That a variation to the current Highway Works and Services Term Contract with F M Conway for an extension of up to 6 months from 31 August 2019 be approved, as provided for in CSO 27 of the Contract Standing Orders (CSO) and in particular S.27.12.2 in line with the procurement activities currently on going for a new contract to be in place. This is to allow enough time for mobilisation after contract award. 2. That authority to approve the specific terms of the variation be delegated to the Director of Environment and Regeneration. 1. That a variation to the current Highway Works and Services Term Contract with F M Conway for an extension of up to 6 months from 31 August 2019 be approved, as provided for in CSO 27 of the Contract Standing Orders (CSO) and in particular S.27.12.2 in line with the procurement activities currently on going for a new contract to be in place. This is to allow enough time for mobilisation after contract award. 2. That authority to approve the specific terms of the variation be delegated to the Director of Environment and Regeneration.
Word for word from the decision Merton published for this meeting.Source: democracy.merton.gov.uk
Agenda Item 14 Committee: Cabinet Date: 15 July 2019 Agenda Item: Wards: All
Subject: Variation to the existing Highway Works and Service Contract of up to 6 months extension for mobilisation after award of replacement contract presently being procured. Lead Officer: Chris Lee – Director of Environment and Regeneration Lead Member: Councillor Martin Whelton – Cabinet Member for Regeneration, Environment and Housing Contact Officer: Gary Marshall – futureMerton Infrastructure Manager _____________________________________________________________________ Recommendations: 1. That Cabinet agree a variation to the current Highway Works and Services Term Contract with F M Conway for an extension of up to 6 months from 31 August 2019, as provided for in CSO 27 of the Contract Standing Orders (CSO) and in particular S.27.12.2 in line with the procurement activities currently on going for a new contract to be in place. This is to allow enough time for mobilisation after contract award. 2. Approval of the specific terms of the variation be delegated to the Lead Officer. ____________________________________________________________________
1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY 1.1. This report recommends that Cabinet approve an extension and variation to the current Highways Works and Services Term Contract and that the Lead Officer be delegated authority to approve the form of the relevant extension documents. The duration of the extension so delegated should be for a duration of up to 6 months. The current Highways Works and Services Term Contract is between the London Borough of Merton and F M Conway Limited (the Contract). 1.2. It is proposed to extend the agreement from the end date (30 August 2019) otherwise with no further change to the terms and conditions of the Contract including price. 1.3. This extension will only be taken up should it be required as it is intended to facilitate a seamless transition from the current supplier to the new contract following the current procurement process for replacement services and mobilisation period. The proposed extension of the Contract, is intended to
Page 395 reduce the risk of potential disruption to service for the start of the replacement services while ensuring continuity of service as the council delivers on-going public realm regeneration work. 1.4. The variation to the contract to allow for extension of up to six months will help to deliver value for money in accordance with S.27.8 of the CSOs, as contract price for the last 7 years will be applicable. The current contractor has confirmed there won’t be any changes to the current terms including price.
2 DETAILS 2.1. The Contract was awarded to F M Conway Ltd for a five-year term from 1 September 2012 to 31 August 2017. The Contract allowed for its term to be extended for up to a further two years and on 19 September 2016, Cabinet approved the 2 years extension which ends on 30 August 2019.
3 OPTIONS CONSIDERED 3.1. Two options were available to the council to consider: Agree a variation to the current contract to allow for an extension of up to 6 months for mobilisation after award of a contract for the replacement services. Do nothing and allow no mobilisation time or award the contract based on tight mobilisation timescales following award of the contract currently being procured. 3.2. The recommended option is to agree a variation to extend the existing contract to allow adequate time for mobilisation for the new contract following the current procurement process. 3.3. Varying the Contract to allow for an extension of up to 6 months, with no changes to the terms and conditions, is considered the most expedient and risk free approach to allow a seamless transition and continue to deliver planned and reactive highway works during the mobilisation period. 3.4. The variation to the contract will allow enough time for TUPE requirement to be implemented as required by statute.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Morden Town Centre RegenerationCabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a developme...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.