Cabinet, Monday 24 February 2020 at 7.15pm

Bishopsford Road Bridge - preferred option

Decided Executive 2 papers

Cabinet decided this item on Monday 24 February 2020. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

That Cabinet continues to recognise the urgency and importance of reopening Bishopsford Road Bridge and reaffirms its commitment to holding special meetings where necessary. 2. That Cabinet selects the demolition of the existing structure and the erection of a new bridge [options 5 or 6] as the preferred option from a number of options explored to reopen the bridge. 1. That Cabinet continues to recognise the urgency and importance of reopening Bishopsford Road Bridge and reaffirms its commitment to holding special meetings where necessary. 2. That Cabinet selects the demolition of the existing structure and the erection of a new bridge [options 5 or 6] as the preferred option from a number of options explored to reopen the bridge.
Word for word from the decision Merton published for this meeting. Source: democracy.merton.gov.uk

Follow this further

Built from Merton's papers

What the report saysPro

Report to Cabinet

Agenda Item 8 Committee: Cabinet Date: 24th February 2020 Wards: Ravensbury

Subject: Bishopsford Road Bridge – preferred options for reopening the bridge Lead officer: Director of Environment and Regeneration, Chris Lee Lead member: Cabinet Member for Regeneration, Housing and Transport, Councillor Martin Whelton Contact officer: Deputy FutureMerton Manager, Tara Butler

Recommendations: A. That Cabinet continues to recognise the urgency and importance of reopening Bishopsford Road Bridge and reaffirms its commitment to holding special meetings where necessary. B. That Cabinet selects the demolition of the existing structure and the erection of a new bridge [ options 5 or 6] as the preferred option from a number of options explored to reopen the bridge.

1 PURPOSE OF REPORT AND EXECUTIVE SUMMARY 1.1. This report sets out the options the council has explored to reopen the Bishopsford Road Bridge and recommends a preferred option to Cabinet. 1.2. Reopening the bridge to all vehicles is a high priority for the council. Cabinet members have already committed to prioritising works to reopen the bridge and have offered to undertake measures to speed up decision-making such as hold special meetings where necessary. 1.3. Six different options have been explored to reopen the bridge: options 1 to 4 are mainly based around repair and options 5 and 6 provide for a new bridge. 1.4. The primary aim has been to reopen the road as quickly and as safely as possible, ensure both the river and the structure are restored to the state they would have been in if the incident hadn’t happened in June 2019 while ensuring that the project can minimise or mitigate risks. 1.5. The report recommends the demolition of the existing structure and the construction to the new bridge as the preferred option to reopen the bridge. This will be either a two span structure (option 5) or a single span structure (option 6). 2 DETAILS 2.1. The council had been carrying out deck strengthening of Bishopsford Road Bridge as part of the annual highways maintenance programme. Works started on 23rd April 2019 which were due to finish by the end of July 2019

Page 51 2.2. On the evening of Monday 10th June 2019 following a weekend of heavy rain the river Wandle flooded at various points including three houses downstream from Bishopsford Bridge. 2.3. The council and its main structures contractor, FM Conway, worked on stabilising the bridge during the week 10th-14th June. Council staff also arranged sandbags and other support for the residents in the flooded houses 2.4. Four days later on the evening of Friday 14th June 2019 the northern arch of the bridged partially collapsed, breaking the utilities services (gas, water, electricity and broadband) that are routed through the bridge structure. The central arch suffered minor structural damage and the southern arch has no visible defects. 2.5. Details of the civil contingencies plan enacted from 14th – 17th June 2019, the subsequent stabilisation works to the structure and the mitigation measures enacted in the nearby park and surrounding area are set out in the Bishopsford Bridge update to Sustainable Communities Overview and Scrutiny Panel October 2019. Options for reopening the bridge 2.6. Officers have been working with a multidisciplinary engineering company, WSP and the highways term contractor FM Conway to develop different options to reopen the bridge. 2.7. The options have been based on  Restoring the structure and the road to the state it would have been in, had the strengthening works been completed as planned and had the incident not occurred in June 2019.  Reopening the bridge to traffic and pedestrians as quickly as possible while managing or mitigating risks to avoid any further incidents, either during construction or with the new structure.  Restoring river flow as promptly possible as required by the Water Resources Act, again minimising or mitigating risks in undertaking this.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2020-02-24 Cabinet report Bishopsford Bridge Appendix 1Appendix 111 KB Download
PDF
Bishopsford Road Bridge: preferred optionReport 156 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 28 attended
SA
Stephen AlambritisChair, present
MA
Mark AllisonCommittee Member, present
LA
Laxmi AttawarCommittee Member, present
KB
Kelly BraundCommittee Member, present
TB
Tobin ByersCommittee Member, present
CC
Caroline Cooper-MarbiahCommittee Member, present
EM
Edith Macauley MBECommittee Member, present
ES
Eleanor StringerCommittee Member, present
MW
Martin WheltonCommittee Member, present
TO
Test OfficerCouncil Staff, expected
TB
Thomas BarlowGuest, in attendance
DH
Daniel HoldenGuest, in attendance

All 28 on the meeting page

On this subject at Merton

Search all
  1. Bishopsford Road Bridge - preferred optionThis decision
  2. Road Bridge Bishopsford Road - London Road Morden SM4Decided
  3. Tooting & Mitcham FC, Bishopsford Road, SM4 6BFAgreed
  4. Tooting & Mitcham FC, Bishopsford Road, SM4 6BFNoted

More from Merton Cabinet

All decisions
MeetingDecisionOutcome
21 Sep 2026 Council’s New Homes ProgrammeCabinet is asked to: A. Approve the establishment of the (the Programme) as set out in this paper. B. Approve the pro... Approved Open
21 Sep 2026 Morden Town Centre RegenerationCabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a developme... Noted Open
21 Sep 2026 Property Asset Strategy Principles and corporate landlord modelCabinet is asked to: A. Approve the Property Asset Strategy principles as set out in this report. B. Agree the implem... Approved Open
21 Sep 2026 Recycling and Waste Collection Services Contract Update 2026Cabinet is asked to: A. Note the key performance indicators for the first year following the award of the contract fo... Noted Open
21 Sep 2026 Environmental Enforcement and Animal Welfare Contract – Extension and VariationCabinet is asked to: A. Approve the extension of the environmental enforcement contract (without the stray/abandoned ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies