report consolidates the capital expenditure forecasts for the second quarter and Appendix 1 provides a scheme by scheme forecast position for the whole programme. The report also provides details of any additions to the capital programme since the Quarter 1 monitoring report.
3. Forecast Position at Quarter 2
3.1Table 1 summarises the overall capital programme and the latest forecast position:
Directorate Current 2018/19 2019/20 2020/21 2021/22 Forecast Budget Forecast Forecast Forecast Forecast Variance £000s £000s £000s £000s £000s £000s Children and Adults 15,915 14,629 1,465 0 0 178 Regeneration, Culture, 61,895 38,974 16,198 5,838 886 0 Environment and Transformation Housing Revenue Account 7,045 5,714 1,331 0 0 0 Business Support 142,723 13,991 52,151 38,697 37,884 0 Department Public Health 0 0 0 0 0 0 Members Priorities 197 197 0 0 0 0 Total 227,773 73,505 71,144 44,534 38,770 178 3.2 Table 2 shows how the current programme is funded:
Funding Source C&A RCET HRA BSD Public Member Total Health Priorities £000s £000s £000s £000s £000s £000s £000s Prudential Borrowing 0 6,852 0 20,164 0 0 27,016 Borrowing in lieu of 0 10,768 0 121,352 0 0 132,120 Capital Receipts Capital Receipts 0 2,905 0 257 0 194 3,355 Capital Grants 15,249 39,762 0 31 0 0 55,041 RTB Receipts 0 127 300 0 0 0 427 S106 Contributions 667 1,437 0 0 0 0 2,104 Revenue / Reserves 0 46 6,745 919 0 0 7,710 Total 15,916 61,895 7,045 142,723 0 194 227,773
3.3The overspend on Children and Adults of £178,000 relates to variances on four schemes: Hundred of Hoo Primary extension phase 2 – value engineering throughout the project is projected to result in an underspend of £85,000 which will be transferred back to the Basic Need Programme. Abbey Court relocation and expansion – value engineering throughout the project is projected to result in an underspend of £86,000 which will be transferred back to the Basic Need Programme. Family Hubs and Wellbeing Centre – works required to bring the Elaine Centre up to the required standard to deliver the services previously provided at Bligh resulted in a forecast overspend of £50,000. This will be funded by a revenue contribution to capital. Children & Adults Mobile Working – the overspend of £299,000 relates to the cost of the prudential borrowing taken out to fund the purchase of mobile devices. Cabinet have agreed to recommend to the January meeting of the Full Council that this sum be added to the Capital Programme, funded by prudential borrowing.
4. New Schemes and Virements
4.1At its meeting on 19 July 2018, Full Council approved the addition to the capital programme of £850,000 to fund the re-modelling of the Britton Farm supermarket premises, following the departure of Budgens, to allow it be let as new office accommodation for KMPT (Kent and Medway NHS and Social Care Partnership Trust).
4.2In August 2018, the Chief Finance Officer, in consultation with the Leader approved the addition of £235,000 to the capital programme for road adoption works and tree works relating to St Mary’s Island, with funding received from the developer via a S38 Agreement. This was in accordance with Chapter 4, Part 6, Paragraph 3.7 of Medway Council’s Constitution.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Q2 Capital MonitoringAppendix 1 | 160 KB | Download |
PDF |
Capital Budget Monitoring 2018/19: Quarter 2Report | 156 KB | DownloadRead as text |
Follow Business Support Overview and Scrutiny Committee at Medway and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Jul 2023 | Work programmeDecision a) The Committee agreed the Committee’s provisional work programme at Appendix 1 to the report. b) The Commi... | Agreed | Open |
| 30 Mar 2023 | Annual Review of the Council's Petitions SchemeThe Committee noted the 2022 annual review of the Council’s Petitions Scheme. | Noted | Open |
| 30 Mar 2023 | Work programme and review of the Committee's work, 2019/231) The Committee agreed the Committee’s provisional work programme at Appendix 1, subject to the following and the vi... | Agreed | Open |
| 25 Jan 2023 | Contract Procedure RulesThe Committee: a) noted the comments of the Audit Committee on the draft revised set out in Appendix 2 to the report;... | Noted | Open |
| 25 Jan 2023 | Work programmeThe Committee: a) agreed the committee’s work programme at Appendix 1 to the report; b) noted the work programmes of ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.