A. That Cabinet agreed to award a new contract for the provision of arboriculture services across the Council’s administrative area to Barkland Tree Specialists for a period of three (3) years (from 01 November 2022) with potential extensions of up to 36 months (three years). The contract value is set out in Appendix A. B. That Cabinet delegate the decision to award an extension of the awarded contract to the Director of Environment and Regeneration in consultation with the Cabinet Member, for any period up to 3 years in accordance with CSO 27 That the recommendations within the Exempt Appendix were approved. A. That Cabinet agreed to award a new contract for the provision of arboriculture services across the Council’s administrative area to Barkland Tree Specialists for a period of three (3) years (from 01 November 2022) with potential extensions of up to 36 months (three years). The contract value is set out in Appendix A. B. That Cabinet delegate the decision to award an extension of the awarded contract to the Director of Environment and Regeneration in consultation with the Cabinet Member, for any period up to 3 years in accordance with CSO 27 That the recommendations within the Exempt Appendix were approved.
Word for word from the decision Merton published for this meeting.Source: democracy.merton.gov.uk
Committee: Cabinet Date: 22 September 2022 Wards: All Subject: Award of Contract for Aboriculture Services Lead officer: John Bosley, Assistant Director, Public Space Lead member: Cllr Natasha Irons, Cabinet Member for Local Environment, Green Spaces and Climate Change Contact officer: Claire Secord, Neighbourhood Client Officer
Exempt or confidential report
The following paragraph of Part 4b Section 10 of the constitution applies in respect of information within this appendix and it is therefore exempt from publication:
Information relating to the financial or business affairs of any particular person (including the Authority holding that information).
Members and officers are advised not to disclose the contents of the appendix.
Recommendations: A. To award a new contract for the provision of arboriculture services across the Council’s administrative area to Barkland Tree Specialists for a period of three (3) years (from 01 November 2022) with potential extensions of up to 36 months (three years). The contract value is set out in Appendix A. B. To delegate the decision to award an extension of the awarded contract to the Director of Environment and Regeneration in consultation with the Cabinet Member, for any period up to 3 years in accordance with CSO 27.
1 PURPOSE OF REPORT AND EXECUTIVE SUMMARY 1.1. The purpose of this report is to explain the procurement process for a new contract for the provision of arboricultural services across the Council’s administrative area and to recommend that Cabinet approves the award of the contracts to the successful bidder (Barkland Tree Specialists) contained within Appendix B. 1.2. The proposed award of contract will work towards meeting the Council’s strategic service priorities for clean streets and environment. This will be achieved through close work with the Contractor to maintain and manage the Council’s tree assets and continue to bolster new tree numbers and to deliver improved canopy cover across the borough which will be further underpinned by the developing tree strategy.
Page 7 1.3. The tender process involved contractors bidding to provide the arboriculture services following a pre-qualification exercise, fully in line with CSOs and the Public Contract Regulations 2015. 1.4. One (1) service provider is recommended to be appointed. Due to the commercial sensitivity the details of assessment results have been circulated as a confidential appendix to this report. 1.5. The recommended service provider offered the best overall value for money in the procurement process.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Morden Town Centre RegenerationCabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a developme...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.