AI summaryMedway Cabinet noted the third round of 2025/26 capital budget monitoring, showing a £333.326million programme with a forecast £177,000 overspend, mainly from a school roofing overrun and a virement of £502,000 to cover enforcement cameras.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted budget changes since Round 2
Money£333.326million programme, £177,000 overspendApproved programme up from £229.722million at Round 2
What happens nextRound 4 monitoring reportNext round of capital budget monitoring to follow
Who it affectsCapital projects across schools, highways, regenerationIncludes several new school and infrastructure schemes
What was decided
Cabinet noted the results of the third round of capital budget monitoring for 2025/26.
Cabinet noted changes to the approved budget since Round 2 as set out in sections 10.1 to 10.2. Report 1.2
A virement of £502,000 from Integrated Transport LTP3 to the Enforcement Cameras scheme is to be requested to address the cameras overspend. Report P24, P25
Why
Full Council agrees the capital programme; Cabinet ensures expenditure stays within the approved programme and can instruct corrective action to prevent overspends. Report P7
The capital programme for 2025/26 has grown from £229.722million at Round 2 to £333.326million at Round 3 through new additions, while the forecast overspend has risen from £58,000 to £177,000. Report P10
The overspend is concentrated in Children and Adults, driven by the School Condition Programme roofing work overspending by £220,000, and is partly offset by small underspends in Basic Needs Secondary and SEND schemes. Report P11, P16, P17, P18
What happens next
The service will request a virement of £502,000 from the Integrated Transport LTP3 budget to the Enforcement Cameras scheme, where a £502,000 overspend is forecast. Report P24, P25
The £220,000 roofing programme overspend will be repaid from future Condition Programme grant, which will reduce the size of the 2026/27 programme. Report P17
Several major new schemes (East Hill primary, Strood Academy expansion, Danecourt secondary expansion, Chatham Grammar SEN, Care For Medway) are expected to progress into 2026/27 and beyond. Report P14, P16, P18, P20
The money
£333.326million Approved capital programme for 2025/26 at Round 3 Report P10
£229.722million Approved capital programme for 2025/26 at Round 2 Report P10
£177,000 Forecast overall overspend at Round 3 Report P10, P11
£21.399million Gun Wharf Improvement Works budget Report P29
£10.000million East Hill New Primary School new scheme Report P14
Options considered
Chosen: Note the results of the third round of capital budget monitoring for 2025/26. Cabinet responsibility to ensure expenditure remains within approved programme Report P7
Chosen: Note the changes to the approved budget since Round 2. Required to keep Cabinet aware of in-year programme movements including virements and additions Report 1.2, P8
Implications
Financial: Overall programme is forecast to overspend by £177,000 in 2025/26, up from £58,000 at Round 2, all within the Children and Adults directorate. Report P10, P11
Financial: A £502,000 virement from Integrated Transport LTP3 to Enforcement Cameras is to be requested to address the cameras overspend. Report P24, P25
Financial: The £220,000 roofing overspend will be repaid from future Condition Programme grant, reducing the 2026/27 programme. Report P17
Financial: Capital virements up to £2million can be approved by Cabinet; anything above requires Full Council. Report P8
Other: Several major new schemes have been added in Round 3, including East Hill primary, Strood Academy expansion, Danecourt secondary expansion, Chatham Grammar SEN, and Care For Medway. Report P14, P16, P18, P20
Who and where
Medway school pupils and families (new and expanded schools, SEND provision, co-ed adaptations) Report P14, P16, P18
Residents in areas affected by highways, lighting, active travel and country park schemes Report P24, P25, P27, P29
Adult social care users (new Care For Medway home on IPM Southern site) Report P20
Council tax payers and budget holders across directorates Report P7, P10
Contractors delivering the schemes (multi-site play, sports, building works) Report P28, P29
Timeline
10 February 2026: Cabinet meeting where Round 3 capital monitoring was noted Report P1
2025/26: Current financial year covered by the monitoring report Report P10
March 2026: Expected outcome of National Lottery Heritage Fund Stage 1 application for Dickens Chalet Restoration Report P28
April 2026: Expected full completion of Hoo Academy 6th Form external works Report P16
September 2026: Expected completion of co-ed adaptations at Chatham Grammar, Holcombe Grammar, Fort Pitt Grammar and Robert Napier extension Report P16
Spring 2026: Expected start of works at Hoo Sports Centre, Deangate Ridge and Maidstone Road Playzones, Town Hall Gardens, and play area sites Report P28, P29
2026/27: Design and start of construction for East Hill, Strood Academy expansion, New Road primary, Hoo St Werburgh, Danecourt secondary expansion, Chatham Grammar SEN, and Care For Medway Report P14, P16, P18, P20
2027/28 and 2028/29: Construction phases for East Hill, Hoo St Werburgh, Danecourt secondary expansion, and Care For Medway Report P14, P18, P20
Plain English for the jargon
Section 106 (S106): Developer contributions paid to the council to fund local infrastructure linked to a development
Prudential borrowing: Council borrowing for capital investment, repaid from future revenue budgets
Capital Grant: Government funding provided for specific capital projects
Virement: Transfer of budget from one scheme to another within the capital programme
RAAC: Reinforced Autoclaved Aerated Concrete, a lightweight building material
DfE: Department for Education
LTP3: Local Transport Plan 3, the council's transport strategy
LCWIP: Local Cycling and Walking Infrastructure Plan
RIBA stages: Royal Institute of British Architects work stages used to plan building projects
ATF: Active Travel Fund, government grant for walking and cycling schemes
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12
Resolved
The Cabinet noted the results of the third round of capital budget monitoring for 2025/26. The Cabinet noted the changes to the approved budget since Round 2 as set out in sections 10.1 to 10.2 of the report. Reasons: Full Council is responsible for agreeing the capital programme. The Cabinet is responsible for ensuring that expenditure remains within the approved programme, including instructing corrective action to prevent any forecast overspend from materialising.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
Cabinet 10 February 2026 Capital Budget Monitoring – Round 3 2025/26 Portfolio Holder: Councillor Vince Maple, Leader of the Council
Report from: Phil Watts, Chief Operating Officer (Section 151 Officer)
Author: Andy McNally-Johnson, Head of Corporate Accounts
Summary This report presents the results of the third round of the Council’s capital budget monitoring process for 2025/26.
1. Recommendations 1.1. The Cabinet is asked to note the results of the third round of capital budget monitoring for 2025/26.
1.2The Cabinet is asked to note the changes to the approved budget since Round 2 as set out in sections 10.1 to 10.2 of the report below.
2. Suggested reasons for decisions 2.1. Full Council is responsible for agreeing the capital programme. Cabinet is responsible for ensuring that expenditure remains within the approved programme, including instructing corrective action to prevent any forecast overspend from materialising.
3. Budget and policy framework 3.1. The Cabinet is responsible for ensuring that capital expenditure remains within the budget approved by Council. Where required, the report will give details relating to additional schemes (capital additions) or movements in budgets between schemes (virements). Capital virements of up to £1million can be approved by the Chief Executive and Directors, capital virements up to £2million can be approved by Cabinet with anything above that being reported to Full Council for decision.
3.2The Chief Operating Officer has delegated authority to approve in year additions to the capital programme, in consultation with the Finance Portfolio Holder, subject to the following criteria: • funding coming from external sources, to be used for a specific purpose on a specific asset, • no financial contribution coming from the Council, • funding being ringfenced for specific purposes. • Any additions made under delegated authority are reported through the next budget monitoring report.
4. Summary Capital Budget Position 2025/26 4.1. The approved capital programme for 2025/26 as at Round 3 is £333.326million (£229.722million at Round 2). Table 1 below summarises the capital programme and Round 3 forecast position showing a projected overspend of £177,000 (£58,000 overspend as at Round 2). Table 2 details how the approved programme will be funded.
Table 1: Round Three Capital Monitoring Summary Forecast Total Total Forecast Forecast Spend Directorate Approved Expenditure Remaining Spend (Under)/ in Future Cost to 31/03/25 Budget 2025/26 overspend Years £000 £000 £000 £000 £000 £000 Children and Adults (including 140,738 23,116 117,622 14,898 102,901 177 Public Health) Regeneration, Culture and 346,311 190,663 155,853 88,115 67,739 0 Environment Housing Revenue Account 103,481 43,768 59,713 27,580 32,133 0 Business Support Department 2,458 2,320 138 138 0 0 Total 592,989 259,867 333,326 130,731 202,772 177
Table 2: Funding the Capital Budget Funding Source Total C&A RCE HRA BSD £000 £000 £000 £000 £000 Capital Grants 95,689 55,920 36,989 2,780 0 Developer Contributions 5,757 481 5,276 0 0 Capital Receipts 2,223 0 2,088 0 135 RTB Receipts 1,000 0 0 1,000 0 Revenue / Reserves 19,919 0 304 19,615 0 Borrowing 208,738 61,222 111,195 36,319 3 Total 333,326 117,622 155,853 59,713 138 5. Children and Adults 5.1. The Children and Adults programme is forecast to overspend by £0.177million against the approved budget of £117.622million as set out below.
Forecast Total Total Forecast Spend Total Approved Exp to Remaining Spend in Future Scheme Cost 31/03/25 Budget 2025/26 Years Variance Basic Needs - Primary 20,102 645 19,458 508 18,950 0 Basic Needs - Secondary 20,540 5,154 15,386 6,504 8,844 (38) School Condition Programme 7,242 6,574 668 887 0 220 Schools Devolved Capital 117 0 117 117 0 0 Basic Needs - SEND 47,028 10,432 36,596 5,261 31,330 (5) Children’s Social Care 1,432 175 1,257 980 277 0 Adult Social Care 44,278 136 44,141 641 43,500 0 Children and Adult Services Total 140,738 23,116 117,622 14,898 102,901 177
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.