Cabinet, Tuesday 1 February 2022 at 10.00am

Cullompton Town Centre Relief Road Project (1-14-38)

Approved Executive 1 paper

Cabinet approved this item on Tuesday 1 February 2022. Below is the council's own wording, with the papers it was decided on.

Item138

Resolved

RESOLVED that the drawdown and expenditure of a further tranche of the Housing Infrastructure Fund (HIF) funding, totalling £560k be approved, to enable the progression of further feasibility and technical work relating to the Cullompton Town Centre Relief Road. (Proposed by Cllr R J Chesterton and seconded by Cllr Mrs N Woollatt) Reason for the decision – there is a need for the scheme to progress with the use of the funding being made available. Note : *Report previously circulated, copy attached to minutes.
Word for word from the decision Mid Devon published for this meeting. Source: democracy.middevon.gov.uk

Follow this further

Built from Mid Devon's papers

What the report saysPro

Report to Cabinet

CABINET 1 FEBRUARY 2022

CULLOMPTON TOWN CENTRE RELIEF ROAD (CTCRR) PROJECT

Cabinet Member(s): Cllr Richard Chesterton, Cabinet Member for Planning and Economic Regeneration Responsible Officer: Richard Marsh, Director of Place.

Reason for Report and Recommendations: The report presents a recommendation to utilise a further tranche of the Housing Infrastructure Fund (HIF) monies to facilitate the progression of technical work relating to the Cullompton Town Centre Relief Road (CTCRR) over the next 12 months. This will support ongoing work and discussions to identify and secure funding to enable the delivery of the relief road and minimise the overall impact on programme (slippage) to the project.

RECOMMENDATIONS FOR CABINET:

1. To approve the drawdown and expenditure of a further tranche of the Housing Infrastructure Fund (HIF) funding, totalling £560k, to enable the progression of further feasibility and technical work relating to the Cullompton Town Centre Relief Road (CTCRR).

Financial Implications: The drawdown of further HIF funding (£560k) to support further feasibility and technical work in relation to the Cullompton Town Centre Relief Road (CTCRR) will have limited financial implication for the Authority owing to the fact that Homes England are prepared to offer the Authority an indemnity to protect the Authority from the clawing back of any of this expenditure should the scheme ultimately not proceed to completion. For clarity: the Council could still be at risk of claw-back from that element of HIF funding already committed (approx. £635k), as set out within the November 2021 report.

Budget and Policy Framework: The CTCRR Scheme has detailed planning consent, is a scheme which has broad public support and is a key scheme in realising wider objectives and ambitions for Cullompton and the district as a whole. Provision is made within the existing Budget framework for the scheme and arrangements are under continual review.

Legal Implications: Legal obligations apply in relation to the original/existing grant of HIF (Housing Infrastructure Fund) funding and the delivery of the CTCRR scheme. The utilisation of a further tranche of the HIF funding, without the risk of clawback, will allow the scheme to progress – but it does not fundamentally address the issue of how to fund delivery of the road and deliver the outputs which the Council would wish to see, or which underpin the grant of the HIF monies.

MDDC Report: CTCRR 1 February 2022 It will be necessary to keep the other terms of the original HIF grant in mind, and be mindful of the legal implications for the Council to avoid the Council breaching any terms of the HIF Agreement.

Risk Assessment: As set out above, the risk associated with the utilisation of a further tranche of HIF funding is limited, as the Council is to be indemnified against clawback of the funding from Homes England. This means that the Council’s financial risk is not increased as a consequence of the expenditure of further HIF money to progress the technical design work associated with the scheme.

However, risks do remain for the Council. Notably;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cullompton Town Centre Relief Road Project (1-14-38)Report 128 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 36 attended
BD
Councillor Bob DeedAssociate Member, present
RC
Councillor Richard ChestertonCommittee Member, present
CD
Councillor Chris DawCommittee Member, present
BE
Councillor Bob EvansCommittee Member, present
DK
Councillor Dennis KnowlesCommittee Member, apologies
AM
Councillor Andrew MooreCommittee Member, present
CS
Councillor Colin SladeCommittee Member, present
NW
Councillor Nikki WoollattCommittee Member, present
SW
Stephen WalfordOfficer, in attendance
CO
Carole OliphantSecretary, expected
MD
Maria De LeiburneOfficer, expected
AJ
Andrew JarrettOfficer, in attendance

All 36 on the meeting page

On this subject at Mid Devon

Search all
  1. Cullompton Town Centre Relief Road Project (1-14-38)This decision
  2. Cullompton Town Centre Relief RoadDecided
  3. Cullompton Town Centre Masterplan (1:21.25)Decided
  4. Cullompton Town centre Relief Road - UpdateAgreed
  5. Levelling Up Fund Bid and Cullompton Town Centre Relief Road - update (00-32-11)Agreed
  6. Cullompton Town Centre Relief Road (CTCRR) Project (1-34-04)Approved

More from Mid Devon Cabinet

All decisions
MeetingDecisionOutcome
1 Sep 2026 2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps... Approved Open
4 Aug 2026 Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ... Approved Open
4 Aug 2026 2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart... Noted Open
4 Aug 2026 Air Source Heat Pump (ASHP) Contract 2026-2030The Cabinet had before it a report * from Head of Housing and Health on the Air Source Heat Pump (ASHP) Contract 2026... Decided Open
4 Aug 2026 Notification of Key DecisionsThe Cabinet had before it, and NOTED , the notification of Key Decisions *. Note: * Key Decisions previously circulated. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies