That the objections be overruled and the proposed Prohibition of Waiting at Any Time Traffic Regulation Order at St. Illtyd’s Drive, Church Crescent, St. Catherine’s Road and Church Road, Baglan (as detailed in Appendix A) be implemented on site and the objectors be informed accordingly. That the objections be overruled and the proposed Prohibition of Waiting at Any Time Traffic Regulation Order at St. Illtyd’s Drive, Church Crescent, St. Catherine’s Road and Church Road, Baglan (as detailed in Appendix A) be implemented on site and the objectors informed accordingly. Reason for To prevent indiscriminate parking in the interest of highway safety. Implementation of The decision will be implemented after the three day call in period. Consultation: This item has been subject to external consultation.
Word for word from the decision Neath Port Talbot published for this meeting.Source: democracy.npt.gov.uk
Report to Streetscene and Engineering Cabinet Board
Purpose of the report
To consider the objections received following the advertisement of the above scheme, as indicated in Appendix A.
Executive summary
Four letters objecting to the scheme were received.
The report outlines the objections and the recommendations for the scheme.
Background
The local Member for Baglan has requested the scheme as part of the Members Community Fund. The scheme included the construction of disabled crossings, the installation of Araf/Slow markings and the proposed double yellow lines to prevent indiscriminate parking and also to leave the crossings clear so that pedestrians may cross the road. The Traffic Regulation Order does not prohibit loading or unloading. Therefore, Funerals and Weddings should not be affected by the proposal. Financial Impacts:
The work will be funded from the Member’s Community Fund.
Integrated Impact Assessment:
A first stage Impact Assessment has been undertaken to assist the Council in discharging its legislative duties (under the Equality Act 2010, the Welsh Language Standards (No.1) Regulations 2015, the Well-being of Future Generations (Wales) Act 2015 and the Environment (Wales) Act 2016.
The first stage assessment, attached at Appendix B, has indicated that a more in-depth assessment is not required. A summary is included below:-
A full impact assessment is not required as the proposed Traffic Regulation Order will provide a benefit for the local community.
Valleys Communities Impacts:
No implications.
Workforce Impacts:
No implications.
Legal Impacts:
The scheme was advertised for a 21-day period as part of the statutory process.
Risk Management Impacts:
No implications.
Consultation
A consultation exercise was undertaken in January/February 2020 and four letters objecting to the scheme were received:-
The first objector has concerns that patrons using St. Catherine’s Church will not be able to stop outside the Church, in particular for Weddings and Funerals. The second objector is concerned about displaced parking leading to vehicles parking on both sides of the road from Pentwyn Baglan Road along Church Crescent when there is a service on at the Church.
The third objector is concerned that the proposed double yellow lines will de- value the property if they were to sell. The objector also raised concerns about their H-Bar marking and that family will have nowhere to park when they visit.
The fourth objector is concerned about elderly members of the community that attend the Church will not be able to park directly outside the Church. They are also concerned that weddings and funerals will not be able to load and unload during services.
The objections have been discussed with the local Councillor who fully supports the scheme as advertised.
Recommendations
That the objections are overruled and the proposed Prohibition of Waiting at Any Time Traffic Regulation Order at St. Illtyd’s Drive, Church Crescent, St. Catherine’s Road and Church Road, Baglan (as detailed in Appendix A) be implemented on site and the objectors be informed of the decision accordingly.
Reasons for Proposed Decision:
To prevent indiscriminate parking in the interest of highway safety.
Implementation of Decision:
The decision is proposed for implementation after the three day call in period.
Appendices
Appendix A – Plan: St. Illtyd’s Drive, Baglan – Proposed Traffic Regulation Orders
Appendix B – First Stage IIA
List of Background Papers:
None. Officer Contact:
Martin Brumby, Project Manager Highways - Engineering & Transport Tel. No: 01639 686013 Email: [email protected]
Jonathan Davies Assistant Engineer - Engineering & Transport Tel. No: 01639 686494 Email: [email protected] Appendix A Appendix B
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Streetscene and Engineering Cabinet Board at Neath Port Talbot and we tell you when its next papers are published, before the meeting rather than after it.
Traffic Regulation Orders - GlynneathHaving had due regard to the integrated impact assessment, approval be granted to advertise the B4242 Pontneathvaugha...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.