London Borough of Merton
Cabinet, Monday 21 March 2022 at 7.15pm

Compulsory Purchase Orders for estate regeneration: Eastfields Phase 1, High Path Phase 2 and 3 and Ravensbury Phase 2, 3 and 4

Agreed Executive 6 papers

Cabinet agreed this item on Monday 21 March 2022. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

A That Cabinet resolved to make three Compulsory Purchase Orders (the 2022 CPOs ) for the acquisition of land, interests and rights (other than those already in the ownership of Clarion Housing Group) over the Order Land shown shaded pink and blue on the Plans attached as Appendix 1 and described more fully in section 3 of each of the draft Statements of Reasons attached as Appendix 2. B That Cabinet agreed that the 2022 CPOs shall be, entitled: I. “The London Borough of Merton (High Path No1) Compulsory Purchase Order 2022"; II. "The London Borough of Merton ( Eastfields No1) Compulsory Purchase Order 2022"; and III. "The London Borough of Merton ( Ravensbury No1) Compulsory Purchase Order 2022". C That Cabinet agreed that there is a compelling case in the public interest to justify the making of the 2022 CPOs to include specific interests that must be acquired to facilitate the redevelopment of the High Path Estate, the Eastfields Estate and Ravensbury Estate (the Estates ) as part of the Merton Estates Regeneration Programme, for the reasons detailed in this Report and the draft Statements of Reasons. D That Cabinet delegated to the Director of Environment and Regeneration the power to effect the making, confirming and implementation of the 2022 CPOs and to take all necessary steps to give effect to the 2022 CPOs in respect of the Order Land, but not limited to, the following procedural steps: I. making such amendments and additions to the draft Statements of Reasons as deemed necessary to properly reflect the Council's position regarding the proposed 2022 CPOs so as to properly present the Council's case; II. making such amendments and additions to the Plans attached at Appendix 1 as deemed necessary to properly enable construction of phases 2 and 3 of High Path, phase 1 of Eastfields and phases 2 to 4 of Ravensbury ; III. making the 2022 CPOs, the publication and service of any press, site and individual notices and other correspondence for such making; IV. monitoring of negotiated agreements with landowners or statutory undertakers as applicable, setting out the terms for withdrawal of any objections to the 2022 CPOs, including where appropriate seeking exclusion of land or new rights from the 2022 CPOs; V. seeking confirmation of the 2022 CPOs by the Secretary of State (or, if permitted, by the Council pursuant to Section 14A of the Acquisition of Land Act 1981), including the preparation and presentation of the Council’s case at any Public Inquiry which may be necessary; VI. publication and service of notices of confirmation of the 2022 CPOs and thereafter to execute and serve any General Vesting Declarations and/or notices to treat and notices of entry, and any other notices or correspondence to acquire those interests within the area; VII. acquiring title to and / or taking possession of the Order Land; VIII. transferring the title of the acquired land to Clarion Housing Group; IX. paying all costs associated with making the 2022 CPO, including ... A That Cabinet resolved to make three Compulsory Purchase Orders (the 2022 CPOs ) for the acquisition of land, interests and rights (other than those already in the ownership of Clarion Housing Group) over the Order Land shown shaded pink and blue on the Plans attached as Appendix 1 and described more fully in section 3 of each of the draft Statements of Reasons attached as Appendix 2 . B That Cabinet agreed that the 2022 CPOs shall be, entitled: I. “The London Borough of Merton (High Path No1) Compulsory Purchase Order 2022"; II. "The London Borough of Merton ( Eastfields No1) Compulsory Purchase Order 2022"; and III. "The London Borough of Merton ( Ravensbury No1) Compulsory Purchase Order 2022". C That Cabinet agreed that there is a compelling case in the public interest to justify the making of the 2022 CPOs to include specific interests that must be acquired to facilitate the redevelopment of the High Path Estate, the Eastfields Estate and Ravensbury Estate (the Estates ) as part of the Merton Estates Regeneration Programme, for the reasons detailed in this Report and the draft Statements of Reasons. D That Cabinet delegated to the Director of Environment and Regeneration the power to effect the making, confirming and implementation of the 2022 CPOs and to take all necessary steps to give effect to the 2022 CPOs in respect of the Order Land, but not limited to, the following procedural steps: I. making such amendments and additions to the draft Statements of Reasons as deemed necessary to properly reflect the Council's position regarding the proposed 2022 CPOs so as to properly present the Council's case; II. making such amendments and additions to the Plans attached at Appendix 1 as deemed necessary to properly enable construction of phases 2 and 3 of High Path, phase 1 of Eastfields and phases 2 to 4 of Ravensbury ; III. making the 2022 CPOs, the publication and service of any press, site and individual notices and other correspondence for such making; IV. monitoring of negotiated agreements with landowners or statutory undertakers as applicable, setting out the terms for withdrawal of any objections to the 2022 CPOs, including where appropriate seeking exclusion of land or new rights from the 2022 CPOs; V. seeking confirmation of the 2022 CPOs by the Secretary of State (or, if permitted, by the Council pursuant to Section 14A of the Acquisition of Land Act 1981), including the preparation and presentation of ... view the full minutes text for item 6.
Word for word from the decision Merton published for this meeting. Source: democracy.merton.gov.uk

Follow this further

Built from Merton's papers

What the report saysPro

Report to Cabinet

Agenda Item 6

Committee: Cabinet Date: 21 March 2022 Wards: Abbey Ward, Figges Marsh and Ravensbury Subject: Merton Estates Regeneration Programme, Use of Compulsory Purchase Powers at High Path Estate Phase 2 and 3, Eastfields Estate Phase 1 and Ravensbury Estate Phase 2 to 4 Lead officer: Director for Environment and Regeneraiton, Chris Lee.

Lead member: Cabinet Member for Housing, Regeneration and the Climate Emergency, Councillor Martin Whelton

Contact officer: future Merton Programme Manager, Tara Butler. ________________________________________________________________________

Recommendations to Cabinet:

A To resolve to make three Compulsory Purchase Orders (the 2022 CPOs) for the acquisition of land, interests and rights (other than those already in the ownership of Clarion Housing Group) over the Order Land shown shaded pink and blue on the Plans attached as Appendix 1 and described more fully in section 3 of each of the draft Statements of Reasons attached as Appendix 2.

B To agree that the 2022 CPOs shall be, entitled:

I. “The London Borough of Merton (High Path No1) Compulsory Purchase Order 2022";

II. "The London Borough of Merton (Eastfields No1) Compulsory Purchase Order 2022"; and

III. "The London Borough of Merton (Ravensbury No1) Compulsory Purchase Order 2022".

C To agree that there is a compelling case in the public interest to justify the making of the 2022 CPOs to include specific interests that must be acquired to facilitate the redevelopment of the High Path Estate, the Eastfields Estate and Ravensbury Estate (the Estates) as part of the Merton Estates Regeneration Programme, for the reasons detailed in this Report and the draft Statements of Reasons.

D To delegate to the Director of Environment and Regeneration the power to effect the making, confirming and implementation of the 2022 CPOs and to take all necessary steps to give effect to the 2022 CPOs in respect of the Order Land, but not limited to, the following procedural steps:

I. making such amendments and additions to the draft Statements of Reasons as deemed necessary to properly reflect the Council's position

Page 1 75 regarding the proposed 2022 CPOs so as to properly present the Council's case;

II. making such amendments and additions to the Plans attached at Appendix 1 as deemed necessary to properly enable construction of phases 2 and 3 of High Path, phase 1 of Eastfields and phases 2 to 4 of Ravensbury;

III. making the 2022 CPOs, the publication and service of any press, site and individual notices and other correspondence for such making;

IV. monitoring of negotiated agreements with landowners or statutory undertakers as applicable, setting out the terms for withdrawal of any objections to the 2022 CPOs, including where appropriate seeking exclusion of land or new rights from the 2022 CPOs;

V. seeking confirmation of the 2022 CPOs by the Secretary of State (or, if permitted, by the Council pursuant to Section 14A of the Acquisition of Land Act 1981), including the preparation and presentation of the Council’s case at any Public Inquiry which may be necessary;

VI. publication and service of notices of confirmation of the 2022 CPOs and thereafter to execute and serve any General Vesting Declarations and/or notices to treat and notices of entry, and any other notices or correspondence to acquire those interests within the area;

VII. acquiring title to and / or taking possession of the Order Land;

VIII. transferring the title of the acquired land to Clarion Housing Group;

IX. paying all costs associated with making the 2022 CPO, including the compensation payable to owners , noting that those costs will be reimbursed to the Council by Clarion;

X. referral and conduct of disputes, relating to compulsory purchase compensation, at the Upper Tribunal (Lands Chamber); and

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 2.4 MB Download
PDF
Appendix 2Appendix 2 1.1 MB Download
PDF
Appendix 3aAppendix 3a 9 MB Download
PDF
Appendix 3bAppendix 3b 4 MB Download
PDF
Appendix 3cAppendix 3c 4.3 MB Download
PDF
Compulsory Purchase Orders for estate regeneration: Eastfields Phase 1, High Path Phase 2 and 3 and Ravensbury Phase 2, 3 and 4Report 443 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 5 attended
MA
Mark AllisonChair, present
OP
Owen PritchardCommittee Member, present
MW
Martin WheltonCommittee Member, present
TO
Test OfficerCouncil Staff, expected
BF
Brenda FraserCommittee Member, present

On this subject at Merton

Search all
  1. Compulsory Purchase Orders for estate regeneration: Eastfields Phase 1, High Path Phase 2 and 3 and Ravensbury Phase 2, 3 and 4This decision
  2. Compulsory Purchase OrdersNoted

More from Merton Cabinet

All decisions
MeetingDecisionOutcome
21 Sep 2026 Council’s New Homes ProgrammeCabinet is asked to: A. Approve the establishment of the (the Programme) as set out in this paper. B. Approve the pro... Approved Open
21 Sep 2026 Morden Town Centre RegenerationCabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a developme... Noted Open
21 Sep 2026 Property Asset Strategy Principles and corporate landlord modelCabinet is asked to: A. Approve the Property Asset Strategy principles as set out in this report. B. Agree the implem... Approved Open
21 Sep 2026 Recycling and Waste Collection Services Contract Update 2026Cabinet is asked to: A. Note the key performance indicators for the first year following the award of the contract fo... Noted Open
21 Sep 2026 Environmental Enforcement and Animal Welfare Contract – Extension and VariationCabinet is asked to: A. Approve the extension of the environmental enforcement contract (without the stray/abandoned ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies