RESOLVED That Cabinet 1. agrees that the existing lease of Donald Hope Library be surrendered and the Council take a new lease to develop the Cavendish House site to provide improved and efficient library facilities in the Colliers Wood area subject to final terms being agreed by the Director of Environment and Regeneration under his delegated authority. 2. replaces the existing capital scheme of £550,000 for Colliers Wood Library provision with a new scheme of £200,000. 3. agrees, subject to the authority of the Director of Environment and Regeneration, that a lease of temporary library facilities is taken on the main terms identified within the body of this report whilst the library site is developed.
Word for word from the decision Merton published for this meeting.Source: democracy.merton.gov.uk
Agenda Item 4 Committee: Cabinet Date: 8 June 2015 Wards: Colliers Wood Subject: Colliers Wood Library Development Lead officer: Simon Williams and Chris Lee Lead member: Councillor Nick Draper Contact officer: Anthony Hopkins Recommendations: 1. That Cabinet agree that the existing lease of Donald Hope Library be surrendered and the Council take a new lease to develop the Cavendish House site to provide improved and efficient library facilities in the Colliers Wood area subject to final terms being agreed by the Director of Environment and Regeneration under his delegated authority. 2. That Cabinet replace the existing capital scheme of £550,000 for Colliers Wood Library provision with a new scheme of £200,000. 3. That Cabinet agree, subject to the authority of the Director of Environment and Regeneration, that a lease of temporary library facilities is taken on the main terms identified within the body of this report whilst the library site is developed.
1 PURPOSE OF REPORT AND EXECUTIVE SUMMARY 1.1. This report provides recommendations on how library services can be improved in the Colliers Wood area whilst delivering ongoing efficiencies in the way services are provided. 1.2. The current library provision in Colliers Wood (Donald Hope Library) is leased from Urb Group Property Development. The lease is due to expire in May 2017. Since acquiring the building in May 2014 Urb Group have been actively seeking to develop the Cavendish House site in order to provide new and improved library facilities along with additional housing and retail accommodation. 1.3. The development proposal was approved at Planning Committee on 26 March 2015 subject to Section 106 obligation or any other enabling agreement. This report outlines the timeframes involved in the construction, what the new facilities will consist of and proposals for temporary library facilities during the interim.
2 DETAILS 2.1. Work is scheduled to begin on construction of the Cavendish House site in summer 2015. The new library facilities will be spread over 3 levels and will consist of significantly increased community facilities, improved floor space and services. The library will also have within it coffee shop facilities.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Morden Town Centre RegenerationCabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a developme...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.