AGREED (with 6 votes For and 5 votes Against) that planning permission be approved , subject to the conditions contained within the report. Councillor Vote R. Blaney For L. Brazier Against M. Brock For M. Brown Against L. Dales Was not present for duration of presentation M. Dobson Against L. Goff Against R. Holloway For J. Lee Apology for absence P. Rainbow Was not present for duration of presentation M. Skinner For T. Smith Apology for absence I.Walker For K. Walker For Y. Woodhead Against
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
Proposal: Development of one temporary construction access point (resubmission)
Location: Land at Ollerton Road, Edwinstowe
Applicant: Harworth Group Plc
Agent: Pegasus Group – [name removed]: 12 June 2020 Target Date: 07 August 2020
Link to https://publicaccess.newark-sherwooddc.gov.uk/online- application file: applications/applicationDetails.do?activeTab=documents&keyVal=QBQZDWLBHQR00
This application is referred to the Planning Committee given that it relates to the resubmission of a scheme that was recently refused by the Planning Committee. Ward member, Cllr M Brown, has also explicitly referred the application to committee on highway safety grounds and requested a site visit be undertaken by Members.
The Site
The application site relates to an area of land adjacent to the A6075 Ollerton Road in Edwinstowe, immediately adjacent to Phase 2 of the wider redevelopment. It comprises an existing agricultural access point between hedgerows.
Extract: Google Street View (prior to enabling works beginning) Officer Photo taken 22.07.2020
Relevant Planning History
The most relevant applications are, in brief, as follows:
19/02159/FUL – Development of one temporary construction access point. This was refused contrary to officer recommendation by Committee in March 2020 for the following reason:
In the opinion of the Local Planning Authority the proposed temporary construction access was considered likely to lead to conflicts between vehicles utilising it and other traffic using the highway, particularly given the speed of traffic along Ollerton Road. When considering this likely highway conflict and the lack of robust justification regarding the need for such a temporary construction access given the width and adequacy of the existing main access already in situ, it was considered that the application was unnecessary, harmful and contrary to Policies SP7 (Sustainable Transport), ShAP4 (Land at Thoresby Colliery) of the adopted Newark and Sherwood Amended Core Strategy (2019) and Policy DM5 (Design) of the Allocation and Development Management DPD, adopted 2013 which together form the relevant parts of the Development Plan.
APP/B3030/W/20/3253579 - An appeal (written representations method) against this decision has been lodged and validated. By agreement with the appellant and PINS, the appeal statement is due on 12th August 2020. The appeal would be withdrawn if this resubmission were to be approved.
16/02173/OUTM – Outline planning permission for a residential development up to 800 dwellings, a strategic employment site comprising up to 4,855 sqm class B1a, up to 13,760 sqm class B1c, and up to 13,760 sqm class B2, a new country park, a local centre, containing a mix of leisure, commercial, employment, community, retail health, and residential uses, a primary school, open space and green infrastructure together with associated access works including the details of the primary access junctions into the site from Ollerton Road. Approved March 2019 subject to 51 conditions and a S106 Planning Agreement which secured a range of developer contributions.
19/00674/RMAM – Reserved Matters for the ‘enabling infrastructure phase’ of the comprehensive development. The approved works included the provision of a new ghost island at the junction of the existing colliery access with Ollerton Road, a new main spine road to serve the first two phases of the residential development which utilises the existing colliery access drive together with its associated highway drainage, surface water and foul infrastructure drainage systems, landscaping and earthworks. It also included the approval of an air quality assessment which covered the whole of the site and all phases of development. This was granted in July 2019 under delegated powers.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.