A. That Cabinet agreed to no longer proceed with the proposal to implement emissions based parking charges from October 2021. A. That Cabinet agreed to no longer proceed with the proposal to implement emissions based parking charges from October 2021.
Word for word from the decision Merton published for this meeting.Source: democracy.merton.gov.uk
A. To agree to no longer proceed with the proposal to implement emissions based parking charges from October 2021.
1 PURPOSE OF REPORT AND EXECUTIVE SUMMARY
1.1In January 2021, the Council took the decision to implement an emissions based charging scheme (“The Scheme”), which was due for implementation from October 2021 (Cabinet report). The proposals comprised an additional charge for the most polluting vehicles parked on- and off-street.
1.2The Council is recommending to no longer proceed with the scheme because it is recognised that many residents are, and will continue, to suffer economically as a result of the COVID-19 pandemic and other cost of living increases more generally. Travel patterns which shifted during the pandemic – including a reluctance to return to public transport – have continued longer than anticipated, with uncertainty as to when or whether they will return. Moreover, Merton has already observed a significant shift to cleaner, greener vehicles during the time emissions-based charging has been considered, potentially linked to London-wide policies such as the ULEZ charge, and borough initiatives implemented in Merton, including low traffic neighbourhoods and school safety zones, as well as the Air Quality Action Plan.
1.3If the Council no longer proceeds with the scheme then the existing parking charges that are currently in force across the borough will remain unchanged.
2 DETAILS
2.1Economic impacts 2.1.1 Since Cabinet first reviewed the potential implementation of an Emissions Based Charging scheme, there have been a number of significant economic
Page 7 changes impacting residents that now need to be taken onto account to determine whether it would be appropriate for the current proposals, due to be implemented from October 2021, to go ahead. These are set out below: 2.1.2 The current furlough scheme will cease to exist from the end of September 2021, which may have a significant impact on the number of residents who find their incomes affected by reduced working hours or indeed, in some cases, redundancy. 2.1.3 The current additional payment of an extra £20 per week to Universal Credit payments will also cease to be paid from early October. This will affect the hardest hit families in the borough. 2.1.4 The recent price hikes and ongoing uncertainty regarding the increased prices in energy, alongside current inflation rates of 4.8%, will add an additional burden to hard-hit families from October 2021. 2.1.5 In addition, the Government has also announced a 1.5% increase to National Insurance from April next year. 2.1.6 Each of these factors need to be taken into consideration when balanced with additional financial burdens from other areas of policy e.g. Emissions Based Charging.
2.2Transport environmental factors. 2.2.1 Traffic volumes in Merton have continued to increase over the last decade which contributes to a number of strategic challenges including: traffic congestion and parking dominance, road safety concerns; public health concerns associated with sedentary lifestyles and; vehicular emissions that contribute to local air pollution and climate change. 2.2.2 The Council acknowledges there is no one simple solution that will be effective in isolation to achieve these objectives, but that a comprehensive package of measures is required that offers better sustainable travel options, alongside measures to disincentivise car use. 2.2.3 The Council acknowledges the limitations of using local measures alone to fully achieve a reduction in emissions and recognises that national and regional policies and initiatives introduced by the Government and TfL will be required.
2.3Recent transport trends
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Morden Town Centre RegenerationCabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a developme...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.