Resolved
The Council agreed to add £11,155,144 to the Council’s Capital Programme for the Street Lighting LED (light emitting diode) and Column Replacement Programme to be funded by prudential borrowing met from projected energy savings.
Council agreed this item on Thursday 23 April 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
The Council agreed to add £11,155,144 to the Council’s Capital Programme for the Street Lighting LED (light emitting diode) and Column Replacement Programme to be funded by prudential borrowing met from projected energy savings.
This report provides details of the LED (Light Emitting Diode) and Column Replacement Programme and procurement exercise following consideration at the Procurement Board on 18 March 2020 and Cabinet on 7 April 2020, details of which are set out at sections 5 and 6 of the report.
This report asks full Council to agree to add £11,155,144 to the Council’s Capital Programme for the Street Lighting LED (light emitting diode) and Column Replacement Programme to be funded by prudential borrowing met from projected energy savings.
1. BACKGROUND INFORMATION
1.1Background Information
1.1.1 The street lighting network comprises 25,667 street lights and in 2018, Medway Council secured borrowing, via the Prudential Borrowing route, of £2.72m for a column replacement scheme, across financial years 2018/19 and 2019/20. As part of this scheme, those columns, which did not already have LED lanterns, would be converted to LED. This would increase the number of LED lanterns, on the network, to approximately 4,526. With additional lanterns being replaced over the past 2 years, the total now stands at over 5000. Having said that, some of the older LED lanterns have been in place up to 10 years and therefore could not support future proofing “Smart City” ambitions, so some of these would need to be replaced under a full LED scheme. In total it is anticipated that approximately 23,100 lanterns will need conversion.
1.1.2 In addition to the LED scheme, a subset of essential column replacements is required. These columns require replacing, irrespective of whether the LED scheme goes ahead or not, but as part of the LED scheme, have attracted more competitive financial rates, due to economies of scale.
1.1.3 The current situation, where column replacements are prioritised within an inadequate funding envelope is unsustainable. Most columns are already beyond their original design life and even focussing on columns that are deemed structurally unsafe, there is insufficient funding, in annual budgets to meet the needs of the service. As such a total of 4,668 column replacements form part of this scheme. Of these, 3,656 are of concrete design and could not support an LED lantern due to weighting and design issues.
1.1.4 As part of budget setting for this financial year, the Capital and Revenue Budgets 2020/21 Report presented to full Council on 22 February 2020 noted that a business case and gateway 3 report for the LED street lighting programme would be presented to the Cabinet. The business case for the conversion of the highway street lighting network to LED (light emitting diode) sets out how the Council would realise financial and environmental benefits, through reduction in energy use and which would also support Medway Council’s “Smart City” ambitions. It was accepted that a subset of column replacements would also form part of the scheme.
1.1.5 The tender encompasses both LED conversion and column replacements, with options for a Central Management System (CMS) for dimming and trimming light levels and Smart City future proofing and integration, with the preferred option being to install a CMS system, if it was financially viable.
1.1.6 The benefits of CMS both now and in the future are:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Addition to the Capital Programme: Street Lighting LED and Column Replacement ProgrammeReport | 549 KB | DownloadRead as text |
Follow Council at Medway and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2026 | Amendments to the Revenue Budget and Capital Programmea) The Council agreed the addition of £3.743million to the revenue budget from general reserves to fund the final ove... | Agreed | Open |
| 16 Jul 2026 | Review of the Council's Petitions Schemea) The Council noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in ... | Noted | Open |
| 16 Jul 2026 | Independent Remuneration Panel - Report on Members' Allowances Schemea) The Council thanked the members of the Panel for undertaking the review of Members Allowances and producing their ... | Approved | Open |
| 13 May 2026 | Election of Mayor and Appointment of Deputy Mayor 2026/2027a) The Council elected Councillor Hamandishe to the Office of the Mayor of Medway for the 2026/2027 municipal year. b... | Decided | Open |
| 13 May 2026 | Establishment of Committees, Appointments and Schedule of Meetings 2026/20271) The Council: a) Agreed the establishment of Committees, their size and the allocation of seats to political groups... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.