A. Vary the existing Environmental Infrastructure Asset Management and Street Works Solution Contract with Causeway which commenced on the 16 July 2024, to accommodate and include the ‘One.Network’ and ‘Parkmap’ software solutions provided by Causeway for the provision of street works mapping facility and digital traffic order recording functionality. B. That Cabinet delegate the authority to award further extensions or variations to the executive director of ECP&C via procurement board for the duration of the contract term A. Vary the existing Environmental Infrastructure Asset Management and Street Works Solution Contract with Causeway which commenced on the 16 July 2024, to accommodate and include the ‘ One.Network ’ and ‘ Parkmap ’ software solutions provided by Causeway for the provision of street works mapping facility and digital traffic order recording functionality. B. That Cabinet delegate the authority to award further extensions or variations to the executive director of ECP&C via procurement board for the duration of the contract term
Word for word from the decision Merton published for this meeting.Source: democracy.merton.gov.uk
Report cover sheet NAME OF DECISION-MAKER DATE Cabinet 23 June 2025
REPORT/DECISION TITLE WARD(S) GW3 - Variation report - EAMS contract to All include DTTRO and One network
CHIEF OFFICER(S) CABINET/LEAD MEMBER(S) Name: Caroline Bruce Name: Cllr Stuart Neaverson Executive Director of Environment, Civic Cabinet Member for Transport and Pride and Climate Cleaner Streets
DECISION CLASSIFICATION IS THE FINAL DECISION ON THE RECOMMENDATIONS IN THIS REPORT TO BE MADE AT THIS Is the decision exempt from call in? MEETING? No No Is the report, in whole or in part, exempt Final Decision to be made by Cabinet from publication? on 23 June 2025 Not exempt
1. Recommendations Cabinet is asked to: A. Approve the variation of the existing Environmental Infrastructure Asset Management and Street Works Solution Contract which commenced on the 16th July 2024, to accommodate and include the ‘One.Network’ and ‘Parkmap’ software solutions utilising Regulation 72 (F) of the PCR2015 procurement regulations. The systems are provided by Causeway for the provision of street works mapping facility and digital traffic regulation order recording functionality.
Page 1 B. That Cabinet delegate the authority to award further extensions or variations to the Executive Director of ECP&C via Procurement Board for the duration of the contract term.
Procurement Details Summary – Direct Award Contract Manager / Project Manager Jayne Rusbatch (Name and Title) Head of Sustainable Transport Highways and Climate Name and description of Contract GW3 - Variation report - EAMS contract to include Digital Traffic Regulation Order and One network platforms. Is the Contract for Services that are a No Statutory Requirement? Total Value of Existing Contract £3,039,323.51 (excluding VAT) £3,647,188.21 Rate of applicable VAT 20% See gov.uk guidance here Estimated Total Value of New £39,000, ex VAT Contract: VAT £7,800 £46,800 (incl VAT) New total values of contract £3,078,323.51 and with VAT added £3,693,188.21
Does the current provider pay staff Yes working on the Merton contract London Living Wage (LLW) or above? If this is a new contract, will the new provider pay LLW as per Merton’s policy requirements? If no, please explain why
Page 2 Recommendations, report summary and relevance to strategic priorities 2. Recommendations (repeated from page 1) The Executive Director of Environment, Civic Pride and Climate is asked to: A. Vary the existing Environmental Infrastructure Asset Management and Street Works Solution Contract with Causeway which commenced on the 16 July 2024, to accommodate and include the ‘One.Network’ and ‘Parkmap’ software solutions provided by Causeway for the provision of street works mapping facility and digital traffic order recording functionality. B. That Cabinet delegate the authority to award further extensions or variations to the executive director of ECP&C via procurement board for the duration of the contract term.
3. Executive summary 3.1 The current Environmental Infrastructure Asset Management and Street Works management system contract currently held with the supplier ‘Causeway’ is necessary to manage and maintain environmental infrastructure assets but also to ensure compliance of statutory duties, including to maintain a Street Works Register ensuring it fulfils its duty as set out in both the New Roads and Street Works Act 1991 and Traffic Management Act 2004. In addition, there is a requirement to perform Merton Council’s statutory duty to Highways Safety Inspections and defect rectification in protection under Highway’s claims through the Highways Act 1980 section 58 defence.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Morden Town Centre RegenerationCabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a developme...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.