Pentagon Shopping Centre - Addition to the Capital Programme and Virements

Agreed Committee 1 paper

Council agreed this item on Wednesday 24 January 2024. Below is the council's own wording, with the papers it was decided on.

Item564

Resolved

a) The Council agreed an addition to the Capital Programme , of £2,752,000 for the delivery of the Healthy Living Centre in the Pentagon Centre, noting this figure would be reimbursed by the NHS and is subject to NHS final approvals and S106 contributions. b) The Council agreed the following virements from the existing Pentagon Centre future works budget, to deliver the diversification of the first floor of the Pentagon Centre: A. £1,245,900 to deliver the Healthy Living Centre B. £1,811,366 to deliver the Innovation Hub
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Council

Council 24 January 2024 Pentagon Shopping Centre – Addition to the Capital Programme and Virements Portfolio Holder: Councillor Naushabah Khan, Portfolio Holder for Housing and Property

Report from: Sunny Ee, Assistant Director Regeneration

Author: Beth Westwood, Regeneration Programme Manager

Summary This report requests a capital addition to deliver the Healthy Living Centre in the Pentagon Centre, a cost which will be reimbursed by the NHS. The report also seeks approval for virements for reporting clarity purposes.

The report was due to be considered by the Cabinet on 16 January 2024. The recommendations to the Cabinet are set out in section 6 of the report.

1. Recommendations 1.1 The Council is asked to agree an addition to the Capital Programme, of £2,752,000 for the delivery of the Healthy Living Centre in the Pentagon Centre, noting this figure will be reimbursed by the NHS and is subject to NHS final approvals and S106 contributions.

1.2The Council is asked to agree the following virements from the existing Pentagon Centre future works budget, to deliver the diversification of the first floor of the Pentagon Centre:

A. £1,245,900 to deliver the Healthy Living Centre B. £1,811,366 to deliver the Innovation Hub

2. Budget and policy framework 2.1 In February 2019, Cabinet recommended to Full Council the acquisition of the head lease of the Pentagon Centre and in so doing granted delegated authority to carry out the re-configuration and improvement works to the Pentagon Centre and to manage and let the centre (decision no. 32/2019).

2.2On 21 February 2019, the Council added £45 million to the capital programme to fund the acquisition of the Pentagon Centre. 2.3 In 2020 Council approved the virement of the underspend following the acquisition of the Pentagon Centre to a new capital scheme for future capital works at the Pentagon Centre (Minute no.713D, Full Council 20 February 2020).

2.4Full Council in Feb 2022 added £10,348,000 to the Capital Programme to fund the Healthy Living Centre (HLC), on the provision that the NHS would reimburse the full amount.

2.5The Council was awarded c.£9.5m grant funding from the Future High Street Fund (FHSF), to assist with the delivery of the HLC and Innovation Hub on the first floor of the Pentagon Centre, the acquisition and redevelopment of the ground floor of the former Debenhams project, along with other regeneration projects in the heart of Chatham. The £9,497,720 was added to the Capital Programme in 18 February 2021.

2.6It is the responsibility of Cabinet to ensure that expenditure for each capital scheme remains within the budget approved by the Council, it remains the responsibility of Council to approve schemes for inclusion in the capital programme.

3. Background 3.1 In February 2019 the Council approved a £45 million addition to the capital programme to acquire the head lease of the Pentagon Centre. The Council acquired the Pentagon Centre in 2019 at a total cost of almost £37 million. £3 million was vired to fund the subsequent acquisition of the Mountbatten House sub-lease and the circa £5 million balance of the original borrowing approval allocated to fund ‘future capital works to the Pentagon Centre’ (Minute No. 713D, Full Council 20 February 2020).

3.2The Council acquired the Pentagon Centre in April 2019, knowing that the ground floor was trading well and that the first floor would need investment. Various options have been considered for the redevelopment of the first floor, with the two uses below being progressed:

• An NHS HLC, this will provide a much-needed medical facility in Chatham. • An Innovation Hub, which will be part funded from the Future High Street Fund.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Pentagon Shopping Centre: Addition to the Capital Programme and VirementsReport 164 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

52 of 63 attended
KA
Councillor Kwashie Anang (Con)Committee Member, present
DA
Councillor Damola Animashaun (Lab)Committee Member, present
RB
Councillor Roger Barrett (Con)Committee Member, present
LB
Councillor Linda Bowen (Lab)Committee Member, present
DB
Councillor David Brake (Con)Committee Member, present
HB
Councillor Hazel Browne (Lab)Committee Member, present
SC
Councillor Smitha Campbell (Lab)Committee Member, present
TC
Councillor Trevor Clarke (Con)Committee Member, present
EC
Councillor Esther Cook (Lab)Committee Member, present
TC
Councillor Tracy Coombs (Lab)Committee Member, present
GC
Councillor George Crozer (Ind)Committee Member, present
SC
Councillor Simon Curry (Lab)Committee Member, apologies

All 63 on the meeting page

On this subject at Medway

Search all
  1. Pentagon Shopping Centre - Addition to the Capital Programme and VirementsThis decision
  2. Gateway 3 Tender Process Review and Contract Award: Building Contractor for the Healthy Living Centre, the Pentagon Shopping CentreAgreed
  3. Planning application - MC/23/2700 Pentagon Shopping Centre, Military Road, Chatham, MedwayApproved
  4. Project update - Pentagon Shopping Centre and former Debenhams BuildingApproved
  5. Pentagon Shopping Centre Development BriefApproved

More from Medway Council

All decisions
MeetingDecisionOutcome
16 Jul 2026 Amendments to the Revenue Budget and Capital Programmea) The Council agreed the addition of £3.743million to the revenue budget from general reserves to fund the final ove... Agreed Open
16 Jul 2026 Review of the Council's Petitions Schemea) The Council noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in ... Noted Open
16 Jul 2026 Independent Remuneration Panel - Report on Members' Allowances Schemea) The Council thanked the members of the Panel for undertaking the review of Members Allowances and producing their ... Approved Open
13 May 2026 Election of Mayor and Appointment of Deputy Mayor 2026/2027a) The Council elected Councillor Hamandishe to the Office of the Mayor of Medway for the 2026/2027 municipal year. b... Decided Open
13 May 2026 Establishment of Committees, Appointments and Schedule of Meetings 2026/20271) The Council: a) Agreed the establishment of Committees, their size and the allocation of seats to political groups... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies