Traffic Order: Old Road, Briton Ferry, Neath

Decided Executive 1 paper

Streetscene and Engineering Cabinet Board decided this item on Friday 28 February 2020. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

That the objections be overruled and the prohibition of waiting, loading and unloading at any time traffic regulation order at Old Road, Briton Ferry, Neath be implemented on site as advertised (as detailed in Appendix A of the circulated report) and the objectors informed accordingly. That the objections be overruled and the Prohibition of Waiting, Loading and Unloading at Any Time Traffic Regulation Order at Old Road, Briton Ferry, Neath be implemented on site as advertised (as detailed in Appendix A of the circulated report) and the objectors informed accordingly. Reason for To maintain a safe crossing facility in the interest of highway safety. Implementation of The decision will be implemented after the three day call in period. Consultation: This item has been subject to external consultation.
Word for word from the decision Neath Port Talbot published for this meeting. Source: democracy.npt.gov.uk

Follow this further

Built from Neath Port Talbot's papers

What the report saysPro

Report to Streetscene and Engineering Cabinet Board

Purpose of the report

To consider the objections received following the advertisement of the above scheme, as indicated in Appendix A.

Executive summary

Seven letters/e-mails objecting to the scheme were received.

The report outlines the objections and the recommendations for the scheme.

Background

A dropped crossing facility is required outside Ysgol Carreg Hir, Old Road, Briton Ferry to allow school children and pedestrians to cross the road safely. After discussion with the local Councillor, it was decided to propose a No Waiting, No Loading or Unloading at Any Time Traffic Order on Old Road, Briton Ferry to prevent vehicles from obstructing the proposed dropped crossing. Financial Impacts:

The work is to be funded from the Revenue Works Programme.

Integrated Impact Assessment:

A first stage Impact Assessment has been undertaken to assist the Council in discharging its legislative duties (under the Equality Act 2010, the Welsh Language Standards (No.1) Regulations 2015, the Well-being of Future Generations (Wales) Act 2015 and the Environment (Wales) Act 2016.

The first stage assessment, attached at Appendix B, has indicated that a more in-depth assessment is not required. A summary is included below:-

A full impact assessment is not required as the proposed dropped crossing facility will provide a safe location for pedestrians to access Ysgol Carreg Hir.

Valleys Communities Impacts:

No implications.

Workforce Impacts:

No implications.

Legal Impacts:

The scheme was advertised for a 21-day period as part of the statutory process.

Risk Management Impacts:

No implications.

Consultation

A consultation exercise was undertaken in January 2020.

Seven letters/e-mails objecting to the scheme were received. The objections are summarised as follows:- 1. The resident believes that the proposed traffic order will impact upon them being able to park outside their property and inconvenience them exiting their driveway safely.

2. The resident states that the proposed traffic order is a waste of money as no children cross at the proposed location and if implemented motorists will not adhere to the restrictions. They also state that parking is already difficult in the area especially on weekends when there are football matches being played.

3. The resident objects to the scheme as the proposed traffic order and dropped crossing will prevent them parking outside their property. They have a disabled family member residing in the household that has activities arranged several times a week who requires transport to collect them outside their property.

4. The resident believes that the proposed traffic order will be ignored by motorists who already ignore the existing traffic orders in the area. The proposed parking restrictions will impact further upon the residents of Old Road that already have difficulty parking in the area.

5. The resident objects to the proposals as they have no access to off-street parking. They are concerned that they will not be able to park safely close to their property.

6. The resident objects to the proposals stating that when exiting their driveway they would cross the proposed crossing area. They also have concerns that the already limited availability of parking in the area will become worse. The recently implemented traffic calming has reduced vehicular speeds on Old Road therefore is the crossing facility required.

7. The resident is concerned that they will not be able to park outside their property. There are already parking problems on Old Road and the proposed traffic regulation order will only cause further parking issues.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Traffic Order: Old Road, Briton Ferry, NeathReport 1.3 MB DownloadRead as text

At this meeting

Whole meeting

On this subject at Neath Port Talbot

Search all
  1. Traffic Order: Old Road, Briton Ferry, NeathThis decision
  2. B4242 Pontneathvaughan Road, Glynneath - New Car Park Development- Proposed Traffic Regulation OrdersAgreed
  3. (Park Lane, Brynamman) (One Way Traffic) and (No Entry) Order 2026Decided
  4. Proposed Traffic Regulation Orders associated with the Welsh Governments Grant Funded Active Travel, Learner Travel Wales, 20mph Speed Limit National Roll Out, Safe Routes in Communities and Capital Road Safety Programme of Work 2026-2027Approved
  5. B4242 Pontneathvaughan Road, Glynneath, New Car Park Development. Proposed Traffic Regulation OrdersApproved
  6. Proposed No Waiting, No Loading At Any Time and Limited Waiting Traffic Regulation Orders in association with Aberavon Seafront 2026.Approved

More from Neath Port Talbot Streetscene and Engineering Cabinet Board

All decisions
MeetingDecisionOutcome
28 Jan 2022 Appointment of ChairpersonAgreed that Councillor M.Harvey be appointed Chairperson for the meeting . Agreed Open
28 Jan 2022 Minutes of Previous MeetingThat the Minutes of 17 December 2021, be approved. Approved Open
28 Jan 2022 Traffic Regulation Orders - GlynneathHaving had due regard to the integrated impact assessment, approval be granted to advertise the B4242 Pontneathvaugha... Approved Open
28 Jan 2022 Traffic Regulation Orders – Tonna and AberdulaisHaving had due regard to the integrated impact assessment, the objections to the B4434 Dulais Fach Road, Station Road... Decided Open
28 Jan 2022 New Post Code for Bro Nantfer in Gwaun Cae GurwenHaving due regard to the first stage integrated impact assessment, residents of Bro Nantfer be consulted on whether t... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies