RESOLVED that: a) Delegated authority be given to the Head of Planning, Economy and Regeneration to submit a bid to the Housing Infrastructure (Marginal Viability) Fund to seek finance for the projects identified within the report; and b) The bid be prioritised to relate to improvements to Junction 28 of the M5 (Proposed by the Chairman) Note : * Report previously circulated, copy attached to minutes.
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
1.1In July 2017 the Government launched its £2.3 billion Housing Infrastructure Fund to finance infrastructure to unlock housing delivery. This funding will be awarded on a highly competitive basis. The Government has made this fund available to: Deliver new physical infrastructure to support new and existing communities; Make more land available for housing in high demand areas, resulting in new additional homes that otherwise would not have been built;
MDDC Report [title] v Support ambitious local authorities who want to step up their plans for growth and make a meaningful difference to overall housing supply; and Enable local authorities to recycle the funding for other infrastructure schemes, achieving more and delivering new homes in the future.
1.2The government fund consists of two separate funding streams which the Department for Communities and Local Government (DCLG) describe as follows:
“• Marginal Viability Funding: This will be used to provide the final, or missing, piece of infrastructure funding in order to get existing sites unblocked quickly or new sites allocated. We expect the infrastructure to be built soon after schemes have been awarded funding, and for the homes to follow at pace.
• Forward Funding: This funding will be used for a small number of strategic and high-impact infrastructure schemes. We may put in the first amount of funding, which then gives the market confidence to provide further investment and make more land available for development and future homes.”
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps...
Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ...
2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.