Gateway 1 Procurement Commencement: Innovation Park Medway North

Agreed Executive 1 paper

AI summaryMedway Cabinet approves procurement of a development partner for Innovation Park Medway North using a multi-stage competitive procedure, with an estimated £120 million investment and a 7-year contract.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedCompetitive flexible procedure, 7 year contract
Money£120,000,000 estimated investmentBrought in by the development partner
What happens nextTender notice due 22 May 2026Contract award targeted early 2027
Who it affectsInnovation Park Medway North siteOwned by Medway Council, complex regeneration

What was decided

The Cabinet agreed to procure a development partner for Innovation Park Medway North under the competitive flexible procedure in accordance with the Procurement Act 2023, with a contract length of 7 years. Report P2, P63, P64

The Cabinet agreed the draft Heads of Terms in the exempt appendix and delegated authority to the Director of Place, in consultation with the Portfolio Holder for Climate Change and Strategic Regeneration and the Portfolio Holder for Economic and Social Regeneration and Inward Investment, to finalise and amend the Development Agreement. Report P3

Why

Officers consider the project a complex requirement that benefits from a multi-stage process allowing shortlisting, dialogue with bidders, and refinement of the specification, advantages not available under the open single-stage procedure. Report P8, P10, P11, P51, P53, P55

Soft market testing in early 2026 received four formal and five informal responses from credible national commercial developers, three of them active in the Kent market, indicating sufficient market appetite. Report 4.4, 10.1

Doing nothing or using an existing framework were rejected as not viable for a regeneration project of this scale, complexity and value. Report P44, P45

What happens next

Publish the tender notice and associated tender documents on 22 May 2026, run a participation period to 22 June 2026, then evaluate pre-selection responses and issue invitations for initial tenders. Report P57, 4.6

Carry out technical, commercial and legal dialogue, final tender evaluation, Cabinet approval and contract award notice by March 2027, then enter the development agreement targeted for 26 July 2027. Report P58, P59, 4.6

Finalise the Development Agreement and Heads of Terms via the Director of Place in consultation with the two named portfolio holders, with the Regeneration Programme Manager responsible for subsequent contract management. Report P3, P36, P37

The money

  • £120,000,000 Estimated investment by the development partner into Innovation Park Medway North Report P1, P84

Options considered

  • Rejected: Do nothing. Without a development partner IPM North will remain undelivered Report P44
  • Rejected: Use a framework or existing contract. Not suitable for a site of this scale, complexity and value Report P45
  • Rejected: Open (single stage) procedure under the Procurement Act 2023. Single stage with no shortlisting, specification must be fixed at start, and very limited dialogue with bidders Report P5, P7, P46, P50
  • Chosen: Competitive flexible (multi-stage) procedure under the Procurement Act 2023. Allows shortlisting, dialogue and refinement of specification, appropriate for complex regeneration Report P8, P11, P51, P63, P64

Implications

  • Financial: Procurement costs were agreed by Cabinet in March 2025; the £120 million is partner investment, not Council capital, though a capital addition would be sought if that changed before award. Report 3.1, P82, P84
  • Financial: Failure to deliver the site would prevent the Council from receiving 100 percent retained business rates under the enterprise zone, which are intended to offset borrowing for enabling works. Report P83
  • Legal: External legal advisors have been appointed; the process complies with the Procurement Act 2023, Medway Council Contract Procedure Rules, the Local Government (Contracts) Act 1997 and the Localism Act 2011. Report P85, P86, P89, P90
  • Legal: The Council reserves the right to require a Parent Company Guarantee or other security, subject to bidders' financial standing assessment. Report 6.1, P68, P73
  • Equalities: No TUPE implications are identified. Report 11.3, P93
  • Climate: Sustainability is a key element of the development agreement with a minimum expectation of BREEAM very good, and climate change improvement is a contract KPI. Report 11.6, P99, P38
  • Risk: Key risks include inability to find a suitable partner, geopolitical and economic instability, planning or statutory delays, developer financial failure and programme delays affecting business rate receipts. Report P68, P70, P71, P72, P73, P75
  • Staffing: Procurement will be run by the Category Management team; subsequent contract management sits with the Regeneration Programme Manager. Report 7.3, P34, 7.4, P36

Who and where

  • Medway Council as landowner of Innovation Park Medway North Report 7.1, P30
  • Shortlisted and longlisted national commercial developers invited to tender, including three active in the Kent market Report 4.2, 4.4
  • Local supply chain, MSMEs, VCSEs and schools targeted through social value commitments in the tender Report 12.1, P103, P105
  • Council taxpayers, via retained business rates funding borrowing for enabling works Report P83

Timeline

  • 10 February 2026: Soft market testing brief sent to agreed shortlist of developers Report 4.2
  • 4 March 2026: Soft market testing extended to longlist of developers Report 4.2
  • 17 March 2026: Deadline for written soft market testing responses Report 4.2, P57
  • April 2026 to May 2026: Cabinet approvals and call-in period Report P57
  • 22 May 2026: Tender notice and associated tender documents to be published Report 4.6, P57
  • 22 June 2026: Participation period ends and evaluation of pre-selection questionnaire begins Report P57
  • 6 July 2026: Invitation for initial tenders issued Report P57
  • 1 September 2026: Initial proposals deadline Report P57
  • 24 September 2026 to 21 October 2026: Technical, commercial and legal dialogue Report P58
  • 11 December 2026: Invitation to Submit Final Tenders response deadline Report P58
  • February 2027: Targeted Cabinet approval of contract award Report 4.6, P58
  • 1 March 2027: Contract award decision and assessment summaries issued Report P58
  • 26 July 2027: Enter into development agreement Report P59

Plain English for the jargon

  • Procurement Act 2023 (PA23): UK law governing how public bodies award contracts, offering open and competitive flexible procedures.
  • Competitive flexible procedure: Multi-stage procurement process under PA23 allowing shortlisting, dialogue with bidders and refinement of the specification.
  • Open procedure: Single-stage tender under PA23 where any party can bid and the contract is awarded on published criteria, with no shortlisting.
  • Heads of Terms: Draft principles of the development agreement that will form part of the tender pack and basis of the final contract.
  • Development Agreement (DA): Contract under which the development partner delivers the site in line with the Council's masterplan.
  • Gateway 1: Initial procurement decision stage seeking approval to commence a procurement exercise.
  • BREEAM very good: A sustainability rating standard for buildings; a minimum of 'very good' is required on the site.
  • Parent Company Guarantee (PCG): Form of security a council may require from a parent company to underwrite a contractor's performance.
  • TUPE: Transfer of Undertakings (Protection of Employment) regulations; here confirmed as not applicable.
  • Enterprise zone: Designated area where the Council can retain 100 percent of business rates to offset borrowing for enabling works.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

77/2026 The Cabinet agreed to the procurement of a development partner for Innovation Park Medway North as per the preferred option identified in paragraph 8.4, under the competitive flexible procedure in accordance with the Procurement Act 2023; with a contract length of 7 years. 78/2026 The Cabinet agreed to the draft Heads of Terms within the Exempt Appendix 4 to the report and agreed to delegate authority to the Director of Place in consultation with the Portfolio Holder for Climate Change and Strategic Regeneration and the Portfolio Holder for Economic and Social Regeneration and Inward Investment to finalise and make any necessary amendments to the Development Agreement. Reasons: This exercise will be procured under the Procurement Act 2023 (PA23) which offers a choice of two procedures: The open procedure: a single stage tender procedure whereby any interested party can submit a tender and the Council would decide, on the basis of the published award criteria, to whom to award the contract. It is not possible under this procedure to shortlist / limit the number of suppliers who would receive the tender documents. This process maximises the number of suppliers that tender but is used for more straightforward purchases. Weaknesses of open procedure: (a) single stage approach means that bidders must prepare tenders without knowledge of the number of other bids/bidders, this can mean that bidders are unlikely to invest time and resource into the bid as the prospect of success is unknown resulting in no or poor quality bids; (b) the specification issued with the tender pack at the commencement of the process must be sufficiently clear and simple from the outset to allow bids to be submitted on a comparable basis. For major regeneration projects such as this Project, this is exceedingly difficult/impossible to achieve; and (c) there is extremely limited opportunity for dialogue with bidders during the tender process, there is no opportunity for the Council to help shape proposals to ensure it receives tenders which best meet its needs. The competitive flexible procedure can be a multi-staged process and does allow for a shortlisting stage (pre-qualification/pre-selection) to limit the number of suppliers receiving a tender. The procedure can be adapted to the Council's requirements so long as it complies with the basic requirements of the Procurement Act 2023. The Cabinet Office Guidance suggests that this procedure is most appropriate for more complex requirements. We consider that the Project falls within the definition of a complex requirement. Advantages of the competitive flexible procedure: (a) a multi-stage approach means ... view the full minutes text for item 8.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet

Summary

This report seeks permission to commence the procurement of a Development Partner and their estimated investment of £120,000,000 for Innovation Park Medway North (IPM N), and agreement to the proposed Head of Terms that will form part of the tender pack and form the basis of the future contract with the development partner.

1. Recommendations 1.1. The Cabinet is asked to: 1.1.1. agree the procurement of a development partner for Innovation Park Medway North as per the preferred option identified in paragraph 8.4;

1.1.2. agree the draft Heads of Terms within the Exempt Appendix 4 to the report and agree to delegate authority to the Director of Place in consultation with the Portfolio Holder for Climate Change and Strategic Regeneration and the Portfolio Holder for Economic and Social Regeneration and Inward Investment to finalise and make any necessary amendments to the Development Agreement. 2. Suggested reasons for decisions

2.1This exercise will be procured under the Procurement Act 2023 (PA23) which offers a choice of two procedures:

2.1.1. The open procedure: a single stage tender procedure whereby any interested party can submit a tender and the Council would decide, on the basis of the published award criteria, to whom to award the contract. It is not possible under this procedure to shortlist / limit the number of suppliers who would receive the tender documents. This process maximises the number of suppliers that tender but is used for more straightforward purchases.

2.1.2. Weaknesses of open procedure:

(a) single stage approach means that bidders must prepare tenders without knowledge of the number of other bids/bidders, this can mean that bidders are unlikely to invest time and resource into the bid as the prospect of success is unknown resulting in no or poor quality bids; (b) the specification issued with the tender pack at the commencement of the process must be sufficiently clear and simple from the outset to allow bids to be submitted on a comparable basis. For major regeneration projects such as this Project, this is exceedingly difficult/impossible to achieve; and (c) there is extremely limited opportunity for dialogue with bidders during the tender process, there is no opportunity for the Council to help shape proposals to ensure it receives tenders which best meet its needs.

2.1.3. The competitive flexible procedure can be a multi-staged process and does allow for a shortlisting stage (pre- qualification/pre-selection) to limit the number of suppliers receiving a tender. The procedure can be adapted to the Council's requirements so long as it complies with the basic requirements of the Procurement Act 2023. The Cabinet Office Guidance suggests that this procedure is most appropriate for more complex requirements. We consider that the Project falls within the definition of a complex requirement.

2.1.4. Advantages of the competitive flexible procedure:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gateway 1 Procurement Commencement: Innovation Park Medway NorthReport 224 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
VM
Councillor Vince Maple (Lab)Committee Member, present
TM
Councillor Teresa Murray (Lab)Committee Member, present
TC
Councillor Tracy Coombs (Lab)Committee Member, present
SC
Councillor Simon Curry (Lab)Committee Member, present
NG
Councillor Nina Gurung (Lab)Committee Member, present
HM
Councillor Harinder Mahil (Lab)Committee Member, present
AP
Councillor Alex Paterson (Lab)Committee Member, present
LP
Councillor Louwella Prenter (Lab)Committee Member, present
AP
Councillor Adam Price (Lab)Committee Member, apologies
ZV
Councillor Zoë Van Dyke (Lab)Committee Member, present

On this subject at Medway

Search all
  1. Gateway 1 Procurement Commencement: Innovation Park Medway NorthThis decision
  2. Gateway 1: Procurement of Housing Related Support ServicesAgreed
  3. Gateway 1 Procurement Commencement: Repairs and Maintenance for Temporary Accommodation Owned, One Medway Lettings, One Medway – Inspiring Change LA Hostels, Housing Revenue Account (HRA) Requirements, Medway Development Company (MDC) and the Sanctuary SchemeAgreed
  4. Gateway 1 Procurement Commencement: Innovation Park Medway South/Care for MedwayAgreed
  5. Gateway 3 Contract Award: Recycling Resource Management (RRM) ProcurementAgreed
  6. Gateway 1 Procurement Commencement: Medway Tunnel Lighting UpgradeAgreed

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open