RESOLVED that That, in light of the above and reflecting the Cabinet decision of the 3 rd August 2021, approval is given for officers to; a) work to explore other funding opportunities which could deliver the additional funding required to enable the delivery of the Cullompton town centre relief road, and; b) bring a further report before Cabinet as soon as possible in order to update members on the progress of discussions and the options available to the Council in relation to the delivery of the relief road project. (Proposed by Cllr R J Chesterton and seconded by Cllr Mrs N Woollatt) Reason for the decision – there is a need to explore further funding opportunities. Note : *report previously circulated, copy attached to minutes.
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
CULLOMPTON TOWN CENTRE RELIEF ROAD (CTCRR) PROJECT
Cabinet Member(s): Cllr Richard Chesterton, Cabinet Member for Planning and Economic Regeneration Responsible Officer: Richard Marsh, Director of Place.
Reason for Report and Recommendations: To note the update provided in relation to the LUF (Levelling-up Fund) application and approve the recommendations as set out below in order to allow officers to continue to examine potential opportunities to secure the additional funding required to support the delivery of the Cullompton town centre relief road.
RECOMMENDATIONS FOR CABINET:
1. To note that the Council has been advised that, at this time, it has not been successful in securing funding through the Levelling-Up Fund in order to enable the delivery of the Cullompton town centre relief road. And;
2. That, in light of the above and reflecting the Cabinet decision of the 3rd August 2021, approval is given for officers to;
a) work to explore other funding opportunities which could deliver the additional funding required to enable the delivery of the Cullompton town centre relief road, and; b) bring a further report before Cabinet as soon as possible in order to update members on the progress of discussions and the options available to the Council in relation to the delivery of the relief road project.
Financial Implications: There are negligible direct financial consequences of continuing to explore alternative funding arrangement for the Cullompton town centre relief road in the short term. However, members should be aware that the Council has already utilised part of the existing HIF (Housing Infrastructure Fund) funding and that there is a risk that, unless the scheme is implemented and delivered within the pre-agreed timetable, the HIF funding could be withdrawn and that the Council would have to re- pay the amount of funding already utilised, or committed (totalling approx. £635k). As continuing to work on the scheme beyond the end of the calendar year will continue to incur expenditure, members should therefore note that unless an alternative source of funding can be identified (in the short term) which can enable delivery of the CTCRR scheme (through to completion), serious consideration will need to be given to the risks of continuing on the timescales originally envisaged. Options in this regard will be brought back to cabinet once officers have a better understanding of what opportunities exist in relation to securing the required additional funding to unlock delivery.
MDDC Report: CTCRR 1 30th November 2021 Budget and Policy Framework: The CTCRR Scheme has detailed planning consent, is a scheme which has broad public support and is a key scheme in realising wider objectives and ambitions for Cullompton and the district as a whole. Provision is made within the existing Budget framework for the scheme and arrangements are under continual review.
Legal Implications: As set out above, legal obligations apply in relation to the original/existing grant of HIF (Housing Infrastructure Fund) funding and the delivery of the CTCRR scheme. If additional funding is not secured, then the Authority will need to consider its options with the legal implications of the existing Grant Agreement in mind.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps...
Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ...
2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.