Business Plan 2024-2028

Agreed Executive 1 paper

Cabinet agreed this item on Thursday 16 November 2023. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

That Cabinet considered and agreed the new capital proposals for 2024/25 to 2027/28 and the draft Capital Programme 2024-2028 (Appendix 1) and refers them to the Overview and Scrutiny panels and Commission in November 2023 for consideration and comment. 2. That Cabinet agreed the approach to setting a balanced budget outlined in the report 3. That Cabinet agreed the financial timetable for the Budget 2024/25 and MTFS 2024-28 (Appendix 5) 4. That Cabinet considered and agreed the draft growth proposals for 2024/25 to 2027/28 (Appendix 2) put forward by officers and refers them to the Overview and Scrutiny panels and Commission in November 2023 for consideration and comment. 5. That Cabinet considered and agreed the new savings proposals for 2024/25 to 2027/28 (Appendix 3) and refers them to the Overview and Scrutiny panels and Commission in November 2023 for consideration and comment. 6. That Cabinet considered and agreed the Equalities Impact Assessments for each saving, where applicable, and refers them to the Overview and Scrutiny panels and Commission in November 2023 for consideration and comment.(Appendix 3) 1. That Cabinet considered and agreed the new capital proposals for 2024/25 to 2027/28 and the draft Capital Programme 2024-2028 (Appendix 1) and refers them to the Overview and Scrutiny panels and Commission in November 2023 for consideration and comment. 2. That Cabinet agreed the approach to setting a balanced budget outlined in the report 3. That Cabinet agreed the financial timetable for the Budget 2024/25 and MTFS 2024-28 (Appendix 5) 4. That Cabinet considered and agreed the draft growth proposals for 2024/25 to 2027/28 (Appendix 2) put forward by officers and refers them to the Overview and Scrutiny panels and Commission in November 2023 for consideration and comment. 5. That Cabinet considered and agreed the new savings proposals for 2024/25 to 2027/28 (Appendix 3) and refers them to the Overview and Scrutiny panels and Commission in November 2023 for consideration and comment. 6. That Cabinet considered and agreed the Equalities Impact Assessments for each saving, where applicable, and refers them to the Overview and Scrutiny panels and Commission in November 2023 for consideration and comment.(Appendix 3)
Word for word from the decision Merton published for this meeting. Source: democracy.merton.gov.uk

Follow this further

Built from Merton's papers

What the report saysPro

Report to Cabinet

Recommendations

1. That Cabinet considers and agrees the new capital proposals for 2024/25 to 2027/28 and the draft Capital Programme 2024-2028 (Appendix 1) and refers them to the Overview and Scrutiny panels and Commission in November 2023 for consideration and comment. 2. That Cabinet agrees the approach to setting a balanced budget outlined in the report 3. That Cabinet agrees the financial timetable for the Budget 2024/25 and MTFS 2024-28 (Appendix 5) 4. That Cabinet considers and agrees the draft growth proposals for 2024/25 to 2027/28 (Appendix 2) put forward by officers and refers them to the Overview and Scrutiny panels and Commission in November 2023 for consideration and comment. 5. That Cabinet considers and agrees the new savings proposals for 2024/25 to 2027/28 (Appendix 3) and refers them to the Overview and Scrutiny panels and Commission in November 2023 for consideration and comment. 6. That Cabinet considers and agrees the Equalities Impact Assessments for each saving, where applicable, and refers them to the Overview and Scrutiny panels and Commission in November 2023 for consideration and comment.(Appendix 3)

1. Purpose of report and executive summary 1.1 This report presents an update of the Medium Term Financial Strategy (MTFS) since the initial report to Cabinet in June which rolled the MTFS forward and repriced it for the latest inflation assumptions.

1.2The Capital Programme has been reviewed and the report sets out the details in the draft Capital Programme 2024-28 (Appendix 1) for approval.

1.3The report sets out the approach towards setting a balanced budget for 2024- 28.

1.4The report sets out the draft financial timetable from September 2023 to March 2024 for setting the budget 2024/25 and council tax 2024/25.

1.5The report presents initial growth proposals which are required to alleviate pressures on services which have been identified as part of ongoing budget

Page 5 monitoring procedures and by officer’s expectations of demographic trends and other pressures such as the cost of living.(Appendix 2)

1.6Finally, the report sets out initial draft savings proposals which have been identified by officers to contribute towards meeting the Council’s statutory requirement to approve a balanced budget for 2024/25. (Appendix 3)

1.7Equalities impact assessments for each saving, where applicable, are included in Appendix 3.

1.8The council has clear priorities for its services but Members should note that the delivery of some of those priorities has been challenging due to the one-off nature of some government funding.

2. Details

2.1The initial report to Cabinet in June updated the MTFS for known changes arising from outturn 2022/23 and revised inflation assumptions for pay and prices.

2.2The MTFS gap was revised as follows:-

2024/25 2025/26 2026/27 2027/28 (cumulative) £000 £000 £000 £000 MTFS Gap (Council March 2023) 0 2,296 3,836 13,533

Ongoing impact of 3% pay award in 2023/24 992 992 992 992 Impact of increased pay and price inflation in 2024/25 2,513 2,513 2,513 2,513 Collection Fund (Surplus)/Deficit change on outturn (1,945) 0 0 0

MTFS Gap 2024-28 (Cabinet June 2023) 1,560 5,801 7,341 17,039

3. Review of Assumptions

3.1Pay

Ongoing cost of 2023/24 Pay Award For 2023/24 the final pay award has just been agreed by the unions.Provision of 3% was included in the MTFS. An additional provision was added to the MTFS reported to Cabinet in June.

The Local Government Employers offer which has just been accepted is:-

• A one year (1 April 2023 – 31 March 2024) pay increase of £1,925 (pro rata for part-time employees) to be paid as a consolidated, permanent addition on all NJC points 2-43 inclusive.

Page 6 • An increase of 3.88% on all allowances (as listed in the 2022 NJC Pay Agreement Circular dated 1st November 2022).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Business Plan 2024-2028Report 3 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 21 attended
RG
Ross GarrodChair, present
ES
Eleanor StringerCommittee Member, present
SA
Stephen Alambritis MBECommittee Member, present
BC
Billy ChristieCommittee Member, present
CC
Caroline Cooper-MarbiahCommittee Member, present
BF
Brenda FraserCommittee Member, present
NI
Natasha IronsCommittee Member, apologies
AJ
Andrew JudgeCommittee Member, present
SK
Sally KennyCommittee Member, present
PM
Peter McCabeCommittee Member, present
TO
Test OfficerCouncil Staff, expected
ZB
Zara BishopOfficer, in attendance

All 21 on the meeting page

On this subject at Merton

Search all
  1. Business Plan 2024-2028This decision
  2. Budget and Business PlanDecided
  3. Scrutiny of the Business Plan; comments and recommendations from the overview and scrutiny panelsDecided
  4. Business Plan 2023-27Agreed
  5. Business Plan 2023-27Agreed
  6. Business Plan Update 2023-2027Decided

More from Merton Cabinet

All decisions
MeetingDecisionOutcome
21 Sep 2026 Council’s New Homes ProgrammeCabinet is asked to: A. Approve the establishment of the (the Programme) as set out in this paper. B. Approve the pro... Approved Open
21 Sep 2026 Morden Town Centre RegenerationCabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a developme... Noted Open
21 Sep 2026 Property Asset Strategy Principles and corporate landlord modelCabinet is asked to: A. Approve the Property Asset Strategy principles as set out in this report. B. Agree the implem... Approved Open
21 Sep 2026 Recycling and Waste Collection Services Contract Update 2026Cabinet is asked to: A. Note the key performance indicators for the first year following the award of the contract fo... Noted Open
21 Sep 2026 Environmental Enforcement and Animal Welfare Contract – Extension and VariationCabinet is asked to: A. Approve the extension of the environmental enforcement contract (without the stray/abandoned ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies