AGREED (unanimously) that the current projection of the Council’s net expenditure compared to budget at 31 March 2018 be noted. Reason for Decision To advise Members of the projected outturn monitored against service budgets for the period ending 31 March 2018, as at 31 December 2017.
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
1.1This report compares the General Fund Revised Budget for the period ending 31 March 2018 with the Projected Outturn forecast for the period, based on meetings with Financial Services staff and the appropriate Business Manager, based on three quarters performance information.
2.0Background Information
2.1The Council’s Constitution states that the Section 151 Officer shall present to the Policy & Finance Committee, at least twice in each financial year, budgetary control statements showing performance against the approved estimates of revenue expenditure and income. The appropriate Chief Officer will report on any major variances from planned budget performance.
2.2Where it appears that the amount included under any head of the approved budget is likely to be exceeded or the budgeted amount of income under any head is unlikely to be reached then Business Managers are required to find savings elsewhere in their budget. In circumstances where savings cannot be identified it will be necessary to consult with the Section 151 Officer and ultimately take a report to the Policy & Finance Committee.
3.0Proposals
3.1The attached appendices detail anticipated performance against budget for the period to 31 March 2018 for all general Fund service provision, split by committee.
3.2Appendix A comprises a projection of all transactions during the financial year. A significant number of transactions take place ‘below the line’, i.e. shown in the General Fund account rather than identified to a particular service. This is in line with the CIPFA Code of Practice and includes such things as transfers to and from reserves. Appendices B to E shows projected outturn on expenditure and income on provision of services within each Committee.
3.3Under the Accounting Code of Practice Local Authorities are required to show capital charges for the use of their assets based on the current market value. These amounts are included within the estimates to show the true cost of delivering local services however they are reversed ‘below the line’ in the overall cost of services therefore not impacting on the Council Tax payer. Variations on ‘capital charges’ are therefore not an area for concern.
3.4The introduction of International Financial Reporting Standards (IFRS) for the financial year 2010/2011 has resulted in a change in the way the Council accounts for grants received from third parties. These changes mean that income and expenditure is charged direct to the service accounts and, at the year end, any under spend is transferred to reserves and any overspend is transferred from reserves. The base budget does not include grant funded expenditure or income, although at the year end these are included in the profiled budget and actual figures. 3.5 Support services (e.g. HR, Financial Services, ICT) are charged to individual budget heads at the end of the financial year and are reported here for noting only.
3.6Capital charges are applied to accounts at the end of the financial year and are reversed ‘below the line’ so have no impacts on the Council Tax payer. These are reported here for noting only.
4.0Performance Comments
4.1The total for service net expenditure shows a projected additional income and underspend on expenditure totalling (£360,221) (highlighted in yellow on Appendix A) against the revised budget for the period to 31st March 2018. All managers are very aware of the current financial environment and challenges facing local government in the future and will be closely monitoring budgets to ensure that year end net expenditure is in line with the revised budget for the year. Officers from Financial Services are working with Business Managers to examine where savings can be achieved in the next three months of the financial year, to further improve the projection.
4.2The main variations from the Revised Budget to 31st March 2018 are itemised below:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Programme 2022/23 to 2025/26AGREED (unanimously) that the General Fund schemes set out at Appendix A to the report, and the Housing Services sche...
Newark Castle - Condition SurveyAGREED (unanimously) that: (a) the inclusion of this work in the 2022/23 Capital Programme for £570,000 be approved, ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.