Cabinet, Monday 24 November 2025 at 7.15pm

Planning Peer Challenge Action Plan

Agreed Executive 3 papers

AI summaryMerton Cabinet approves an action plan responding to a Planning Advisory Service peer review of the Development Management service, with 15 recommendations to be delivered over two years through a new Regeneration Board.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedCabinet agreed the proposed actions and timescales
MoneyNo budgets required at this stageNo financial costs identified for the report
What happens nextImplementation and monitoringUpdates to CLT and Sustainable Communities OSC
Who it affectsPlanning applicants, residents, communitiesAlso developers and the council planning service

What was decided

Cabinet agreed the proposed actions set out in the plan and the timescales for their implementation. Report P1, P4

The plan covers 15 recommendations from the Planning Advisory Service peer review of the Development Management service, with each recommendation matched by an action in Appendix 2. Report 2.4, 4.4, 4.5, 5.1

Why

To supplement and build on the intensive peer challenge review carried out by the Planning Advisory Service, an independent part of the Local Government Association. Report 2.3, 4.4, 7.1

The Development Management service plays a key role in delivering the strategic aims of the Council Plan, including housing supply, heritage protection and tree cover. Report 2.1, 7.2, P12, P13

What happens next

The Executive Director for Housing and Sustainable Development will oversee delivery through a Regeneration Board made up of officers with place making roles. Report 5.2, 6.1

All actions are expected to be substantially complete within two years, with most fully evolved after one year. Report 5.2

The peer challenge report and action plan will be published online, with regular updates to the Corporate Leadership Team and the Sustainable Communities Overview and Scrutiny Committee. Report 9.1

Options considered

  • Chosen: Approve the action plan for Development Management purposes. PAS review is comprehensive; actions move the service towards best in class; resources judged sufficient with minimal risk Report P43, P47, P49, P51, P54
  • Rejected: Vary the action plan for Development Management purposes. Variation could deviate from the expert analysis and misalign resources, though the programme can evolve through governance procedures Report P56, P60, P63
  • Rejected: Do not approve the action plan for Development Management services. Peer challenge process would become moribund and the LPA would not improve in line with national guidance Report P65, P69, P72

Implications

  • Legal: There may need to be changes to the Scheme of Management or the Constitution as a result of national planning reforms aligned with these proposals. Report P87
  • Financial: No financial costs and therefore no budgets required at this stage. The Planning and Infrastructure Bill proposes local fee setting that could enable full cost recovery. Report P52, P87
  • Equalities: The actions have remote or low relevance to the substance of the Equality Act and no apparent equality impact on end users. Report P87
  • Staffing: The outdated M3 IT software is being replaced by a new IDOX cloud system bringing new efficiencies through greater automation. Report 4.1
  • Risk: Service income is affected by slow housing build rates and a relatively small number of major planning applications being submitted; local fee setting may offset this. Report P87

Who and where

  • Planning applicants, agents and developers Report 4.3, P12
  • Residents and community groups in Merton Report 4.4, 8.1, P14
  • Merton Council planning officers Report 4.4, 5.2
  • Elected members on the planning committees Report 4.4, P30

Timeline

  • November 2024: Council adopted the new Local Plan Report 4.1
  • November 2025: Agents Forum scheduled to improve engagement with applicants, agents and developers Report 4.3
  • Within one year: Most actions expected to be fully evolved Report 5.2
  • Within two years: All actions expected to be substantially complete Report 5.2

Plain English for the jargon

  • LPA: Local Planning Authority, the council function that decides planning applications
  • PAS: Planning Advisory Service, part of the Local Government Association
  • DM: Development Management, the council function that assesses and decides planning applications
  • EoT: Extension of Time, an agreement to extend the deadline for determining a planning application
  • SCI: Statement of Community Involvement, setting out how the council engages communities in planning
  • DM Toolkit: A self assessment tool published by PAS for Development Management services
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

The Cabinet is asked to: A. Agree the proposed actions set out in the plan and the timescales for their implementation. The Cabinet is asked to: A. Agree the proposed actions set out in the plan and the timescales for their implementation.
Word for word from the decision Merton published for this meeting. Source: democracy.merton.gov.uk

Follow this further

Built from Merton's papers

What the report saysPro

Report to Cabinet

Recommendations

The Cabinet is asked to: A. Agree the proposed actions set out in the plan and the timescales for their implementation.

Page 41 Recommendations, report summary and relevance to strategic priorities

1. Recommendations (repeated from page 1)

The Cabinet is asked to: A. Agree the proposed actions set out in the plan and the timescales for their implementation.

Executive summary

2.1The Local Planning Authority (LPA) service is a high performing function of Merton Council which processes Development Management applications; enforces Planning Control; preserves and enhances the heritage of the borough; and protects privately owned trees whilst securing new planting in new developments. It also produces the Local Plan for the area, allocates sites for specific development purposes and sets policies for technical matters such as the delivery of affordable housing, climate change, biodiversity and ecology.

2.2National statutory and local targets for the determination of planning submissions are regularly exceeded in terms of the quality and speed of decision making and the statistics published by Central Government in recent years demonstrate strong performance. In the previous two-year period ending in quarter 1 of 2025 the Council had no major appeal decisions overturned whilst for minor appeal decision making the figure is 1%, both significantly beneath the 10% threshold for being placed in special measures. Meanwhile in the 1-year period leading to quarter 3 of 2025 major applications were determined on time in 100% of cases whilst 93% of minor applications were also determined on time.

2.3However, in the context of the Corporate Peer Challenge carried out for the Council by the Local Government Association around the same time it was considered it would be helpful if the national Planning Advisory Service (PAS) part of that organisation carried out a review of Development Management. The purposes of this were to make a health check statement for the operation, identify any risks (particularly given the need to adjust to national planning reforms) and suggest improvements so that the service can become best in class.

2.4The report produced by PAS is attached at Appendix 1. This identifies 15 key recommendations to propel a positive direction of travel. The action plan included at Appendix 2 responds to each one of these to demonstrate how the workstreams will benefit applicants, residents, communities and deliver on the spatial development and regeneration needs of the borough moving forward.

Page 42 3. Relevance to strategic priorities, including Council Plan priorities

Strategic priority Relevant? Brief explanation of relevance

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
LB Merton Planning Peer Challenge ReportAppendix A 551 KB Download
PDF
LB Merton Response to Planning Peer Challenge: Action PlanAppendix B 178 KB Download
PDF
Planning Peer Challenge Action PlanReport 161 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 21 attended
SE
Sharon EvansCouncil Staff, in attendance
LA
Lewis Addlington-LeeCouncil Staff, expected
RG
Ross GarrodChair, present
ES
Eleanor StringerCommittee Member, present
CC
Caroline Cooper-MarbiahCommittee Member, present
AJ
Andrew JudgeCommittee Member, present
SK
Sally KennyCommittee Member, present
PM
Peter McCabeCommittee Member, present
UK
Usaama KaweesaCommittee Member, present
TO
Test OfficerCouncil Staff, expected
EM
Edith Macauley MBECommittee Member, present
SN
Stuart NeaversonCommittee Member, present

All 21 on the meeting page

More from Merton Cabinet

All decisions
MeetingDecisionOutcome
21 Sep 2026 Council’s New Homes ProgrammeCabinet is asked to: A. Approve the establishment of the (the Programme) as set out in this paper. B. Approve the pro... Approved Open
21 Sep 2026 Morden Town Centre RegenerationCabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a developme... Noted Open
21 Sep 2026 Property Asset Strategy Principles and corporate landlord modelCabinet is asked to: A. Approve the Property Asset Strategy principles as set out in this report. B. Agree the implem... Approved Open
21 Sep 2026 Recycling and Waste Collection Services Contract Update 2026Cabinet is asked to: A. Note the key performance indicators for the first year following the award of the contract fo... Noted Open
21 Sep 2026 Environmental Enforcement and Animal Welfare Contract – Extension and VariationCabinet is asked to: A. Approve the extension of the environmental enforcement contract (without the stray/abandoned ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies