30/2024 The Cabinet agreed to pause delivery at Innovation Park Medway at appropriate milestones and noted the pause of expenditure associated with this . 31/2024 The Cabinet agreed to officers carrying out the review of development options for the Innovation Park Medway sites and agreed to delegate authority to the Director of Place, in consultation with the Leader of the Council and Portfolio Holders for Climate Change and Strategic Regeneration and for Economic and Social Regeneration and Inward Investment, to investigate options for disposal of the Innovation Park Medway sites, including a Joint Venture, and present Cabinet with the preferred option for approval. 32/2024 The Cabinet approved the virement of £200,000 capital funding from the Innovation Park Medway budgets to a new capital budget code to undertake a review of the most sustainable development options for the Innovation Park Medway sites. Reasons: Further work is required to ensure that the sites are brought forward in a manner that suits the evolving needs of businesses in Medway along with ensuring that the sites are delivered in the most sustainable manner. It is deemed necessary to pause the current work to avoid any abortive expenditure whilst this review takes place.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
Cabinet 13 February 2024 Innovation Park Medway Update Portfolio Holders: Councillor Simon Curry, Portfolio Holder for Climate Change and Strategic Regeneration Councillor Lauren Edwards, Portfolio Holder for Economic and Social Regeneration and Inward Investment
Report from: Sunny Ee, Assistant Director - Regeneration
Author: Tay Arnold, IPM Programme Manager
Summary Medway Council is proposing to pause development at Innovation Park Medway and explore the best options for its future delivery. The market has changed quite significantly in the current financial climate and in the wake of COVID-19 impacting the way businesses now work. It is good practice to take the opportunity to pause and review the best long-term opportunities for Innovation Park Medway to ensure the most sustainable future for the sites and to achieve the outcomes envisaged from the sites.
1. Recommendations 1.1 The Cabinet is requested to agree to pause delivery at Innovation Park Medway at appropriate milestones and note the pause of expenditure associated with this.
1.2The Cabinet is asked to agree to officers carrying out the review of development options for the Innovation Park Medway sites and to delegate authority to the Director of Place, in consultation with the Leader of the Council and Portfolio Holders for Climate Change and Strategic Regeneration and for Economic and Social Regeneration and Inward Investment, to investigate options for disposal of the Innovation Park Medway sites, including a Joint Venture, and present Cabinet with the preferred option for approval.
1.3Subject to the above recommendation at paragraph 1.2 being agreed, the Cabinet is asked to approve the virement of £200,000 capital funding from the Innovation Park Medway budgets to a new capital budget code to undertake a review of the most sustainable development options for the Innovation Park Medway sites. 2. Suggested reasons for decisions 2.1 Further work is required to ensure that the sites are brought forward in a manner that suits the evolving needs of businesses in Medway along with ensuring that the sites are delivered in the most sustainable manner. It is deemed necessary to pause the current work to avoid any abortive expenditure whilst this review takes place.
3. Budget and policy framework 3.1 IPM to date has been funded by a mix of council borrowing, grants and loans. IPM has been awarded £11.6m external funds (a mix of capital grants, loans and revenue grants).
3.2As a consequence of this proposed pause, spend in the IPM capital budgets will also be paused at appropriate milestones. Where works are partially completed spend will continue until a suitable milestone is reached, alongside continued staffing costs to manage this work. The anticipated spend against capital is contained within the Council’s Capital monitoring report. It is proposed that £200k of the IPM capital budget is repurposed to fund the work required to assess development options and a virement to a new budget code agreed. This is a matter for Cabinet.
4. Background 4.1 IPM retains the ability to be a catalyst for business growth in Medway, focusing on high value knowledge intensive businesses. Set over two discrete but adjacent sites, IPM is designed to deliver Over 60,000m2 of commercial space to help grow Medway’s local economy and create up to 3,000 High Value (high GVA) jobs attracting high value technology, engineering, manufacturing, and knowledge intensive businesses. The Council support for IPM has helped secure the extension of the investment in the neighbouring BAE site due to the potential for a cluster of related high value occupiers. Currently the Regeneration and Planning teams have received more than 200 general enquires seeking to locate on site. A new development approach is now required to respond to raised interest rates and the impact nationally of inflation. This report sets out options for this revised approach.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.