List of Approved Contractors

Approved Executive 1 paper

Streetscene and Engineering Cabinet Board approved this item on Friday 28 February 2020. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

That the following Contractors be included on the Approved List of Contractors in the categories below:- Firm Category W.F.James & Son Ltd (T/A Emroch Landscapes) 75, 77, 84, 102, 104 R & R Waterblock (T/A Wales Roofing) 17a,17b,17c,17d,17e (up to the value of £40k) Ezra Property & Environmental Services Ltd 15, 16, 84, 89 Vanguard Roofing Ltd 17a, 17b Ibex Technical Access Ltd 25, 27, 85, 88, 89, 93, 96, 97, 98, 101, 102, 105, 111(Rope Access) That the following contractors be included on the Approved List of Contractors in the categories below:- Firm Category W.F.James & Son Ltd (T/A Emroch Landscapes) 75, 77, 84, 102, 104 R & R Waterblock (T/A Wales Roofing) 17a,17b,17c,17d,17e (up to the value of £40k) Ezra Property & Environmental Services Ltd 15, 16, 84, 89 Vanguard Roofing Ltd 17a, 17b Ibex Technical Access Ltd 25, 27, 85, 88, 89, 93, 96, 97, 98, 101, 102, 105, 111 (Rope Access) Reason for To keep the List of Approved Contractors up to date and as far as possible, ensure a competitive procurement process. These recommendations to be adopted for the purpose of supplying a for invitation to tender within the relevant category. Implementation of The decisions will be implemented after the three day call in period.
Word for word from the decision Neath Port Talbot published for this meeting. Source: democracy.npt.gov.uk

Follow this further

Built from Neath Port Talbot's papers

What the report saysPro

Report to Streetscene and Engineering Cabinet Board

Purpose of the report

To seek Members’ approval to amend the List of Approved Contractors.

Executive summary

To seek approval for Contractors to be included on the List of Approved Contractors and for Contractors that have not completed the Health and Safety renewal checks to be removed from the list.

Background

Members will be aware that on previous occasions reports concerning the List of Approved Contractors have been presented to Cabinet Board.

The process gives local companies an opportunity to provide goods and services to the Council.

The full list of categories is set out in Appendix A for your information. Financial Impacts

No implications.

Integrated Impact Assessment

A first stage impact assessment has been undertaken to assist the Council in discharging its legislative duties (under the Equality Act 2010, the Welsh Language Standards (No.1) Regulations 2015, the Well-being of Future Generations (Wales) Act 2015 and the Environment (Wales) Act 2016.

The first stage assessment, attached at Appendix B, has indicated that a more in-depth assessment is not required. A summary is included below:-

The report is seeking approval to include additional contractors onto the existing List of Approved Contractors. This does not affect any group of people and or impact the Welsh language, biodiversity or the five ways of working.

Valleys Communities Impacts

No implications.

Workforce Impacts

No implications.

Legal Impacts

No implications.

Risk Management Impacts

No implications.

Consultation

There is no requirement for external consultation on this item. Recommendations

That the Approved list is amended as follows:

Firms to be added to the List of Approved Contractors

The following firms have applied to be included on the list and have passed the required assessments:-

Firm Category

W.F.James & Son Ltd (T/A Emroch 75, 77, 84, 102, 104 Landscapes) R & R Waterblock(T/A Wales Roofing) 17a,17b,17c,17d,17e (up to the value of £40k) Ezra Property & Environmental Services Ltd 15, 16, 84, 89

Vanguard Roofing Ltd 17a, 17b

Ibex Technical Access Ltd 25, 27, 85, 88, 89, 93, 96, 97, 98, 101, 102, 105, 111(Rope Access)

Reasons for Proposed Decision

To keep the List of Approved Contractors up to date and as far as possible, ensure a competitive procurement process.

These recommendations to be adopted for the purpose of supplying a List of Approved Contractors for invitation to tender within the relevant category.

Implementation of Decision

The decision is proposed for implementation after the three day call in period.

Appendices

Appendix A - List of Categories for List of Approved Contractors

Appendix B - First Stage IIA List of Background Papers

None

Officer Contact

Hasan Hasan, Engineering Manager Tel. No: 01639 686463 Email: [email protected]

Amanda Phillips, Programme & Commissioning Manager Tel. No: 01639 686483 Email: [email protected] Appendix A

General Services 1. Signs 2. Plant Hire 3. Security 4. Clinical Waste 5. Pest Control 6. Re-Cycling 7. Waste Disposal (e.g. Car, Computers, Steel) 8. Crowd Control 9. Traffic Management 10. Portable Buildings 11. Scaffolding

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
List of Approved ContractorsReport 1.3 MB DownloadRead as text

At this meeting

Whole meeting

On this subject at Neath Port Talbot

Search all
  1. List of Approved ContractorsThis decision
  2. List of Approved ContractorsApproved
  3. List of Approved ContractorsApproved
  4. List of Approved ContractorsApproved
  5. List of Approved ContractorsDecided
  6. List of Approved ContractorsApproved

More from Neath Port Talbot Streetscene and Engineering Cabinet Board

All decisions
MeetingDecisionOutcome
28 Jan 2022 Appointment of ChairpersonAgreed that Councillor M.Harvey be appointed Chairperson for the meeting . Agreed Open
28 Jan 2022 Minutes of Previous MeetingThat the Minutes of 17 December 2021, be approved. Approved Open
28 Jan 2022 Traffic Regulation Orders - GlynneathHaving had due regard to the integrated impact assessment, approval be granted to advertise the B4242 Pontneathvaugha... Approved Open
28 Jan 2022 Traffic Regulation Orders – Tonna and AberdulaisHaving had due regard to the integrated impact assessment, the objections to the B4434 Dulais Fach Road, Station Road... Decided Open
28 Jan 2022 New Post Code for Bro Nantfer in Gwaun Cae GurwenHaving due regard to the first stage integrated impact assessment, residents of Bro Nantfer be consulted on whether t... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies