That Cabinet agrees that: 1) two options for a shared approach are followed up in detail: i ) a traditional shared service where one of the Councils is the employing authority, and ii) a shared service provided through a shared delivery company 2) a full business case recommending the best delivery model is agreed through a Joint Member Board with Sutton and Kingston and presented to members by September 2016. Details of the financial figures will emerge as the result of developing options (a) and (b) in more detail. It was noted that the benefits of adopting a shared approach include: delivery of more resilient services; the ability to compete with the private sector as the market opens up; improvement in the quality of services; financial savings and income growth. That Cabinet agrees that: 1) two options for a shared approach are followed up in detail: i ) a traditional shared service where one of the Councils is the employing authority, and ii) a shared service provided through a shared delivery company 2) a full business case recommending the best delivery model is agreed through a Joint Member Board with Sutton and Kingston and presented to members by September 2016. Details of the financial figures will emerge as the result of developing options (a) and (b) in more detail. It was noted that the benefits of adopting a shared approach include: delivery of more resilient services; the ability to compete with the private sector as the market opens up; improvement in the quality of services; financial savings and income growth.
Word for word from the decision Merton published for this meeting.Source: democracy.merton.gov.uk
Committee: Cabinet Date: 7th March 2016 Wards: All Subject: Planning shared service outline business case Lead officer: James McGinlay Lead member: Councillor Andrew Judge/Councillor Mark Allison Contact officer: James McGinlay ________________________________________________________________________ Recommendations The following recommendations are made in the Proposed Way Forward section of this report: i. Two options for a shared approach are followed up in detail: a. a traditional shared service where one of the Councils is the employing authority b. a shared service provided through a shared delivery company ii. A full business case recommending the best delivery model is agreed through a Joint Member Board with Sutton and Kingston and presented to members by September 2016. Details of the financial figures will emerge as the result of developing options (a) and (b) in more detail. The benefits of adopting a shared approach include: delivery of more resilient services; the ability to compete with the private sector as the market opens up; improvement in the quality of services; financial savings and income growth. _________________________________________________________________________ 1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY 1.1. This paper proposes to explore in more depth options for a shared service between the London Boroughs of Merton and Sutton and the Royal Borough of Kingston for elements of planning services. 1.2. The services included for the London Borough of Merton are Building Control, Development Management (minors/householder applications), major applications, land charges Trees, Enforcement, & Business Support. Kingston are not including majors or land charges at this point in time. 1.3. The shared approach’s core objective is to explore options that will enable Merton to achieve the £612,000 saving target for DC/BC that is required in 2017/18. 2. DETAILS
2.1Objectives ● To retain sovereignty for each partner. ● To ensure that planning applications are processed in a timely and proportionate manner. ● To enhance each partner's reputation with residents and local business and the planning sector. ● To meet the savings targets of the three councils.
Page 11 1 2.2. Decision points
Merton Kingston Sutton
Cabinet 7th March Growth Committee - Housing, Economy and 17th March 2016 Business Committee - Cabinet Oct 2016 22nd March 2016
Further development of potential models - March-August 2016
Potential go live - April 2017
2.3Project Governance
*To clarify the London Borough of Merton will be a member of the Sutton and Kingston Shared services programme board. A Special Joint Member Board will be set up specifically for this project.
2.4Project Approach This project is being run following the project management approach adopted by each partner and is currently being led by Sutton who have commissioned an industry expert to help support the scoping and analysis phase.
Page 12 2 3. Strategic Context 3.1. The planning services in scope face the same challenges as the public sector generally with reducing budgets, a struggle to maintain standards of service within the lower financial envelop and delivering a sustainable service through periods of fluctuating demand and increasing customer expectation. The growth in the economy over recent years has seen an increase in demand for planning services both in general householder applications and for major schemes. Each of the Councils has a healthy regeneration portfolio to drive through changes which will form the foundation for the future development of the boroughs. There are, however, some fundamental changes being proposed by the government which will have a significant impact on planning services and how they are shaped for the future.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Morden Town Centre RegenerationCabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a developme...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.