AGREED (Unanimously) to recommend to the Chief Executive, that Planning Permission be refused contrary to Officer recommendation on the grounds of highway safety and lack of need, given the width and adequacy of the existing access. In the opinion of the Local Planning Authority the proposed temporary construction access was considered likely to lead to conflicts between vehicles utilising it and other traffic using the highway, particularly given the speed of traffic along Ollerton Road. When considering this likely highway conflict and the lack of robust justification regarding the need for such a temporary construction access given the width and adequacy of the existing main access already in situ, it was considered that the application was unnecessary, harmful and contrary to Policies SP7 (Sustainable Transport), ShAP4 (Land at Thoresby Colliery) of the adopted Newark and Sherwood Amended Core Strategy (2019) and Policy DM5 (Design) of the Allocation and Development Management DPD , adopted 2013 which together form the relevant parts of the Development Plan.
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
Proposal: Development of one temporary construction access point
Location: Land at Ollerton Road, Edwinstowe
Applicant: Harworth Group Plc Agent: Pegasus Group – [name removed]: 23 December 2019 Target Date: 17 February 2020
Extension of Time Agreed Until 2 April 2020
This application is being referred to the Planning Committee for determination by all 3 of its local ward members on the grounds of highway safety.
The Site
The application site, as originally submitted, relates to two areas of land adjacent to the A6075 Ollerton Road in Edwinstowe.
The eastern most area of land (immediately adjacent to Phase 1 of the wider redevelopment) was an existing field access in a clearing of mature vegetation. Some construction works have already been carried out within the site area such as the laying of kerbs, hardcore etc) but falls short of connecting to the highway. This area is currently fenced off with high metal fencing along the back edge of the footway.
The western most area of land (immediately adjacent to Phase 2 of the wider site) comprises an existing agricultural access point between hedgerows.
Extract: Google Street View (prior to enabling works beginning) Relevant Planning History
The most relevant applications are, in brief, as follows:
16/02173/OUTM – Outline planning permission for a residential development up to 800 dwellings, a strategic employment site comprising up to 4,855 sqm class B1a, up to 13,760 sqm class B1c, and up to 13,760 sqm class B2, a new country park, a local centre, containing a mix of leisure, commercial, employment, community, retail health, and residential uses, a primary school, open space and green infrastructure together with associated access works including the details of the primary access junctions into the site from Ollerton Road. Approved March 2019 subject to 51 conditions and a S106 Planning Agreement which secured a range of developer contributions.
19/00674/RMAM – Reserved Matters for the ‘enabling infrastructure phase’ of the comprehensive development. The approved works included the provision of a new ghost island at the junction of the existing colliery access with Ollerton Road, a new main spine road to serve the first two phases of the residential development which utilises the existing colliery access drive together with its associated highway drainage, surface water and foul infrastructure drainage systems, landscaping and earthworks. It also included the approval of an air quality assessment which covered the whole of the site and all phases of development. This was granted in July 2019 under delegated powers.
19/01016/RMAM - Reserved matters application for Phase 1 (Harron Homes Ltd) residential development comprising 143 dwellings with access gained from the primary, central spine road. This was approved 4th December 2019.
19/01865/RMAM – Phase 2; Reserved Matters submission for 219 dwellings with access gained from the primary, central spine road (permitted under 19/00674/RMAM) including open space, landscaping (soft and hard) and associated internal road infrastructure. Application lodged by Barratt Homes in October 2019 which is currently pending consideration.
The Proposal
Full planning permission was originally sought for the erection of two construction access points to serve Phases 1 and 2 of the Thoresby Colliery redevelopment from Ollerton Road. Part of the proposed access to serve Phase 1 has already been installed albeit it currently stops short of linking to the highway and thus is not in use, as such.
However due to concerns regarding highway safety, the application has been amended to one construction access serving Phase 2. The access is to be for a temporary period during the construction period of Phase 2 only which would be removed and replaced with a permanent pedestrian link and associated landscaping.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics