Gateway 1 Procurement Commencement: Innovation Park Medway South/Care for Medway

Agreed Executive 1 paper

AI summaryMedway Cabinet agrees to open single stage tender for design and build contract at Innovation Park Medway South / Care for Medway, with funding already in capital programme.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedDesign and build contract, unrestricted market access
MoneyOver £5.33M works thresholdFunding added to capital programme Nov 2025
What happens nextCabinet paper before RIBA 4Required prior to awarding the tender
Who it affectsNot stated

What was decided

The Cabinet agreed to pursue procurement of a design and build contract via open single stage procedure, allowing all interested suppliers to tender. Report P19

The procurement was classified as Process 3 under the Council's Contract Procedure Rules, with a tender notice required as it exceeds the works threshold. Report P14, P19

Soft market testing in early 2026 informed the choice of open tender as the best option given market conditions. Report 9.1, P19

Why

Officers said an open tender would promote transparency, competition and value for money by allowing unrestricted market access. Report P19

Early BREEAM assessor engagement has already secured early credits for energy, materials and sustainable construction. Report P23

Social value measures on local employment, apprenticeships, supply chain and CO2 reduction will be scored as part of price evaluation and written into KPIs. Report 11.1, 11.2, P30

What happens next

A further Cabinet paper will be brought forward for permission to move to RIBA 4 before the tender is awarded. Report P12

The Monitoring Officer, with the Procurement Board, will set risk and reporting stages for the rest of the procurement process. Report P14

The tender notice will be published on the Kent Business Portal and Contracts Finder in line with the CPRs. Report P14, P18

The money

  • £25,000.00 Minimum value above which advertising on Kent Business Portal and Contracts Finder is required Report P18
  • £5.33M Works threshold inclusive of VAT that the project will exceed Report P19

Options considered

  • Chosen: Open single stage tender (preferred). Best fit with market conditions, promotes transparency, competition and value for money Report P19
  • Rejected: Alternative procurement routes considered. Open process preferred in light of market conditions per Category Management Report P19

Implications

  • Legal: Process complies with the Procurement Act 2023, the Local Government (Contracts) Act 1997, the Localism Act 2011 and Medway's Contract Procedure Rules. Report P13, P14
  • Financial: Cost plans are reassessed at each RIBA stage for inflation; the tender sum may exceed the current budget (rated CII). Report P2, P12
  • Risk: Key risks include low market returns (CII), market returns exceeding expectations (CIII), planning delays (CII), and contractor financial failure (CII). Report P2, P3, P4, P5, P6
  • Climate: Project targets BREEAM very good; tender quality questions cover sustainable practices and circular economy, and embodied carbon will be mitigated through low carbon materials and waste minimisation. Report P23, P24, P30
  • Other: Social Value commitments from the winning bidder will become contractual KPIs covering local jobs, apprenticeships, local supply chain spend and CO2 reductions. Report 11.2, P29, P30

Who and where

  • Local MSMEs, VCSEs and supply chain in Medway (through social value measures) Report P29, P30
  • Local residents and school/college audiences (careers talks, skills initiatives) Report P29
  • Prospective design and build contractors (market-wide open tender) Report P19

Timeline

  • November 2025: Funding for the project, including contract costs, added to capital programme by Cabinet and Full Council Report P12, P34
  • Early 2026: Soft market testing carried out to gauge supplier appetite Report 9.1
  • 2 June 2026: Cabinet agrees to commence procurement under Gateway 1 (decision 87/2026)
  • Before tender award: Further Cabinet paper required for permission to move to RIBA 4 Report P12

Plain English for the jargon

  • Gateway 1: Medway Council's initial procurement stage at which Cabinet approves the start of a procurement process.
  • RIBA 4: Royal Institute of British Architects Stage 4, the detailed design stage before construction.
  • BREEAM very good: A sustainability rating for buildings, with 'very good' being a standard quality tier.
  • Process 3 procurement: A high value procurement route under Medway's Contract Procedure Rules requiring formal competitive tendering.
  • CII / CIII: Risk matrix ratings combining likelihood (C = Unlikely) and impact (II = Major, III = Moderate).
  • KPI: Key Performance Indicator, a measurable target included in the contract.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

87/2026 The Cabinet agreed to pursue the procurement of a design and build contract via open single stage procedure as per the preferred option identified in paragraph 7.2.4.1 of the report. Reasons: The recommended option allows unrestricted access to the market with all interested suppliers permitted to submit a tender, which can promote transparency, competition and value for money.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet

Cabinet

2 June 2026

Gateway 1 Procurement Commencement: Innovation Park Medway South/Care for Medway Portfolio Holder: Councillor Teresa Murray, Deputy Leader of the Council

Report from: Jackie Brown, Assistant Director for Adult Social Care

Authors: Su Irving, Head of Adults Partnership Commissioning and the Lead for the Better Care Fund Tay Arnold, Regeneration Programme Manager

Procurement Overview Total Contract Value (estimated): £44 million excl. VAT Regulated Procurement: No Proposed Contract Term: 24 months

Summary This report seeks permission to commence the procurement of the Design and Build Contract for Innovation Park Medway South Care for Medway.

1. Recommendations 1.1. The Cabinet is asked to agree to pursue the procurement of a design and build contract via open single stage procedure as per the preferred option identified in paragraph 7.2.4.1 of the report.

2. Suggested reasons for decision 2.1. The recommended option allows unrestricted access to the market with all interested suppliers permitted to submit a tender, which can promote transparency, competition and value for money.

3. Budget & Policy Framework

3.1The Cabinet agreed in July 2025 to expand the scope of the project to include all of the Southern site. It was also agreed that Cabinet recommend to Full Council that £44M be added to the capital programme. As per Cabinet’s decision a report will be brought back to Cabinet later this year (October/November 2026) to agree commencing RIBA 4. Following this the contractors for building out the site will be appointed.

4. Background Information and Procurement Deliverables

4.1Background Information

4.1.1. Provision of a new build 80-bed care home providing residential and nursing dementia care, and separate older persons independent living accommodation.

4.2Procurement Deliverables

4.2.1. As part of the successful delivery of this procurement requirement, the following procurement project outputs / outcomes within the table below have been identified as key and will be monitored as part of the procurement project delivery process.

Outputs / How will Who will When will success be Outcomes success be measure measured? measured? success of outputs/ outcomes Value for Contract price is Client Quantity Completion of tender Money within approved Surveyor evaluation. budget. Technical Recommended Tender Completion of tender Capability Contractor has evaluation evaluation. and demonstrable team Expertise capability and expertise. Financial Recommended Client Quantity Completion of tender Stability Contractor can Surveyor evaluation. provide a performance bond, pass credit rating requirements, and demonstrate ability to deliver this size of scheme. Programme Contractor is Tender Completion of tender able to meet the evaluation evaluation. expected team completion dates. 5. Parent Company Guarantee/Performance Bond Required

5.1Performance Bond will be obtained rather than Parent Company Guarantee as the proposed Contractors are not likely to be part of a group structure.

5.2This will provide further protection against financial loss and other contractual obligations e.g. planned completion and quality, recognising the significant importance and investment of this scheme.

6. Procurement Dependencies and Obligations 6.1. Project Dependency

6.1.1. This project is standalone and not linked to the delivery of Innovation Park Medway North. There will be a need to procure a care operator for the care home in the future but this is operational rather than build related for which the existing funds have been allocated for.

6.2Statutory/Legal Obligations

6.2.1. Not applicable regarding the build contract.

6.3Procurement Project Management

6.3.1. The management of this procurement process will be the responsibility of the Category Management team.

6.4Post Procurement Contract Management

6.4.1. The management of any subsequent contract will be the responsibility of the Regeneration Programme Manager.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gateway 1 Procurement Commencement: Innovation Park Medway South/Care for MedwayReport 263 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
VM
Councillor Vince Maple (Lab)Committee Member, present
TM
Councillor Teresa Murray (Lab)Committee Member, present
TC
Councillor Tracy Coombs (Lab)Committee Member, present
SC
Councillor Simon Curry (Lab)Committee Member, present
NG
Councillor Nina Gurung (Lab)Committee Member, present
HM
Councillor Harinder Mahil (Lab)Committee Member, present
AP
Councillor Alex Paterson (Lab)Committee Member, present
LP
Councillor Louwella Prenter (Lab)Committee Member, present
AP
Councillor Adam Price (Lab)Committee Member, present
ZV
Councillor Zoë Van Dyke (Lab)Committee Member, present

On this subject at Medway

Search all
  1. Gateway 1 Procurement Commencement: Innovation Park Medway South/Care for MedwayThis decision
  2. Gateway 1: Procurement of Housing Related Support ServicesAgreed
  3. Gateway 1 Procurement Commencement: Repairs and Maintenance for Temporary Accommodation Owned, One Medway Lettings, One Medway – Inspiring Change LA Hostels, Housing Revenue Account (HRA) Requirements, Medway Development Company (MDC) and the Sanctuary SchemeAgreed
  4. Gateway 1 Procurement Commencement: Innovation Park Medway NorthAgreed
  5. Gateway 3 Contract Award: Recycling Resource Management (RRM) ProcurementAgreed
  6. Gateway 1 Procurement Commencement: Medway Tunnel Lighting UpgradeAgreed

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies