APPLICATION 15/01612/FULL - VARIATION OF CONDITION 1 OF PLANNING PERMISSION 12/01306/MFUL THE SOLAR PV FACILITY SHALL CEASE TO GENERATE ELECTRICITY ON OR BEFORE 28 MARCH 2043 AT SOLAR FARM AT NGR 274160 105292, ELLICOMBE FARM, MORCHARD ROAD (2-26-09)
DecidedPlanning5 papers
Planning Committee decided this item on Wednesday 10 February 2016. Below is the council's own wording, with the papers it was decided on.
RESOLVED that planning permission be granted subject to conditions as recommended by the Head of Planning and Regeneration. (Proposed by Cllr P J Heal and seconded by Cllr DJ Knowles) Notes : i) Cllrs [name removed], K I Busch, [name removed], [name removed], S G Flaws, P J Heal, D J Knowles, F W Letch, B A Moore, J D Squire and R L Stanley made declarations in accordance with the Protocol of Good Practice for Councillors in dealing with Planning matters as they had all received additional information from the applicant; ii) [name removed] spoke on behalf of the applicant; iii) Cllrs [name removed], B A Moore and R L Stanley requested that their vote against the decision be recorded; iv) *Report previously circulated copy attached to signed minutes.
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
15/01612/FULL - VARIATION OF CONDITION (1) OF PLANNING PERMISSION 12/01306/MFUL THE SOLAR PV FACILITY SHALL CEASE TO GENERATE ELECTRICITY ON OR BEFORE 28TH MARCH 2043 - SOLAR FARM LAND AT NGR 274160 105292 ELLICOMBE FARM MORCHARD ROAD DEVON Reason for Report: th At the last planning committee (16 December 2015) Members resolved that the above application be deferred to allow for a briefing paper to be submitted, investigating case histories of such applications at appeal.
PROPOSED DEVELOPMENT Both applications seek to extend the lifetime of the approved development by an additional five years. This would permit the Ellicombe farm PV array originally granted in 2012 (12/01306/MFUL), to th generate electricity until the 28 March 2043. The Palfreys Barton PV array originally granted in 2012 (12/01376/MFUL, would be permitted to th generate electricity until 30 June 1043 if consent is granted. th The Committee report 15/01612/FULL presented on 16 December 2015 are attached as Appendix 1. th The Committee report 15/01613/FULL presented on 16 December 2015 are attached as Appendix 2.
The Officer report 12/01306/MFUL relating to the original grant of planning permission at Ellicombe Farm is attached as Appendix 3.
The Officer report 12/01376/MFUL relating to the original grant of planning permission at Palfreys Barton is attached as Appendix 4.
MATERIAL CONSIDERATIONS AND OBSERVATIONS Your officer has undertaken a detailed search for appeals relating to the extension of time period in solar PV schemes; however it has only been possible to identify one relevant appeal case study. The rd Planning Inspectorate’s appeal reference is APP/D0840/W/15/3002662 and the decision date is 23 June 2015. The appeal related to a solar Photovoltaic facility on land forming part of an agricultural holding referred to Clann Farm in a largely rural area to the south west of the settlement of Bodmin in Cornwall. Planning permission was granted in 2012 for a facility comprising an array of some 6,144 panels covering an area of 4.14 Hectares. The installed capacity from the scheme was measured at th approximately 1.41 MW. The development became operational on 4 November 2014. An application to vary a planning condition to extend the length of time of operation was submitted to Cornwall Council in 2014. The permission originally granted was for 25 years and the application sought to extend this by 5 years to 30. The Council’s principal concern in refusing the extension of time was in relation to an increased period during which a full and flexible access to the land for agriculture would be prevented. The application was refused by Cornwall Council on this basis and subsequently, the applicant submitted an appeal against the decision to the Planning Inspectorate.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
APPLICATION 15/01612/FULL: VARIATION OF CONDITION 1 OF PLANNING PERMISSION 12/01306/MFUL THE SOLAR PV FACILITY SHALL CEASE TO GENERATE ELECTRICITY ON OR BEFORE 28 MARCH 2043 AT SOLAR FARM AT NGR 274160 105292, ELLICOMBE FARM, MORCHARD ROAD (2-26-09)Report
120APPLICATION 15/01612/FULL - VARIATION OF CONDITION 1 OF PLANNING PERMISSION 12/01306/MFUL THE SOLAR PV FACILITY SHALL CEASE TO GENERATE ELECTRICITY ON OR BEFORE 28 MARCH 2043 AT SOLAR FARM AT NGR 274160 105292, ELLICOMBE FARM, MORCHARD ROAD (2-26-09)This decision
APPLICATION 15/01612/FULL - VARIATION OF CONDITION 1 OF PLANNING PERMISSION 12/01306/MFUL THE SOLAR PV FACILITY SHALL CEASE TO GENERATE ELECTRICITY ON OR BEFORE 28 MARCH 2043 AT SOLAR FARM AT NGR 274160 105292, ELLICOMBE FARM, MORCHARD ROAD (2-26-09)This decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.