Resolved
RESOLVED That Cabinet agrees the recommendation of the Steering Group as set out in detail at Point 6 of the report.
Cabinet agreed this item on Wednesday 13 June 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That Cabinet agrees the recommendation of the Steering Group as set out in detail at Point 6 of the report.
To inform Members about the outcomes of Phase 1 of the South East Wales Shared Services Project and to agree the recommendations to proceed to the next phase.
1.0INTRODUCTION AND BACKGROUND
1.1The Connecting South East Wales Board, comprising Leaders and Chief Executives of the ten Local Authorities in South East Wales, agreed a project to investigate the potential for sharing various “back-office” functions, with a view to releasing resources to invest in frontline services.
1.2The project has been part-funded by the Local Authorities in South East Wales, who have committed £100,000 in total plus staff resources in kind (approximately £113,670 to the end of February 2007). It has also received a grant of (£135,800) from the Making the Connections fund in the Welsh Assembly.
1.3The project is due to be completed by September 2007 and is divided into three stages: -
• Phase 1 - To develop a Strategic Outline Case (SOC) examining seven functional areas with a view to sharing: Payroll and HR; Training; Council Tax and NNDR; Internal Audit; Procurement; ICT; and Debt Recovery
• Phase 2 - To develop an Outline Business Case for services with the greatest potential for sharing.
• Phase 3 - To produce an Outline Implementation Plan for consultation. 1.4 The project is being overseen by a Steering Group, comprising senior managers from the ten authorities and the WLGA. The Steering Group has procured PricewaterhouseCoopers LLP (PwC), a consultancy with a background knowledge and expertise in shared services, to help with the feasibility study.
1.5Cross-cutting functional groups of Local Authority Officers and Directors of HR and Finance have been involved in discussions as the project has progressed. In addition, “Visioning Workshops” have been held with key officers and Members in all Authorities and update reports have been sent to Council Cabinets and Executives. The Connecting South East Wales Board has been regularly informed of progress.
1.6The project is now approaching the end of Phase 1. A copy of the Executive Summary and conclusions from the first phase of the Feasibility Study (Strategic Outline Case) prepared by PwC has been placed in the Members’ Library for information.
2.0BENEFITS IDENTIFIED TO DATE
2.1A full Lessons Learned Review will be carried out at the end of the project but the Steering Group have already identified a number of benefits that have emerged as a result of the work carried out in Phase 1. These include:
• Recognition of successful shared service relationships and best practice methodology currently undertaken by LA’s. All authorities have existing collaborations that share services. The project has reiterated the ability of LA’s to work with and alongside each other effectively, producing excellent achievements.
• Improved communications between colleagues, counterparts and LA’s through various methods. The project has provided invaluable opportunities to meet and network with representatives from other LA’s. These relationships developed, or furthered, have already extended beyond the project.
• Challenges to current status quos within councils. The project has highlighted areas within LA’s where efficiencies, and better practice, can be addressed. Data gathered and compared has given opportunities to evaluate current working methods, beyond the scopes and service areas of this project.
• Embedding of staff skills in the Shared Service sphere that can be utilised in further projects and data gathering exercises.
3.0STRATEGIC OUTLINE CASE - FINDINGS
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
South East Wales Shared Services Project: Recommendations from Phase 1Report | 7 pages | DownloadRead as text |
Follow Cabinet at Merthyr Tydfil and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | The Tobacco and Vapes Act 2026 - Scheme of DelegationResolved that: 2.1 Approve the inclusion of the Tobacco and Vapes Act 2026 within the Council's Scheme of Delegation.... | Approved | Open |
| 22 Oct 2026 | Annual Equality Report 2025-2026Resolved that: 2.1 The Council’s Annual Equality Report for 2025-2026 be approved for publishing. | Approved | Open |
| 22 Oct 2026 | Bright Futures Education Strategy 2026 - 2030Resolved that: 2.1 The Bright Futures Education Strategy 2026-2030 (Appendix 1) be discussed and noted prior to Full ... | Noted | Open |
| 22 Oct 2026 | Greenfield Special School - Satellite ProvisionResolved that: 2.1 The use of the vacated former St Mary’s Primary School site as an interim solution for Greenfield ... | Approved | Open |
| 22 Oct 2026 | Provisional Capital Outturn Report 2025/26Resolved that: 2.1 The provisional Capital Outturn position for the 2025/26 financial year be noted. 2.2 The budget a... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.