AGREED (unanimously) that: (a) the transfer of open space Section 106 funds totalling £49,180 arising from AG842A to Clipstone Welfare be approved, subject to an appropriate legal agreement being entered into by Clipstone Welfare; and (b) the sum of £49,180 be added to the Council’s Capital Programme in order that its expenditure can be appropriately recorded and monitored. Reason for Decision To ensure that S106 funds are spent in an appropriate fashion, for the benefit of the community in which they were generated and that their use is properly monitored.
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
1.1To seek approval for the transfer of S106 funds to Clipstone Welfare.
2.0Background Information
2.1At its meeting held on 9 March 2017 Full Council agreed that the remit of the Policy & Finance Committee should be amended to make clear that the determination of how S106 monies should be applied or obligations fulfilled falls within the remit of that Committee rather than the Planning Committee.
2.2In 2010 the Council received S106 funds to the value of £85,790 from the Gladedale Homes development on Mansfield Road, Clipstone. These were generated by a S106 agreement (AG842A) which stated that, in relation to open space, there should be a financial contribution for the purposes of providing off-site children’s playing space. The actual wording of the agreement was that the contribution should be used ‘towards the provision, improvement and maintenance of children’s playing space in Clipstone as the Council in its absolute discretion shall decide’. Despite a number of projected schemes being brought forward over the past 7 years there has been only limited use of the funds and £78,047 remains unspent. There is no time limit attached to the expenditure of the funds.
3.0Proposals
3.1Clipstone Welfare, in partnership with Clipstone Parish Council, is planning to provide sports and play facilities for older children on land it owns adjacent to Clipstone Youth Centre and has requested that the District Council release £49,180 of S106 open space funds from AG842A to allow it to progress this project. The Welfare wishes to provide a new multi-use games area, together with lighting and fencing, skate equipment, fitness equipment for adults and young people and other play facilities. The Welfare has already received grants from Nottinghamshire County Council (£40,000), the National Lottery (£10,000) and the Garfield Weston Foundation (£20,000) towards the project. The total cost of the project is £109,180, however Clipstone Welfare wishes to retain £10,000 of the Garfield Weston grant to enable it to carry out repairs to the youth club building. Clipstone Parish Council is supportive of the project and has agreed to assist with the inspection and maintenance of the facilities once they are in place.
3.2Prior to the funds being transferred Clipstone Welfare will be required to enter into a legal agreement which binds it to spending the funds in a manner which is consistent with the S106 agreement.
Equalities implications
4.1The design of the new facilities will take full account of equalities implications. 5.0 Comments of Director - Resources and s151 Officer
5.1Confirmation that the s106 funds are currently available via the Council’s balance sheet.
6.0RECOMMENDATIONS that:
(a) the transfer of open space Section 106 funds totalling £49,180 arising from AG842A to Clipstone Welfare be approved, subject to an appropriate legal agreement being entered into by Clipstone Welfare; and
(b) the sum of £49,180 be added to the Council’s Capital Programme in order that its expenditure can be appropriately recorded and monitored.
Reason for recommendations
To ensure that S106 funds are spent in an appropriate fashion, for the benefit of the community in which they were generated and that their use is properly monitored.
Background papers
The relevant S106 agreement is available upon request.
For further information please contact Phil Beard on ext. 5714 or Andy Hardy on ext. 5708.
Kirsty Cole Acting Chief Executive
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Programme 2022/23 to 2025/26AGREED (unanimously) that the General Fund schemes set out at Appendix A to the report, and the Housing Services sche...
Newark Castle - Condition SurveyAGREED (unanimously) that: (a) the inclusion of this work in the 2022/23 Capital Programme for £570,000 be approved, ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.