Resolved
RESOLVED that Cabinet notes the content of the report and approves the appointment of Cowlin Construction to undertake the refurbishment works to Gurnos Shopping Centre in the sum of £2,150,427.07.
Cabinet approved this item on Wednesday 1 October 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that Cabinet notes the content of the report and approves the appointment of Cowlin Construction to undertake the refurbishment works to Gurnos Shopping Centre in the sum of £2,150,427.07.
To update members on the Gurnos Shopping Centre Regeneration project and to recommend the appointment of a contractor to undertake the works.
1.0INTRODUCTION
1.1A report was presented to Cabinet on the 5th September 2007 to support the appointment of Allen Construction Consultancy to provide the necessary Project Management, Quantity Surveyors, Architectural, Structural Engineering and Building Services to support the implementation of the Gurnos Shopping Centre Regeneration Project.
1.2Since this time detailed surveys and proposals have been developed and consultation has been undertaken with businesses in the shopping centre. In addition, the Estates Department has negotiated the relevant lease arrangements to enable the project to be fully implemented.
2.0SHOPPING CENTRE REFURBISMENT
2.1In developing the project to this stage, site surveys and investigations have been undertaken to ensure risks and hazards are minimised. This includes a comprehensive structural survey and asbestos survey. Appendix 1 shows a risk register that has been identified in relation to the project.
2.2In June 2008, 12 contractors were selected from Construction Line to express an interest in undertaking the contract, however only 4 contractors replied. These contractors were then invited to submit tenders by August 14th 2008.
2.3In the meantime, quotations were invited from the same contractors to undertake a Phase 1 programme of works that will assist in delivering the scheme and reduce the period of the main contract. These works include stripping out the tower block, removal of an external canopy and relocating 3G’s and a fish & chip shop. Cowlin Construction were awarded a contract to undertake these works which commenced on 26th August for a 5 week period. This phase was awarded under delegated powers as the total cost was £126,690.20.
2.4The initial budget for the main contract of £1.5m was based on a cost model developed by consultants who undertook the initial feasibility study for the redevelopment in June 2006. On the basis of this cost estimate, 2 tenders were returned and were opened as follows:
1. £2,150,427.07 2. £2,212,781.44
2.5The two tenders received have been assessed by Allen Consultancy and it has been identified that the main reason for the inflated tender amounts are due to an increase in construction costs since the cost model was developed and an underestimate in the security provision and site constraints associated with the contract.
2.6The Physical Regeneration Fund has allocated £1.5m towards the project, however in order to deliver the scheme as originally intended, it is necessary to secure an additional £800,000. In this respect, the Heads of the Valleys Programme approached to secure this additional funding, which has now been approved, and the project will feature in the emerging Holistic Area Regeneration Plan (HARP).
2.7Therefore it is recommended that the tender submitted by Cowlin Construction in the sum of £2,150,427.07 be accepted to undertake the implementation of the refurbishment works, in-accordance with the proposals developed by Allen Construction Consultancy.
2.8It is also intended, once the detailed work programme and phasing is known, to finalise a Communications Strategy which will set-out in detail how information and publicity on the project can best be disseminated to local businesses, users of the shopping centre and the local community.
3.1The Gurnos Shopping Centre Regeneration scheme is being funded through the WAG’s Physical Regeneration Programme, with additional funding being secured through the Heads of the Valleys Programme (HoV) for next year’s (2009/10) expenditure on the project.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Gurnos Town Centre Regeneration ProjectReport | 5 pages | DownloadRead as text |
Follow Cabinet at Merthyr Tydfil and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | The Tobacco and Vapes Act 2026 - Scheme of DelegationResolved that: 2.1 Approve the inclusion of the Tobacco and Vapes Act 2026 within the Council's Scheme of Delegation.... | Approved | Open |
| 22 Oct 2026 | Annual Equality Report 2025-2026Resolved that: 2.1 The Council’s Annual Equality Report for 2025-2026 be approved for publishing. | Approved | Open |
| 22 Oct 2026 | Bright Futures Education Strategy 2026 - 2030Resolved that: 2.1 The Bright Futures Education Strategy 2026-2030 (Appendix 1) be discussed and noted prior to Full ... | Noted | Open |
| 22 Oct 2026 | Greenfield Special School - Satellite ProvisionResolved that: 2.1 The use of the vacated former St Mary’s Primary School site as an interim solution for Greenfield ... | Approved | Open |
| 22 Oct 2026 | Provisional Capital Outturn Report 2025/26Resolved that: 2.1 The provisional Capital Outturn position for the 2025/26 financial year be noted. 2.2 The budget a... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.