Cullompton Town centre Relief Road - Update

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 3 January 2023. Below is the council's own wording, with the papers it was decided on.

Item111

Resolved

To endorse the request for a drawdown and expenditure of a further tranche of the Housing Infrastructure Fund (HIF) funding, totalling £210k, subject to agreement on appropriate indemnity, to enable the progression of further technical work relating to the Cullompton Town Centre Relief Road (CTCRR) until the end of March 2023. (Proposed by Cllr R Chesterton and seconded by Cllr C Slade) Reason for Decision : As stated in the report. Note: *report previously circulated and attached to the minutes
Word for word from the decision Mid Devon published for this meeting. Source: democracy.middevon.gov.uk

Follow this further

Built from Mid Devon's papers

What the report saysPro

Report to Cabinet

CABINET 3 JANUARY 2023

REPORT OF THE DIRECTOR OF PLACE

CULLOMPTON TOWN CENTRE RELIEF ROAD (CTCRR) PROJECT

Cabinet Member(s): Councillor Richard Chesterton, Cabinet Member for Planning and Regeneration Responsible Officer: Richard Marsh, Director of Place

Reason for Report: The report presents a recommendation to request the release of a tranche of Housing Infrastructure Fund (HIF) monies to facilitate the continued progression of technical work relating to the Cullompton Town Centre Relief Road (CTCRR) until the end of March 2023, by which time a decision from Government regarding our pending LUF bid should be received and any Grant Agreement agreed between the parties.

RECOMMENDATIONS: 1. To endorse the request for a drawdown and expenditure of a further tranche of the Housing Infrastructure Fund (HIF) funding, totalling £210k, subject to agreement on appropriate indemnity, to enable the progression of further technical work relating to the Cullompton Town Centre Relief Road (CTCRR) until the end of March 2023.

Financial Implications: The request for a drawdown of further HIF funding (£210k) to support further technical work in relation to the Cullompton Town Centre Relief Road (CTCRR) will need to be subject to an indemnity agreement with Homes England to protect the Authority from the clawing back of any of this expenditure should the scheme ultimately not proceed to completion. Should Homes England not agree to the necessary indemnity provision the request will be withdrawn and work paused. The Council could still be at risk of claw-back from that element of HIF funding already committed (approx. £635k), as set out within the November 2021 report.

Budget and Policy Framework: The CTCRR Scheme has detailed planning permission, is a scheme which has broad public support and is a key scheme in realising wider objectives and ambitions for Cullompton and the district as a whole. Provision is made within the existing Budget framework for the scheme and arrangements are under continual review.

Legal Implications: Legal obligations apply in relation to the original/existing grant of HIF (Housing Infrastructure Fund) funding and the delivery of the CTCRR scheme. The utilisation of a further tranche of the HIF funding, without the risk of clawback, will allow the scheme to progress – but it does not fundamentally address the issue of how to fund delivery of the road and deliver the outputs which the Council would wish to see, or which underpin the grant of the HIF monies should Levelling Up funding not be forthcoming. It will be necessary to keep the other terms of the original HIF grant in mind, and be mindful of the legal implications for the Council to avoid the Council breaching any terms of the HIF Agreement.

Risk Assessment: As set out above, the risk associated with the utilisation of a further tranche of HIF funding is limited if indemnified against clawback of the funding from Homes England. This means that the Council’s financial risk is not increased as a consequence of the expenditure of further HIF money to progress the technical design work associated with the scheme. However, risks do remain for the Council as set out in the report to Cabinet 1st February 2022:

MDDC Report [Cullompton Town Centre Relief Road Project V3] 1. Utilisation of the funding does not fundamentally address the issue that the Council does not yet have the full funds required to deliver the road as currently costed. The Council therefore continues to progress the scheme, without certainty of delivery.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cullompton Town centre Relief Road: UpdateReport 236 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

25 of 31 attended
AS
Andrew SeamanSecretary, present
RM
Richard MarshCouncil Staff, present
AB
Andrew BusbyCouncil Staff, present
DS
Deborah SharpleyCouncil Staff, expected
PL
Philip LangdonCouncil Staff, expected
BD
Councillor Bob DeedAssociate Member, present
CE
Councillor Clive EgintonCommittee Member, present
RC
Councillor Richard ChestertonCommittee Member, present
CD
Councillor Chris DawCommittee Member, present
DK
Councillor Dennis KnowlesCommittee Member, apologies
SP
Councillor Stuart PennyCommittee Member, present
CS
Councillor Colin SladeCommittee Member, present

All 31 on the meeting page

On this subject at Mid Devon

Search all
  1. Cullompton Town centre Relief Road - UpdateThis decision
  2. Cullompton Town Centre Relief RoadDecided
  3. Cullompton Town Centre Masterplan (1:21.25)Decided
  4. Levelling Up Fund Bid and Cullompton Town Centre Relief Road - update (00-32-11)Agreed
  5. Cullompton Town Centre Relief Road Project (1-14-38)Approved
  6. Cullompton Town Centre Relief Road (CTCRR) Project (1-34-04)Approved

More from Mid Devon Cabinet

All decisions
MeetingDecisionOutcome
1 Sep 2026 2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps... Approved Open
4 Aug 2026 Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ... Approved Open
4 Aug 2026 2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart... Noted Open
4 Aug 2026 Air Source Heat Pump (ASHP) Contract 2026-2030The Cabinet had before it a report * from Head of Housing and Health on the Air Source Heat Pump (ASHP) Contract 2026... Decided Open
4 Aug 2026 Notification of Key DecisionsThe Cabinet had before it, and NOTED , the notification of Key Decisions *. Note: * Key Decisions previously circulated. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies