RESOLVED that: the initial one year contract be awarded to Supplier 3 with an agreed annual cost of £66,000. The Contract had been awarded to the contractor with the highest combined quality/price score with 70% of the total score based on quality and 30% on price. (Proposed by the Chairman) Note : * Report previously circulated, copy attached to minutes.
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
PROJECT MANAGER CONTRACT AWARD FOR CULM GARDEN VILLAGE, CULLOMPTON.
Cabinet Member: Cllr Richard Chesterton Responsible Officer: [name removed], Head of Planning, Economy & Regeneration.
Reason for Report: To advise Members on the results for the procurement of a project manager for the Culm Garden Village project.
RECOMMENDATION: That the initial one year contract is awarded to Supplier 3 with an agreed annual cost of £60,000. The contract has been awarded to the contractor with the highest combined quality/price score with 70% of the total score based on quality and 30% price.
Relationship to Corporate Plan: The Culm Garden Village project contributes to the corporate priorities of facilitating housing and economic growth. The promotion of significant growth east of Cullompton forms part of aim 2 of the priority referring to homes.
Financial Implications: The award of this contract is being made for an initial period of 1 year as is to be funded from capacity money awarded to the project by the Government. As a long term project, it is expected that the Council will wish to retain a project management resource beyond this contract period and due to the potential for renewal, an open tender process through OJEU was undertaken. However, the future extension of a project management resource is dependent upon the success of attracting further capacity funding to support Garden Villages from the Government.
Legal Implications: The contract will be let subject to the council standard terms and conditions for supply of services. The suppliers referred to below are not identified – such information is confidential and not necessary to reach a decision. Any discussion which identifies a supplier must be treated as exempt information and must therefore be pre-empted by passing a resolution in accordance with Section 100A(4) of and Schedule 12A to the Local Government Act 1972, namely that such discussion would result in the disclosure of exempt information as defined in paragraph 3 of Part 1 of Schedule 12A of the said Act, being information relating to the financial or business affairs of any particular person (including the authority holding that information).
Risk Assessment: The tender process has assessed against a series of quality criteria as well as price in order to ensure that the successful supplier not only represents value for money, but is also sufficiently experienced and suited to undertake the role.
1.0INTRODUCTION.
1.1In March 2016 the Department for Communities and Local Government (DCLG) published a prospectus titled ‘Locally-led Garden villages, Towns and MDDC Report: Project Manager for Culm Garden Village 1 V1 Cities’ which aimed to deliver accelerated housing supply through the support of high quality locally-led schemes that will realise a new generation of garden villages, towns and cities. Mid Devon District Council submitted an expression of interest for a ‘Culm’ garden village for up to 5,000 dwellings on land to the east of Cullompton.
1.2The submission Local Plan Review identifies land to the east of Cullompton as a suitable location for strategic growth and includes a draft policy for the allocation of mixed use development including 1,750 dwellings with at least a further 800 post 2033. In addition a neighbourhood planning exercise for Cullompton is well underway and is expected to set out aspirations for community infrastructure /facilities on further land to the east of Cullompton.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps...
Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ...
2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.