Resolved
AGREED that the report be noted.
Mansfield and District Crematorium Joint Committee agreed this item on Monday 16 September 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
AGREED that the report be noted.
APPENDIX 1
Please note that approximations of days have been included but not dates as we have no official start date until contracts are signed off.
Wherever possible works will be scheduled for weekends with only quieter works being undertaken during the working week to allow for continuation of service.
PRELIMINARIES AND PROCUREMENT
2 Contract award 3 Initial project and planning review with client has taken place 4 Preliminary design review 5 Contract review meeting with client has taken place 6 Detail design development 7 Create P&IDs and produce BOM/item list 8 Order long lead time items 9 Delivery of major equipment 10 SITE SETUP & REMOVAL OF EXISTING PLANT 52 days Fri - Sun over several weekends 11 Take possession of site 0 days 12 Set up site compound and welfare facilities 3 days 13 Set all cremators to bypass 14 Decommission abatement systems and carry out electrical isolations 5 days 15 Drain Glycol circuits and empty carbon beds 2 days Sat/Sun 16 Remove carbon beds, ID fans, air blast coolers 2 days Sat / Sun 17 Partially dismantle steel mezzanine to facilitate bag filter removal 5 days Mon - Fri 18 Remove bag filters and compressor 2 days Sat /Sun 19 Remove first heat exchanger 1 day Fri 20 Remove second heat exchanger 1 day Sat 21 Remove third heat exchanger 1 day Sun 22 Decommission cremator 1 1 day 23 Rip out cremator 1 refractories 4 days Tue – Fri 24 Remove cremator 1 exhaust ductwork 2 days Sat / Sun 25 Remove cremator 1 carcass 3 days Fri - Sun 26 PLANT INSTALLATION 106 days 27 Refurbish floor in cremator 1 area 5 days Mon – Fri 28 Take down compressor brick enclosure 2 days Sat / Sun 29 Extend yard area 14 days 30 Modifications to steel mezzanines to accommodate new equipment 14 days 31 Modifications to yard area plinths to accommodate new equipment 5 days 33 Install new flue offtakes to cremators 3 days Fri -Sun 34 Install new heat exchangers on front aspect roof area 1 day Sat 35 Install cremator to heat exchanger connecting ducts 3 days Fri - Sun 36 Assemble new pump sets on internal steel mezzanine 5 days Mon - Fri 37 Install bag filters in yard area 2 days Sat / Sun 38 Install reagent dosing units 1 day Sun 39 Install new air blast coolers and induced draught fans 2 days Sat / Sun 40 Install compressors 1 day Sun 41 Install internconnecting ducting 14 days 42 Install heat dissipation pipework 10 days 43 Install compressed air delivery pipework 5 days 44 ELECTRICAL INSTALLATION 63 days 45 Install abatement control panels 2 days Sat /Sun 46 Install abatement electrical devices 2 days 47 Install 2‐into‐1 abatement system electrical wiring 14 days 48 Install first cremator control panel 1 day Sun 49 Electrical wiring to first cremator 7 days 50 Install single abatement system electrical wiring 14 days 51 Install second cremator control panel 1 day Sat 52 Electrical wiring to second cremator 7 days 53 Install third cremator control panel 1 day Sat 54 Electrical wiring to third cremator 6 days 55 TESTING & COMMISSIONING 68 days 56 Pre‐commission first cremator 2 days 57 Commission first cremator 3 days 58 First cremator operational (unabated) 0 days 59 Pre‐commission second cremator 2 days 60 Commission second cremator 4 days 61 Second cremator operational (unabated) 0 days 62 Pre‐commission 2‐into‐1 abatement system 4 days 63 Commission 2‐into‐1 abatement system 8 days 64 First two cremators operational (abated) 0 days 65 Pre‐commission third cremator 3 days 66 Commission third cremator 4 days 67 Third cremator operational (unabated) 0 68 Pre‐commission single abatement system 3 days 69 Commission single abatement system 5 days 70 Practical completion ‐ all three cremators running abated 0 days 71 Full operator training 10 days 72 COMPLETION AND SITE HANDOVER 53 days 73 O&M manuals issued, on site H&S file and CDM file updated 25 days 74 Clear site and deep clean 2 days Sat / Sun 75 Independent emissions testing 5 days
76 Final handover meeting 0 days
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Abatement Equip APP1Report | 315 KB | DownloadRead as text |
PDF |
Abatement EquipmentReport | 14 KB | Download |
Follow Mansfield and District Crematorium Joint Committee at Newark and Sherwood and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Feb 2026 | Operations ReportAGREED (with 6 votes for and 1 abstention) that: i) the committee approve the replacement of the existing crematorium... | Agreed | Open |
| 23 Feb 2026 | Financial Management Review April-December 2025AGREED (unanimously) that the financial information provided in Appendix 1 and Table 1 in the report be noted. | Agreed | Open |
| 23 Feb 2026 | Annual Review of Fees and Charges for 2026/27AGREED (unanimously) that: i) the proposed cremation fee as shown in Table 2 for the period 1 April 2026 to 31 March ... | Agreed | Open |
| 23 Feb 2026 | Revenue and Capital Budget 2026/27 - 2028/29AGREED (unanimously) that: i) the proposed revenue and capital budgets for 2026/27 be approved, as per Appendix 1; ii... | Agreed | Open |
| 23 Feb 2026 | Crematorium Development ReportAGREED (unanimously) that the Committee noted the report. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.