RESOLVED That Cabinet grant an exemption in accordance with the contracting and procurement regulations. That Cabinet authorise to award the remedial contract to Four-Sure Construction Ltd for the value of £500,000. That any further works required are considered when the capital programme priorities are determined.
Word for word from the decision Merthyr Tydfil published for this meeting.Source: democracy.merthyr.gov.uk
2.1Following a report commissioned by the Head of Estates, which showed that some £1.5 million was needed to be spent on maintenance, some £500k was allocated to start to address the backlog maintenance. Work has been ongoing with consultants Design Management Partnership (DMP) to prioritise the repairs required to prevent water ingress through the roof and castellations. Preventing such should have maximum impact in terms of keeping the school and museum operational and prevent further deterioration of the structure.
2.2Given the nature of the works it is very difficult to arrive at a precise specification to tender, as the extent of works will depend to some degree on what is found when opening up works are undertaken. 2.3 It has been possible to determine that works can be undertaken with the contract sum that will have significant impact on water ingress. The contract will have a duration of some 16 weeks. Schedules of works priced and provisional have been prepared and rigorous cost measures will also be in place during the contract.
2.4Given the nature of the work required it is imperative that the works are undertaken over as much of the summer period as possible. It is also due to the type of work required, preferable in the Head of Estates opinion, that a nominated contractor is utilised rather than going through competitive tender in accord with procurement regulations.
2.5In this respect DMP have worked closely with Four-Sure Construction Ltd on a number of similar contracts and have recommended them for quality of work and lack of claim culture.
2.6Four-Sure are on Constructionline and have undertaken works for various public sector bodies including Pontypridd and Rhondda Health Trust and Cardiff County Council.
2.7Financial checks by the COFARM suggests that the award limit of any contract should be £150k. As such should Cabinet agree with the appointment of Four-Sure then the works would be awarded in 3 separate contracts.
2.8As stated above, procurement regulations would normally provide for work of this contract sum to be awarded by competitive tender. However, provision exists in the regulations for this requirement to be waived by Cabinet.
2.9The Head of Estates has little doubt that should the proposed works not be undertaken over the summer period, then it is highly probable that the school will at times over the next winter period have to close for at least short periods. The chances of a more serious event requiring emergency relocation of the school are less likely but still high if we experienced a particularly inclement period of weather. Whilst the works, because of their still limited nature against the overall backlog, will not guarantee in absolute terms that the above action will not be required, it will significantly manage the risk of such.
Financial implications
3.1The financial implications as are described within the body of this report.
Recommendations
4.1That Cabinet:
1. Grant an exemption in accordance with the Contracting and procurement regulations. 2. Authorise the award the remedial contract to Four-Sure Construction Ltd for the value of £500,000. 3. Any further works required are considered when the Capital programme priorities are determined. GARETH CHAPMAN DEPUTY CHIEF EXECUTIVE & DIRECTOR OF CUSTOMER CORPORATE SERVICES
INTERNAL REPORT CONSULTATION:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.