What was decided
Cabinet approved a two-stage procurement under the Procurement Act 2023 to select a developer partner to deliver the regeneration under a phased development agreement, and delegated authority to the Executive Director for Housing and Sustainable Development to finalise and run the procurement, accepting that the Gateway 1 report will be presented after these approvals as a deviation from Contract Standing Orders. Report P1, P2, 4.6, 4.9
Cabinet approved adding £30m to the capital programme for Morden Town Centre, to be recommended to Full Council for ratification on 25th February 2026, and approved in principle the contribution of council land subject to best consideration under section 123 of the Local Government Act 1972. Report P2, 4.21, P102, P103
Cabinet delegated authority to the Executive Director for Housing and Sustainable Development, in consultation with the Executive Director of Finance and Digital, to apply for grant and loan funding and enter into funding agreements, and noted the update on the meanwhile use programme. Report P2, 2.4, 4.25, P70
Why
Officers assessed delivery options and concluded a phased development agreement gives the Council control over outcomes while a land sale would not and a corporate joint venture would expose the Council to unacceptable financial risk. Report 6.1, P23, P82
Viability appraisals by Deloitte show a funding gap, particularly for upfront land assembly costs, so the Council is committing initial capital and will explore GLA and other public sector funding, including the City Hall Developer Investment Fund. Report 2.3, 4.20, 4.23, P66
Pre-market engagement with nine organisations found strong market interest, support for a mixed-tenure housing-led scheme, and a preference for the Civic Centre site to be delivered first while the Abbotsbury Triangle is assembled. Report 4.11, 4.12, 4.13, P46, P47, P50
What happens next
Officers will finalise procurement documents and launch Stage 1 Invitation to Participate in Spring 2026, with Stage 2 Invitation to Tender in Summer 2026, dialogue in Autumn 2026, final tenders in Winter 2026, and evaluation and recommendations in Spring 2027. Report 8.1, P94
Following evaluation of final tenders, Cabinet will consider a further report setting out results, any recommendation to award, and the financial and other implications, before Full Council ratifies the £30m capital addition on 25th February 2026. Report P2, P37
A land assembly strategy will be developed, which may involve compulsory purchase powers under the Town and Country Planning Act 1990, subject to a future Council resolution if required. Report 4.16, 4.17, P24
The money
- £30m Capital programme addition for Morden Town Centre from CHAS Capital Receipt, subject to Full Council ratification on 25th February 2026 Report P2, 4.21, P103
- £30m Balance remaining on CHAS Capital Receipt after the £30m contribution, to fund future legacy schemes Report P102, P103
- £60m Balance on CHAS Capital Receipt allowing for the £15m Merton Legacy Fund Report P102
- 0.50 Approved capital budget for Morden Regeneration Scheme Match Funding 2027-28 (£m) Report P101
- 3.50 Approved capital budget for Morden Regeneration Scheme Match Funding 2028-29 (£m) Report P101
- 4.00 Total approved capital budget for Morden Regeneration Scheme Match Funding (£m) Report P101
- 1.36 Approved capital budget for Acquisitions 2028-29 (£m) Report P100
Options considered
- Rejected: Land disposal to developer(s) without contractual control over outcomes. Would not allow the Council to secure its ambitions for comprehensive regeneration through suitable contractual mechanisms Report 6.1, P74
- Chosen: Phased development agreement with a developer. Allows phased delivery with each phase under standalone agreements while giving the Council control over outcomes Report P23, P51, P75, P82
- Rejected: Corporate joint venture on a 50/50 basis. Would entail the Council taking an unacceptable share of development and financial risk Report 6.1, P76
- Rejected: Investment partnership. Not the preferred route; phased development agreement is more appropriate Report P77
- Rejected: Direct delivery by the Council as developer. Council cannot afford the costs and risk of directly delivering regeneration at this scale Report 6.1, P78
Implications
- Financial: Initial £30m capital contribution from the CHAS Capital Receipt, with further public sector funding to be explored including the GLA and the City Hall Developer Investment Fund; revenue budget needed for 2026/27 onwards to manage the programme. Report 2.3, 4.21, 4.23, P66, P103, P100
- Legal: Council must satisfy its best consideration duty under section 123 of the Local Government Act 1972 for any land contributed; powers under the Localism Act 2011 and Housing Act 1985 underpin the project; any compulsory purchase under the Town and Country Planning Act 1990 would need a separate resolution. Report P2, 4.17, P99
- Equalities: An initial Equality Analysis identifies likely beneficial impacts for children, older people, disabled people, ethnic minority and minority faith groups, care-experienced people and lower socio-economic groups, alongside potential adverse construction impacts including demolition, relocation and environmental health effects; an Improvement Action Plan will be worked up. Report P104
- Climate: The decisions have a low impact on the Climate Strategy and Action Plan, with sustainability and Net Zero targets to be included in procurement documents in line with the Local Plan. Report P105
- Risk: Key risks include lack of private sector interest, further public funding required to achieve viability, upfront land assembly cost and delay, economic downturn halting the programme, dependence on compulsory purchase, and a possible resident ballot for the St Helier neighbourhood redevelopment. Report P106
- Other: The Council must keep its development or corporate landowner function separate from the Local Planning Authority function and observe human rights and equalities duties throughout. Report P99
- Other: Procurement will be conducted under the Procurement Act 2023 and Contract Standing Orders, with social value requirements set for the developer and contractors. Report 4.6, 4.7, P105
Who and where
- Residents, businesses and landowners in Morden Town Centre Report 7.1, 7.2, P89, 4.18
- Existing small businesses and town centre users Report P55, 4.25, P70
- Transport for London and Places for London as key landowners (outside the initial area) Report 7.3, P46
- Developer market participants responding to the procurement Report 4.11, 4.12, P50
- Future residents of new housing, including affordable and social tenures Report P55, P47
Timeline
- September 2025: Cabinet resolved to lead regeneration and prepare a procurement process for a developer partner Report 2.1, P16
- 14th October 2025: Pre-Market Engagement Notice published Report 4.11
- November 2025: Meetings held with 9 organisations as part of pre-market engagement Report 4.12, 4.13
- 28th November 2025: Christmas lights switch-on event held Report P70
- Spring 2026: Stage 1 Invitation to Participate launched Report 8.1, P94
- 25th February 2026: Full Council to ratify the £30m capital programme addition Report P2
- Summer 2026: Stage 2 Invitation to Tender Report P94
- Autumn 2026: Dialogue stage with shortlisted bidders Report P94
- Winter 2026: Call for final tenders Report P94
- Spring 2027: Evaluation and recommendations report to Cabinet Report P94
Plain English for the jargon
- Phased development agreement: A contractual arrangement between the Council and a developer covering pre-development work, land transfer and phased development, with each phase potentially delivered under a separate sub-agreement
- Gateway 1 report: A procurement strategy paper normally considered by Procurement Board before a Cabinet decision, which under this report will be presented after Cabinet approval as a deviation from Contract Standing Orders
- Procurement Act 2023 (PA23): The legislation governing how the Council must run its procurement, including the Competitive Flexible Procedure used here
- Competitive Flexible Procedure: A procurement procedure under PA23 allowing the Council to design a process, used here as a two-stage Invitation to Participate then Invitation to Tender
- CHAS Capital Receipt: Capital receipt held by the Council, described as having a £60m balance allowing for the £15m Merton Legacy Fund, from which the £30m contribution is proposed
- Compulsory Purchase Order (CPO): A legal power under the Town and Country Planning Act 1990 allowing the Council to acquire land needed to deliver the regeneration, which would require a future Council resolution
- Pre-Market Engagement (PME): Early consultation with potential bidders to test the opportunity and inform the procurement design, here carried out with 9 organisations after the 14th October 2025 notice
- HRA: Housing Revenue Account, the ringfenced account local authorities use for council housing, referenced in the context of the Council potentially purchasing affordable units
- Legacy Fund: Fund referenced as the source of the £30m capital contribution for the project