AI summaryMedway Cabinet notes annual update on Gun Wharf Improvement Programme, with main contractor appointed and 55+ council teams relocated ahead of refurbishment works starting in June 2026.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted the contents of the annual update
Money£22,263,266Total budget for the Gun Wharf refurbishment programme
What happens nextRefurbishment works start June 2026Apex Contractors to start on Levels 3 to 5, aiming to open by February 2027
Who it affectsCouncil staff and residentsOver 55 council teams relocated; Level 2 remains open without public access
What was decided
Cabinet noted the contents of the annual update on the Gun Wharf Improvement Programme. Report P4
The decision sits within the existing governance split: Full Council agrees capital additions, while Cabinet oversees delivery through quarterly monitoring. Report P5
Why
The programme was triggered by the discovery of RAAC planks in the roof space during an October 2023 structural inspection, forcing reduced usable capacity at the council's headquarters. Report P7, 4.2
The scope has broadened beyond RAAC remediation to a full refurbishment and redesign intended to extend the building's life by 40+ years and support the council's 'Employer of Choice' aim. Report 4.5, 4.6, 4.7
What happens next
Apex Contractors Ltd is to commence main refurbishment works on Levels 3, 4 and 5 by the start of June 2026, with these floors targeted to open by February 2027. Report P40
Refurbishment of Level 2 and basement (Level 1) is then scheduled for completion by the end of 2027, with the building operational for new ways of working in 2027. Report P40, P74
The GWIP Board will continue monthly reporting into the Corporate Landlord Board, with risks tracked on delays, health and safety, budget control, democratic services, staff engagement and LGR uncertainty. Report 4.4, P53, P54, P55, P56, P57
The money
£22,000,000 Capital additions request agreed by Cabinet 13 February 2024 and Full Council 29 February 2024 for the refurbishment of Gun Wharf Report P6
£263,266 Budget virement from the Council Meeting Facilities scheme approved by the Director of Place in November 2024 Report P6
£22,263,266 Total scheme budget after virement, covering main refurbishment, professional fees, specialist surveys and transition costs Report P6, P66
Implications
Financial: Inflation, unforeseen site conditions and wider geopolitical disruption could drive cost increases or require scope reprioritisation against the £22,263,266 budget. Report P55, P66
Legal: Some permanent changes to where staff are contracted to work will require consultation as a change to terms of employment, and several lease and licence agreements have been signed under tight timeframes. Report 10.2, 10.3
Equalities: Engagement with the Equalities Board and staff forums is informing inclusive wayfinding, welfare facilities, accessibility and technology choices. Report P43
Climate: A 'fabric first' refurbishment design is intended to cut operational energy use and support Medway's carbon neutral by 2050 target, with biodiversity and biophilic design also being considered. Report 8.3, 8.4, 8.5
Risk: Identified risks include programme delays, health and safety during construction, budget control, disruption to democratic services, staff disengagement during decant, and uncertainty from Local Government Reorganisation. Report P53, P54, P55, P56, P57
Staffing: Over 55 council teams have been relocated to alternative sites, with Level 2 at Gun Wharf retained without public access and a temporary staff reception at the riverside entrance. Report P27, P28, P29
Who and where
Over 55 council teams relocated to sites including Chatham Maritime, Strood Sports Centre, the Innovation Centre, Pender House, Kingsley House, Broadside, Deangate Ridge and various leisure sites Report P27, P28, P30, P31, P32, P33, P35, P36
Council Members and democratic services, due to possible disruption to formal meetings during refurbishment Report P55
Residents, who will be redirected from Gun Wharf to Community Hubs for front-line services during the works Report P29, P74
Ministry of Justice and Kyndi Ltd as third party partners based in Gun Wharf Report P43
Timeline
October 2023: Structural inspection identifies RAAC planks in the roof space Report P7
13 February 2024: Cabinet agrees capital additions request of £22,000,000 for the refurbishment Report P6
29 February 2024: Full Council agrees the capital additions Report P6
September 2024: Gun Wharf Improvement Programme Board set up Report 4.3
November 2024: Director of Place approves £263,266 virement from Council Meeting Facilities scheme Report P6
November 2025: Corporate Landlord Board recommends to Cabinet that Level 3 also be decanted Report P27
January 2026: Gun Wharf Transformation Officer appointed; Kyndi Ltd moves into the new CCTV Monitoring Hub Report P22, P39
March 2026: Extensive RAAC remedial work completed Report P38
7 April 2026: Cabinet approves appointment of Apex Contractors Ltd as principal building contractor Report P40
End of May 2026: Detailed planning for temporary relocation of services scheduled to conclude Report P27
11 May 2026: Meetings ordinarily held on Level 3 relocated to alternative venues Report P25
June 2026: Essential roof and gulley maintenance works scheduled to complete Report P38
Start of June 2026: Principal contractor scheduled to commence works on Levels 3, 4 and 5 Report P40
2 June 2026: Cabinet notes the second annual GWIP update Report P4
February 2027: Target for Levels 3, 4 and 5 to reopen Report P40
End of 2027: Target for Level 2 and basement (Level 1) refurbishment to complete Report P40
Plain English for the jargon
RAAC: Reinforced Autoclaved Aerated Concrete, a building material used from the 1950s to 1990s, identified in Gun Wharf's roof space
GWIP: Gun Wharf Improvement Programme, the programme board set up in September 2024 to oversee the refurbishment
CLB: Corporate Landlord Board, the non-statutory senior officer group that sponsors the GWIP Board
LGR: Local Government Reorganisation, identified as an external factor the refurbishment design must accommodate
HRA: Housing Revenue Account, in the context of Landlord Services and Property & Development Service based at Gun Wharf
RIBA Stage: Stages of the Royal Institute of British Architects' plan of work; the programme is moving from RIBA Stage 3 to Stage 4 design
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6
Resolved
The Cabinet noted the contents of the report. Reasons: Full Council is responsible for agreeing to make additions to the Capital Programme and Cabinet is responsible for ensuring effective Capital Programme Delivery through Quarterly Capital Budget Monitoring Reports.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
Cabinet 2 June 2026 Gun Wharf Improvement Programme Annual Update Report Portfolio Holder: Councillor Zoë Van Dyke, Portfolio Holder for Business Management
Report from: Adam Bryan, Director of Place Sunny Ee, Assistant Director for Regeneration
Authors: Dan Stone, Strategic Service Manager - FM & Capital Projects Matt Pinder, Programme Manager for Gun Wharf Improvement Programme Summary This report provides an update of all activities of the Gun Wharf Improvement Programme (GWIP) Board over the last 12 months since the last Cabinet update on 3 June 2025. This is the second annual update in the programme cycle.
1. Recommendation 1.1. The Cabinet is asked to note the contents of this report.
2. Suggested reasons for decisions 2.1. Full Council is responsible for agreeing to make additions to the Capital Programme and Cabinet is responsible for ensuring effective Capital Programme Delivery through Quarterly Capital Budget Monitoring Reports.
3. Budget and Policy Framework 3.1. A capital additions request for £22,000,000 for the refurbishment of Gun Wharf was agreed at Cabinet on 13 February 2024, followed by Full Council agreement on 29 February 2024. A budget virement of £263,266 from the Council Meeting Facilities scheme was also approved by the Director of Place in November 2024, leaving a total budget for this scheme of £22,263,266.
4. Background 4.1. Following a structural inspection of Gun Wharf in October 2023, Reinforced Autoclaved Aerated Concrete (RAAC) planks were identified within the roof space. The use of RAAC as a building material used during the 1950s to 1990s is well documented and was subject to Central Government advice.
4.2Following guidance available at the time, the Council was forced to trigger its Business Continuity Management Plan(s) resulting in a reduced usable capacity at Gun Wharf.
4.3The Gun Wharf Improvement Programme (GWIP) Board was set up in September 2024 and is quite established. The Board is made up of senior officer representation from the Capital Projects Team, Financial and Business Improvement (including Technology), HR (People) and Communications. The Board is chaired by the Assistant Director of Regeneration, who also acts as the Corporate Programme Champion.
4.4In terms of governance, the Gun Wharf Improvement Programme (GWIP) Board has the delegated authority to drive the day-to-day delivery of the programme and reports into the Corporate Landlord Board (CLB). Both boards meet monthly. The CLB acts as the sponsoring group. The CLB is a non-statutory cross-cutting Senior Officer Board that discharges corporate landlord functions on behalf of the Authority in accordance with corporate priorities; the relevant Director or Assistant Director uses their delegated authorities.
4.5Although the programme came about due to the discovery of RAAC in Gun Wharf, the scope has evolved beyond the remediation and repair of the building. To note, no substantial repairs or refurbishment have been carried out since its opening in the late seventies, and it is well overdue on works that will ensure another 40+ years of effective operation. The scope now encompasses our aspirations of redesigning the interior and changing the way that we work and are perceived as an employer, including our aspiration to become an ‘Employer of Choice’ in an ever more competitive and dwindling recruitment pool for local authorities across the country.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.