RESOLVED That Cabinet notes the contents of the report and supports the appointment of English Landscapes to implement the High Street Public Realm Enhancements in the sum of £1,949,260.19. That Cabinet extends the commission of Camlin Lonsdale to project manage and deliver the project, for a maximum increased fee of £91,071.37, subject to discussions about the clerk of works as noted in 2.10 of the report.
Word for word from the decision Merthyr Tydfil published for this meeting.Source: democracy.merthyr.gov.uk
To inform Members of the appointment of a contractor to undertake the High Street & Market Square Public Realm works and to extend Camlin Lonsdale consultant’s commission to project manage the implementation of the scheme.
1.0INTRODUCTION
1.1Members may recall that a report was presented to Cabinet on the 4th October 2006 seeking approval of the detailed design for the public realm enhancement scheme for High Street & Market Square by Camlin Lonsdale Consultants. Subsequently, on the advice of the project consultants, members endorsed a report on 7th March 2007, to secure the pre-order of granite stone, to avoid delays in the contract period and to utilise Heads of the Valleys Programme funding during the 2006/07 financial year.
1.2During the past few weeks United Utilities have progressed their advance phased programme of gas pipeline renewal along High Street, to tie-in with the main contract works, thereby avoiding further disruption at a later date.
2.0PUBLIC REALM IMPROVEMENTS
2.1The project has been developed by consultants Camlin Lonsdale and includes new high quality granite floorscape materials, street signage, seating, planting, public art and the creation and enhancement of public open spaces. The project will involve the removal of street clutter and the provision of new street lighting on buildings, with the aim of removing the proliferation of columns and street signage within the town centre.
2.2In developing the project to this stage, site surveys and investigations have been undertaken to ensure risks and hazards are minimised. This includes a comprehensive cellar survey, trail trenches to determine existing services and a property condition survey to be undertaken by the contractor to reduce all potential claims from third parties. Appendix 1 shows a risk register that has been identified in relation to the project.
2.3Following an OJEU pre-qualification assessment in November 2006, 16 contractors expressed an interest in undertaking the contract. These were assessed through a scoring matrix undertaken by the consultants that recommended a list of six contractors that were invited to submit tenders in April 2007.
2.4The budget for the scheme is £1,522,248 based on a cost model set out by Camlin Lonsdale. On the basis of this cost estimate, tenders were returned by 12.00 noon on Monday 14th May 2007 and were opened as follows:
2.5The two lowest tenders received have been assessed by independent quantity surveyors, Simon Fenton Partnership. It has been identified that the main reason for the inflated tender amounts are due to an underestimate in the costs of laying granite setts due to the difficult phasing of the works and site constraints.
2.6In order to deliver the scheme as originally intended, it is necessary to secure an additional £520,000. In this respect, consideration can be given to the Heads of the Valleys Programme for which funding is available this year to support town centre projects.
2.7As reported to Cabinet on 6th June 2006 on the Heads of the Valleys Strategy, Members resolved, inter-alia, to support the choice of Merthyr Tydfil as the preferred town centre for project implementation under the HoV Programme during the current financial year. Members also resolved that further reports would be presented to Cabinet in due course on potential projects for implementation within the initial 3 years of this programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.