Written from the decision and the officer reportPDF Pro
OutcomeApprovedRegulation 72(1)(b) variation to Tyco contract
Money£1,750,000Variation value; total contract £5.25 million
What happens nextRe-procurement to beginLong-term contract procurement starts July 2026
Who it affectsCCTV and ANPR networkPublic safety cameras, school streets, weight restrictions
What was decided
Cabinet approved a £1,750,000 variation to the existing CCTV and ANPR maintenance contract with Tyco under Regulation 72(1)(b) of the Public Contracts Regulations 2015, covering the period to 5 November 2027. Report P1, P10, 2.1
The variation increases the published contract value from £3.5 million to £5.25 million and covers additional maintenance, upgrades and project work across the remaining contract term. Report 2.3, P6, 4.1
A deed of variation must be signed and a contract modification notice published in the Find a Tender Service, with the Council's Contract Register updated. Report P85, P86, P84
Why
The original £3.5 million contract value has been fully used because of higher operational demand, additional camera deployments and essential project work since award. Report 2.3, P5
The variation is needed to keep statutory enforcement running, complete control room and infrastructure upgrades, and install more cameras at weight-restriction breach hotspots. Report 2.3, 2.4
Officers say delaying the work or running a short separate procurement would risk service failure, loss of enforcement income and mobilisation inefficiency. Report 2.4, P15, P16
What happens next
A full re-procurement will run from July 2026, with Gateway 1 in September 2026, Cabinet decision in October 2026 and new contract start on 1 December 2027. Report P72, P73, P74, P76
A deed of variation will be completed and a Regulation 51 contract modification notice published in the Find a Tender Service after Cabinet approval. Report P84, P85
A £108,000 shortfall in Parking budgets will be covered by further budget realignment identified by finance officers. Report P88
The money
£1,750,000 Value of the proposed contract variation Report P1, P6
£3.5 million Published value of the awarded contract Report P5, P6
£5.25 million Total contract value after variation Report P6, 4.1
£661,063 Annualised cost of current contract Report P6, P87
£2,800,000 Recommended single contract value from credit check Report P7, P88
£1,016,063 Year 1 (2025 to 2026) variation spend Report 6.2, P64
£701,063 Year 2 (2026 to 2027) variation spend Report 6.2, P64
£108,000 Shortfall in Parking budgets to be met by realignment Report P88
Options considered
Rejected: Do not extend or vary the contract. Would end maintenance and support, risk loss of enforcement income and threaten public safety and statutory compliance Report P31, P33, P35, P37
Chosen: Variation under Regulation 72(1)(b) of the PCR 2015 for £1,750,000 to 5 November 2027. Maintains continuity, avoids mobilisation costs, keeps existing rates, supports required deployments and upgrades Report P40, P42, P46, 6.1
Rejected: Run a separate procurement for the remaining term. High mobilisation cost, likely higher market pricing, risk of challenge and operational disruption Report P49, P51, P53, P55
Implications
Legal: Modification is made under Regulation 72(1)(b) of the Public Contracts Regulations 2015; a deed of variation is required and a Regulation 51 notice must be published in the Find a Tender Service. The variation is 50% of the original contract value, so no further value increases can be made under this route. Report P80, P82, P83, P84, P85
Financial: Funded from existing revenue budgets: £106,000 from CCTV Safer Merton budgets and £555,000 from Parking budgets, with a £108,000 shortfall to be met by further budget realignment. Report P45, P60, P87, P88
Risk: If not approved, statutory enforcement could be disrupted, enforcement revenue lost, network coverage reduced and ongoing project work stopped. Report P15, P16
Staffing: The current provider pays staff working on the Merton contract the London Living Wage or above. Report P7, P8
Other: Contract performance is above 98.5%, exceeding the 97.5% standard set in the original contract. Report 4.1
Who and where
Residents and visitors using public spaces, town centres and transport hubs covered by CCTV Report P21, P23
Drivers subject to ANPR enforcement, including in school streets, low traffic neighbourhoods and weight-restricted roads Report P20, 2.3
Schools in the school street scheme using ANPR cameras to restrict vehicle access at drop-off and pick-up times Report P21
Partner agencies including the police, community safety teams and event organisers relying on CCTV coverage Report P23
Timeline
December 2021: Original CCTV and ANPR contract awarded to Tyco Report P4, 4.1
22 June 2026: Cabinet decision on this variation (Gateway 3) Report P72
29 June 2026: Call-in period ends Report P72
17 July 2026: Gateway 0 approval by Procurement Board for re-procurement Report P73
1 September 2026: Gateway 1 approval by Departmental Procurement Group Report P73
October 2026: Cabinet decision to release framework further competition Report P73
26 November 2026: Deadline for tender submissions for new long-term contract Report P73
5 March 2027: Contracts award notice and contract register update for new contract Report P76
5 November 2027: Existing varied contract expires Report P1, 4.1
1 December 2027: New long-term contract starts after eight-month mobilisation Report P76
Plain English for the jargon
ANPR: Automatic Number Plate Recognition cameras used for traffic and enforcement purposes
CCTV: Closed Circuit Television used for public safety surveillance
PCR 2015: Public Contracts Regulations 2015, the procurement rules allowing modifications under Regulation 72(1)(b)
Gateway 3: Procurement approval stage for contract variations before award
Find a Tender Service: UK government publication portal where contract modification notices must be published
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4
Resolved
Cabinet is asked to: A. Approve a contract variation, utilising Regulation 72(1)(b) of the Public Contracts Regulations 2015, to the CCTV and ANPR maintenance contract for the remaining contract period until 5 November 2027, at a total value of £1,750,000, as set out in this report. Cabinet is asked to: A. Approve a contract variation, utilising Regulation 72(1)(b) of the Public Contracts Regulations 2015, to the CCTV and ANPR maintenance contract for the remaining contract period until 5 November 2027, at a total value of £1,750,000, as set out in this report.
Word for word from the decision Merton published for this meeting.Source: democracy.merton.gov.uk
Cabinet is asked to: A. Approve a contract variation, utilising Regulation 72(1)(b) of the Public Contracts Regulations 2015, to the CCTV and ANPR maintenance contract for the remaining contract period until 5 November 2027, at a total value of £1,750,000, as set out in this report.
Sam Dickinson Public Safety CCTV manager Name and description of Contract Provision and maintenance of public safety cameras and ANPR cameras.
Is this an Extension or Variation to the Variation to the Contract Contract? Is the Contracts for Yes Goods/Works/Services that are a Statutory Requirement? Start and End Dates of Initial Contract December 2021 – November 2025 Term Length of extension and new start / December 2025 – November 2027 end dates Current Value of Existing Contract £3.5 million including all extensions
Published Value of Awarded Contract £3.5 million
Annualised cost of current contract £661,063 Rate of applicable VAT See gov.uk guidance here 20% Estimated Value of Extension/ £1,750,000 Variation: Total contract value after variation: £5.25 million Annualised cost of current contract £661,063 per annum
Please provide the outcome of a credit Recommended single contract value: check for the supplier £2,800,000 (carried out within the last 30 days from the date on this report) Does the current provider pay staff Yes working on the Merton contract
Page 6 London Living Wage (LLW) or above? If not, when will they? Recommendations, report summary and relevance to strategic priorities
1. Recommendations (repeated from page 1)
Cabinet is asked to: A. Approve a contract variation, utilising Regulation 72(1)(b) of the Public Contracts Regulations 2015, to the CCTV and ANPR maintenance contract for the remaining contract period until 5 November 2027, at a total value of £1,750,000, as set out in this report.
Executive summary
2.1This report seeks approval for a £1,750,000 variation to the existing Tyco contract for the provision, maintenance and operational support of public safety CCTV and ANPR enforcement cameras, in order to maintain service continuity, statutory enforcement and network resilience for the remainder of the contract term.
2.2The contract was awarded in 2021 for a four‑year term, with two permitted one‑year extensions, and is now operating within its final extended period, expiring on 5 November 2027. No further extensions are available under the existing contractual arrangements.
2.3The approved contract value of £3.5m (inclusive of all extensions) has now been fully utilised due to increased operational demand, additional deployments, and essential project work since award. The proposed variation, to the contract value only, is required to maintain statutory enforcement services, continue essential maintenance, complete agreed control room and infrastructure upgrades, and enable the installation of additional cameras at locations with rising non‑compliance, particularly weight‑restriction breach hotspots.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Morden Town Centre RegenerationCabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a developme...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.