Medway Council
Cabinet, Tuesday 7 April 2026 at 7.00pm

Gateway 3 Contract Award: Gun Wharf Building Refurbishment Works

Agreed Executive 1 paper

AI summaryMedway Cabinet awards Apex Contractors Ltd. the £14,995,041 contract to refurbish Gun Wharf council offices, funded by a £22,263,266 capital budget addition.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedPrincipal Contractor for Gun Wharf refurbishment works
Money£14,995,041Contract sum; £22,263,266 added to capital budget
What happens next8 working-day standstill periodBefore contract award, with 30-day claim window
Who it affectsNot stated

What was decided

Cabinet agreed to award the Principal Contractor contract for the refurbishment of Gun Wharf to Apex Contractors Ltd. for £14,995,041, following their evaluation as the most advantageous tender against the Council's award criteria. Report 1.1

The contract will be a JCT contract; a parent company guarantee or performance bond was waived at Gateway 1 because the JCT contract includes a stated retention release clause. Report 3.4, P22

Why

Apex Contractors Ltd. provided a robust response to all questions, demonstrating excellent understanding of the specification and expected outcomes. Evaluators agreed the bid was well written, with clear, concise answers evidencing additional value and innovation over the contract length. Report 2.1

The refurbishment aligns to the One Medway Council Plan and supports the Council's net zero by 2050 target through sustainable design and energy-efficient infrastructure. Report 2.2, 3.3, P18, P19

What happens next

Following Cabinet approval, bidders (including those who did not apply) have an 8 working-day standstill period to appeal, and a 30-day claim window from when they ought to have known, to challenge the procurement process.

The GWIP Team and a dedicated Technology Workstream Lead will work closely with ICT colleagues to manage technology matters during the construction phase. Contract management will sit with the Capital Projects Programme Manager and the Head of FM & Capital Projects. Report 6.4, P48, P49, 4.4, P34

The money

  • £14,995,041 Contract sum awarded to Apex Contractors Ltd. for Gun Wharf refurbishment Report 1.1
  • £22,263,266 Addition to the capital budget approved by Full Council on 29 February 2024 to fund the procurement requirement and delivery Report P38

Options considered

  • Chosen: Award contract to Apex Contractors Ltd. at £14,995,041. Evaluated as the most advantageous tender; robust, well-written bid showing excellent specification understanding and added value and innovation Report 1.1, 2.1
  • Rejected: Tender at full RIBA Stage 4. Would have produced an unworkable construction period of 15 weeks plus Report P25
  • Rejected: Tender at RIBA Stage 3. Discounted due to inherent cost uncertainty of an evolving technical design and risk of post-award variations Report P24
  • Rejected: Complete remaining design during the tender period. Carried a risk of cost increases if design issues emerged post-tender; managed instead through contingency allowances and change control Report P26

Implications

  • Financial: Delivery of the procurement requirement will be funded through an addition of £22,263,266 to the capital budget approved by Full Council on 29 February 2024. Report P38
  • Legal: Procurement Board approved the award on 5 March 2026, confirming the process complied with council procedures and legislative requirements. Bidders have an 8 working-day standstill and a 30-day claim window to challenge.
  • Risk: The procurement is classified as high risk. Risks rated BIII, BII, CIII and CIV include unforeseen building fabric issues, programme slippage, staff decant delays, poorly controlled value engineering, and reputational risk from unclear communications. A contract contingency is included within the agreed sum to manage unforeseen issues. Report P20, P35
  • Legal: Tendering at RIBA Stage 4a meant some specification needed more detail to follow from engagement with the appointed contractor, increasing risk associated with price, timelines, outcomes and quality. About 360 clarifications and roughly 30 tender documentation amendments were made during the process, increasing the potential risk of procurement challenge. Report P42, P43, P44
  • Climate: The GWIP supports the Council's net zero by 2050 target through sustainable design and energy-efficient infrastructure, and will replace windows and doors to improve thermal efficiency and environmental performance. Report P19, P14
  • Staffing: Refurbishment aims to transform working culture, support the Council's ambition to be an Employer of Choice, and provide a more flexible office floorplate. Staff decant arrangements are in place with phased works and skeleton staff presence on Levels 2. Report P8, P35
  • Equalities: Works will improve accessibility for all users, create a flexible space convertible into a Council Chamber, deliver a self-service café, and replace toilet and welfare facilities to support inclusivity. Report P11, P12
  • Other: TUPE does not apply to this activity. Report 6.3, P46

Who and where

  • Council staff based at Gun Wharf, who will be decanted in phases to alternative accommodation Report P35
  • Members of the public and building users, including those attending future Council Chamber meetings Report P11
  • ICT and Facilities Management teams, including the Capital Projects Programme Manager and Head of FM & Capital Projects who will manage the contract Report 4.4, P34, 6.4, P48
  • The Ministry of Justice (MoJ) area and CCTV Monitoring Hub within Gun Wharf, whose existing improvements Phase 2 will complement Report P13

Timeline

  • October 2023: Reinforced autoclaved aerated concrete (RAAC) discovered in Gun Wharf, leading to the Gun Wharf Improvement Programme (GWIP) Report P7
  • 29 February 2024: Full Council approved the capital budget to which £22,263,266 was added for this project Report P38
  • Prior to Invitation to Tender: GWIP team published a Prior Information Notice and undertook market engagement at the South East Construction Expo Report P24
  • 5 March 2026: Gateway 3 report presented to Procurement Board, which approved the award subject to caveats for Cabinet consideration
  • 7 April 2026: Cabinet decision to award the contract to Apex Contractors Ltd. for £14,995,041

Plain English for the jargon

  • RAAC: Reinforced Autoclaved Aerated Concrete, a lightweight building material identified in Gun Wharf in October 2023 that triggered the improvement programme
  • GWIP: Gun Wharf Improvement Programme, the overarching programme covering remediation, refurbishment and redesign of Gun Wharf
  • JCT: Joint Contracts Tribunal, a standard form of building contract used for this procurement, which includes a stated retention release clause
  • RIBA Stage 3 and Stage 4: Royal Institute of British Architects design stages. Stage 3 coordinates design spatially and technically; Stage 4 develops fully detailed technical information, specifications and construction-ready drawings. The project was tendered at an enhanced 'RIBA 4a' between the two
  • Open ITT: Open Invitation to Tender, the procurement procedure used, compliant with the Procurement Act 2023 and Medway Council's Contract Procurement Rules
  • MAT: Most Advantageous Tender, the basis on which tenders were evaluated
  • M&E: Mechanical and Electrical works, included to replace failing elements across the building
  • CAI: Contract Administrator's Instructions, used alongside RFIs for formal change control during the contract
  • TUPE: Transfer of Undertakings (Protection of Employment) regulations. The report confirms TUPE does not apply to this activity
  • GWIP Programme Priority Hierarchy: A prioritisation framework used for decisions, with Priority 1 denoting highest importance and Priority 5 the lowest
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

70/2026 The Cabinet agreed to award the contract for the refurbishment of Gun Wharf to Apex Contractors Ltd. for the sum of £14,995,041, understanding that they had been evaluated as the most advantageous tender against the Council’s award criteria, as per the evaluation spreadsheet contained wit hin Exempt Appendix 1 to the report. Reasons: Apex Contractors Ltd overall provided a robust response to all the questions, which demonstrated they have an excellent understanding of the specification and expected outcomes for Gun Wharf. Evaluators all agreed that their bid was well written, with clear and concise answers that evidenced additional value and innovation over the length of the contract.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet

Summary

This report seeks permission to commence with the award of the contract for the Principal Contractor for the refurbishment of Gun Wharf (Council Office).

Recommendation

1.1It is recommended that the Cabinet agrees to award the contract for the refurbishment of Gun Wharf to Apex Contractors Ltd. for the sum of £14,995,041, understanding that they have evaluated as the most advantageous tender against the Council’s award criteria as per the evaluation spreadsheet contained within the Exempt Appendix to the report. 2. Suggested reasons for decision

2.1Apex Contractors Ltd overall provided a robust response to all the questions, which demonstrated they have an excellent understanding of the specification and expected outcomes for Gun Wharf. Evaluators all agreed that their bid was well written, with clear and concise answers that evidenced additional value and innovation over the length of the contract.

2.2The refurbishment of Gun Wharf aligns to the One Medway Council Plan.

3. Background Information

3.1Refurbishment Scope and Objectives

3.1.1. Whilst this Gun Wharf Improvement Programme (GWIP) came about due to the discovery of reinforced autoclaved aerated concrete (RAAC) in Gun Wharf back in October 2023, the scope has evolved beyond the remediation and repair of the building. The scope has evolved to encompass aspirations to redesign the interior of the building and transform the way the Council works, supporting Medway Council’s ambition to be recognised as an Employer of Choice.

3.1.2. This is as an opportunity for us to ‘reset’ our working environment, evolving the culture and attitude towards Gun Wharf as our headquarters, looking at more creative, and innovative spaces in the building. We want to provide good conditions for our staff and drive productivity with a building we can all be proud of.

3.1.3. The overriding priority within the programme is to ensure that the building is safe and fit for purpose. This includes an element of future proofing, so that we are not only addressing the building’s current issues, but also proactively managing works and investing in improvements that will ensure the building’s longevity after it is handed back for full operations.

3.1.4. The works will comprise the full refurbishment of all floors within Gun Wharf, improving safety, compliance and accessibility. Delivery will be phased, with Phase 1 covering Levels 3, 4 and 5, followed by Phase 2 covering Level 2 and the basement (Level 1).

3.1.5. The works refurbishment package will deliver a more welcoming and accessible reconfigured reception both front of house and to the rear vastly improving the flow around the building. The works will also include improved accessibility for all users, a flexible space capable of conversion into a Council Chamber of sufficient capacity to accommodate Local Government Reorganisation, whilst able to be easily adapted to create hot desks and team working opportunities when not in use as a chamber.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gateway 3 Contract Award: Gun Wharf Building Refurbishment WorksReport 324 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 16 attended
VM
Councillor Vince Maple (Lab)Committee Member, present
TM
Councillor Teresa Murray (Lab)Committee Member, apologies
TC
Councillor Tracy Coombs (Lab)Committee Member, apologies
SC
Councillor Simon Curry (Lab)Committee Member, present
NG
Councillor Nina Gurung (Lab)Committee Member, present
HM
Councillor Harinder Mahil (Lab)Committee Member, present
AP
Councillor Alex Paterson (Lab)Committee Member, present
LP
Councillor Louwella Prenter (Lab)Committee Member, present
AP
Councillor Adam Price (Lab)Committee Member, present
ZV
Councillor Zoë Van Dyke (Lab)Committee Member, present
RH
Richard HicksOfficer, in attendance
AB
Adam BryanOfficer, in attendance

All 16 on the meeting page

On this subject at Medway

Search all
  1. Gateway 3 Contract Award: Gun Wharf Building Refurbishment WorksThis decision
  2. Gateway 3 Contract Award: for the Pre-Construction and Design Development for the Danecourt Secondary New Build ProjectAgreed
  3. Gateway 3 Contract Award: Medway All Age Service (Substance Misuse)Agreed
  4. Gateway 1 Report: Highways Infrastructure ContractAgreed
  5. Gateway 3 Contract Award: Advocacy for Parents with Children in or on the Edge of CareAgreed
  6. Gateway 3 Contract Award: Recycling Resource Management (RRM) ProcurementAgreed

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies