Monmouthshire County Council
Cabinet, Monday 30 March 2026 at 4.30pm

ACQUISITION OF LAND AT LLANTHONY VALLEY OVER THE LENGTH OF THE SLIP ZONE AT NEUADD STRAIGHT

Approved Executive 1 paper

AI summaryMonmouthshire Cabinet approves buying a 1.5-acre strip of land on Llanthony Valley Road for £100,000 to enable a highway diversion at the Neuadd Straight slip zone, reopening access for the valley community.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved
Money£100,000
What happens nextConstruction to followHighways Authority to carry out works after the Cabinet decision.
Who it affectsLlanthony Valley residents and businessesReopens road access currently cut off by a land slip.

What was decided

Cabinet approved the acquisition of a 1.5-acre strip of land on Llanthony Valley Road at Neuadd Straight to secure long-term access for residents and businesses. Report P7

Authority to finalise exchange and completion was delegated to the Chief Officer for Resources, working with the Cabinet Member for Resources. Report P7

Why

A land slip at Neuadd Straight, following Storm Claudia, has closed the road and forced a diversion of approximately 70 miles, cutting off residents, businesses, HGVs and tourism from the Llanthony Valley. Report P21, P29, P30

Officers reviewed temporary and permanent solutions and concluded that a highway diversion requiring third party land was the only viable option; the landowner has engaged with testing and design, which is now finalised with a preferred contractor identified. Report P29

Acquiring the land is also intended to future-proof the highway against further soil erosion and slip events. Report P21, P30

What happens next

The Chief Officer for Resources will finalise exchange and completion on the terms set out in the report. Report P7

The Highways Authority will then undertake the necessary construction works for the highway diversion. Report P32

The money

  • £100,000 Proposed purchase price for the 1.5-acre strip, exclusive of surveyor and legal fees; exceeds market value due to land premium applied. Report 7.1

Options considered

  • Chosen: Permanent highway diversion requiring purchase of third party land. Identified as the only viable option after reviewing temporary and permanent solutions. Report P24, P29

Implications

  • Financial: Purchase price of £100,000 plus additional surveyor and legal fees; price set above market value to reflect the opportunity. Report 7.1
  • Environment and climate: Loss of 1.5 acres of agricultural land, with negative impacts on biodiversity and local wildlife acknowledged. Report P19, P30
  • Environment and climate: Reopening the road avoids the increased carbon footprint of the current 70-mile diversion. Report P30
  • Risk: Acquiring a wider corridor of land allows the council to respond more swiftly to any future land slip affecting the highway. Report P21, P30
  • Equalities: Integrated Impact Assessment identified no impacts on protected characteristic groups, but notes significant socio-economic disruption for the local community from the current closure. Report P9, P10, P11, P12, P13, P14

Who and where

  • Residents and businesses in the Llanthony Valley, currently disconnected by the road closure Report P29, P30
  • Local farming businesses that HGVs cannot currently reach Report P18, P20
  • Tourists visiting the Llanthony Valley Report P18, P20
  • The landowner of the 1.5-acre strip, who has engaged with the council on testing and design Report P29

Timeline

  • 18th March 2026: Integrated Impact Assessment for Landlord Services dated. Report P8
  • 2026-03-30: Cabinet decision taken to approve the land acquisition and delegate completion.
  • Post Cabinet decision: Highways Authority to undertake the necessary construction works. Report P32

Plain English for the jargon

  • Slip zone: The section of land at Neuadd Straight that has moved or subsided, undermining the highway.
  • HGV: Heavy Goods Vehicle.
  • DMT: Departmental Management Team; Infrastructure DMT was consulted on this proposal.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item3a

Resolved

That Cabinet approves the acquisition of the land to secure long-term access for residents and businesses in the Llanthony Valley over the length of the slip zone at Neuadd Straight. That Cabinet approve the delegation of responsibility to the Chief Officer for Resources to finalise exchange and completion, on terms as captured within this report.
Word for word from the decision Monmouthshire published for this meeting. Source: democracy.monmouthshire.gov.uk

Follow this further

Built from Monmouthshire's papers

What the report saysPro

Report to Cabinet

SUBJECT: ACQUISITION OF LAND AT LLANTHONY VALLEY OVER THE LENGTH OF THE SLIP ZONE AT NEUADD STRAIGHT

MEETING: CABINET

DATE: MARCH 2026

DIVISION/WARDS AFFECTED: ALL

This decision has been authorised by the Chief Executive and Chair of Place Scrutiny as an urgent decision of the Executive in line with section 32.15 of the Council's Constitution. This decision will therefore not be subject to the usual call-in procedures. A report will be presented to the next available meeting of Full Council outlining the reasons for the urgency as per 32.15.3 of the Constitution.

1. PURPOSE 1.1 To seek authorisation to proceed with the purchase of a 1.5-acre strip of land on the Llanthony Valley Road at Neuadd Straight to enable the Council to secure long-term access for residents and businesses.

1.2To delegate authority to exchange and complete to the Chief Officer for Resources, in liaison with the Cabinet Member for Resources.

2. RECOMMENDATIONS: That Cabinet: 2.1 Approves the acquisition of the land to secure long-term access for residents and businesses in the Llanthony Valley over the length of the slip zone at Neuadd Straight. 2.2 Approve the delegation of responsibility to the Chief Officer for Resources to finalise exchange and completion, on terms as captured within this report.

3. KEY ISSUES:

3.1A landslip on the Llanthony Valley road at Neuadd Straight has resulted in a full road closure. Storm surge from the fields above the road and the river below combined to cause a landslip including a section within the carriageway. 3.2 Access for over 50 residential and business properties was compromised with the only access available over the Gospel Pass and 35-mile diversion. 3.3 The businesses are reliant on delivery of animal food for livestock and access for vistors to the wide range of tourism businesses, including the Llanthony Priority, that are prevalent throughout the valley and in the foot of Black Mountains and Bannau Brycheiniog region. 3.4 The residents of Llanthony and Capel Y Ffin are reliant on access to Abergavenny for work, medical care, shopping, post deliveries etc and access for those basic services results in an additional 70-mile diversion. 3.5 Emergency Response services have rerouted resources to provide response but have identified potential delays due to the extended alternative route travel time. 3.6 Support from MACA was not available as the Emergency Service response at a local level was being managed with alternative arrangements in place. 3.7 Council services like waste and recycling, winter and highway maintenance have continued to provide services utilising additional resources and costs. 3.8 Negotiations have been undertaken with the respective landowner to acquire land to provide a highway diversion, and a value in principle agreed that enables the transaction to complete at speed and works commence.

4. EQUALITY AND FUTURE GENERATIONS EVALUATION (INCLUDES SOCIAL JUSTICE, SAFEGUARDING AND CORPORATE PARENTING):

4.1The Equality and Future Generations Evaluation Assessment detailed in Appendix 1, details the following positive impacts which include:

 Reinstating access for over 50 residential and business properties that have been compromised, with their only access being via a 35-mile diversion.  Reinstating the business access for the delivery of animal food for livestock and access for visitors to service a wide range of tourism businesses.

4.2There are therefore no negative impacts associated with this proposal.

5. OPTIONS APPRAISAL

5.1All engineering options to repair the road damaged by the slip were reviewed and discounted due to deliverability and costs.

5.2Other alternative options to improve tracks and trails through the valley were reviewed and discounted due to deliverability and topographical constraints.

5.3The option to purchase the land and re-align the road at the point of the slip is considered the only viable option.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ACQUISITION OF LAND AT LLANTHONY VALLEY OVER THE LENGTH OF THE SLIP ZONE AT NEUADD STRAIGHTReport 744 KB DownloadRead as text

At this meeting

Whole meeting
3aACQUISITION OF LAND AT LLANTHONY VALLEY OVER THE LENGTH OF THE SLIP ZONE AT NEUADD STRAIGHTThis decision

Who was there

9 of 26 attended
JD
Jonathan DaviesOfficer, expected
CC
County Councillor Mary Ann BrocklesbyCommittee Member, present
CC
County Councillor Paul GriffithsCommittee Member, apologies
CC
County Councillor Catrin MabyCommittee Member, present
RM
Robert McGowanOfficer, expected
PD
Peter DaviesOfficer, present
HI
Hazel IlettOfficer, expected
PM
Paul MatthewsOfficer, expected
WM
Will McLeanOfficer, expected
JR
Jane RodgersOfficer, expected
JP
John PearsonOfficer, expected
NP
Nicola PerryOfficer, present

All 26 on the meeting page

On this subject at Monmouthshire

Search all
  1. ACQUISITION OF LAND AT LLANTHONY VALLEY OVER THE LENGTH OF THE SLIP ZONE AT NEUADD STRAIGHTThis decision
  2. Acquisition of plots of land for the Undy to Rogiet Severn Tunnel Junction (STJ) Links Active Travel RouteApproved
  3. Proposed acquisition of land - magorDecided

More from Monmouthshire Cabinet

All decisions
MeetingDecisionOutcome
11 Nov 2026 Local Growth Fund Year 2 and 3 2027- 2029That the Cabinet considered the draft Local Growth Fund proposals for Years 2 and 3. That Cabinet approves the portfo... Approved Open
11 Nov 2026 Future of Former Tudor Street Day Centre, AbergavennyTo terminate the existing Tenancy at Will agreement with The Gathering Community CIO. To Approve the commencement of ... Agreed Open
11 Nov 2026 Medium Term Financial Plan Update - October 2026That Cabinet notes the refreshed MTFP update at Appendix 1, including the current scenario based planning range for 2... Decided Open
14 Oct 2026 Performance and Overview Scrutiny Committee - Feedback to Cabinet of Meeting held on 29th September 2026Noted. Noted Open
14 Oct 2026 Place Committee - Feedback to Cabinet of Meeting held on 1st October 2026Noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies