Resolved
a) The Committee noted the results of the first round of capital budget monitoring for 2024/25. b) The Committee noted that Cabinet of 31 July 2024 were asked to approve a virement of £500,000 from the projected underspend on the scheme at Victory Academy to the Greenacre Academy scheme to cover a projected overspend on that scheme.