AGREED (unanimously) that: (a) the variations detailed in Appendix C to the report be approved; and (b) the proposed resourcing of the Capital Programme be noted. Reason for Decision To enable the Capital Programme to be amended to reflect changes to resources available and better clarity of the cost and phasing of projects.
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
APPENDIX A General Fund - Actual spend and forecast for the year
Revised Budget Current Additional Total 17-18 Actuals to Project Capital Description Project Manager outstanding anticipated Projected Variance Comments - Spend to date (Following P&F period 9 orders spend in year spend in year 30.11.17)
TA1211 Newark, New Leisure Centre Matt Finch 226,763 215,688 3,595 7,480 226,763 0 Project Complete
TA1215 Extension to Newark Leisure Centre Car Park Matt Finch / Kirsty Cole 0 0 0 205,500 205,500 205,500 As per P&F 30.11.17
Matt Finch / Leanne TA1216 Leisure Provision in the West 0 0 0 250,000 250,000 250,000 Reported to this meeting 22.2.18 Monger TA3050 National Civil War Centre Matt Finch 341,976 341,976 0 0 341,976 0 Project Complete TA3052 Palace Theatre/Museum Integration Matt Finch 20,278 20,278 0 0 20,278 -0 Project Complete TA3053 Museum Improvements Matt Finch 465,734 3,970 0 461,764 465,734 0 Update technology as part of moving ahead. TA3286 Information Technology Investment Sharon Parkinson 657,273 412,035 65,200 116,259 593,495 -63,778 Orders almost complete. AV snagging still ongoing.
TA CUSTOMERS 1,712,024 993,947 68,795 1,041,003 2,103,746 391,722
Andrew Kirk (Veh) / Orders raised are for vehicles due to be TB2253 Vehicles & Plant (NSDC) 345,000 0 22,600 0 22,600 -322,400 Matt Finch (Leis Equip) received in 2018/19. Tender for conservation management plan TB3154 Castle Gatehouse Project Phil Beard 80,000 0 -2,935 82,935 80,000 0 accepted. Projected spend - £80k in 17/18, remainder in 18/19. NSH potentially taking on responsibulity for TB3158 Hawtonville School Playing Field Phil Beard 23,123 0 0 23,123 23,123 0 HCC. Maybe not required. PB to check. TB3159 Humberstone Road Open Space, Southwell Phil Beard 575 575 0 0 575 0 Complete. Trfd open space to STC TB6145 Grant to Farndon Sports Pavilion Phil Beard 14,631 0 0 14,631 14,631 0 PB been in touch with FPC. PB to confirm Vicar Water scheme - original project TB6147 Contribution to Cycle Route Improvements Phil Beard 7,634 0 0 7,634 7,634 0 complete. Remaining money PB would like to spend on further improvements. Delayed to consider additional costs - report TB6148 Lorry Carpark - Extension Alan Batty 100,000 50,894 0 49,106 100,000 0 due to go to ED in March 2018. TB6149 Lorry Carpark - Health and Safety Alan Batty 15,820 15,820 0 0 15,820 0 Complete. S106 schemes added to the Capital Farnsfield PC S106 Re Ash Farm AG909 Comm TB6150 Andy Hardy/Phil Beard 128,544 128,544 0 0 128,544 0 Programme. Fully funded expenditure from Fac & SANGS S106 contributions. S106 schemes added to the Capital Ollerton & Boughton TC S106 AG767 Trf of Open TB6151 Andy Hardy/Phil Beard 164,616 164,616 0 0 164,616 0 Programme. Fully funded expenditure from Space & Play S106 contributions. S106 schemes added to the Capital Nottingham Road Southwell S106 AG966 Trf of TB6152 Andy Hardy/Phil Beard 69,208 69,208 0 0 69,208 0 Programme. Fully funded expenditure from Open Space provision S106 contributions. S106 schemes added to the Capital TB6153 Cricket Facilities Kelham Rd - S106 Andy Hardy 0 0 0 52,004 52,004 52,004 Programme. Fully funded expenditure from S106 contributions. S106 schemes added to the Capital TB6154 Community & Activity Village - S106 Andy Hardy 0 0 0 306,183 306,183 306,183 Programme. Fully funded expenditure from S106 contributions. Revised Budget Current Additional Total 17-18 Actuals to Project Capital Description Project Manager outstanding anticipated Projected Variance Comments - Spend to date (Following P&F period 9 orders spend in year spend in year 30.11.17) S106 schemes added to the Capital S106 Off Site Sports Provision Community & TB6155 Andy Hardy 0 0 0 166,068 166,068 166,068 Programme. Fully funded expenditure from Activity Village S106 contributions. TB6156 Clipstone Welfare S106 Andy Hardy/Phil Beard 0 0 0 49,180 49,180 49,180 Reported to this meeting 22.2.18
TB COMMUNITY 949,151 429,657 19,666 750,863 1,200,186 251,035
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Programme 2022/23 to 2025/26AGREED (unanimously) that the General Fund schemes set out at Appendix A to the report, and the Housing Services sche...
Newark Castle - Condition SurveyAGREED (unanimously) that: (a) the inclusion of this work in the 2022/23 Capital Programme for £570,000 be approved, ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.