AGREED That Cabinet: a) note and welcome the updates provided; and b) approve an amendment to the Council’s Capital Programme to the Maximum Capital budget detailed in Exempt Report in order to secure a contractor and delivery of the 32 Stodman Street project. The project, one of 9 priority Towns Fund and Town Investment Plan project will contribute to all of the Council’s Community Plan objectives, including creating more and better-quality homes through our role as landlord and developer. Options Considered: Cabinet could decide not to proceed with the development, which would result in the lack of a much-needed town centre intervention which has the full support of this Council, the Newark Towns Board, the Newark Town Investment Plan and Central Government who have approved the Newark Towns Fund. Moreover, Newark Towns Fund grant would be at risk if the project does not proceed. (Having declared an Other Registerable Interest, Councillor Wendels did not take part in the consideration or voting of this item.)
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
1.1In March 2022 Members will recall resolving, having secured planning permission and a pre-construction sale (to Arkwood Developments Ltd.), to add this scheme to the Council’s Capital program such that a tender exercise could take place in order to secure a preferred contractor. Since that time Officers have progressed with a range of procurement options, having received several tenders from interested parties. Detailed design work has advanced with the procurement of client’s agent, M&E engineer, Structural and Civil Engineer and a Principal Designer. All of these consultants will be retained by NSDC should Members agree to proceed with the scheme due to the specialist nature of the project requiring continuity of specific site and project knowledge. The Council has also continued its preparatory works, including the removal of large amounts of asbestos and clearance of internal partition walls to ready the site for the proposed re-development.
2.0Procurement
2.1Procurement processes have taken place since late 2022, concluding in January 2023. A range of tender returns and prices have been received. Given market conditions, including inflationary pressures, it is clear that a change to the Council’s capital program is required in order to deliver the scheme. A recommended revised Maximum Capital budget is detailed at Exempt Report. The Council’s Business Manager, Corporate Property is confident the scheme can be delivered within this Maximum Budget. An indicative timetable for delivery, subject to agreement of the appointed contractor, is detailed below:
Agreement to Lease and Lease executed for residential units – March 2023 Mobilisation of Contractor – May–August 2023 Demolition Phase and Enabling works – July– November 2023 Construction Phase – December 2023–June 2025 Completion – June 2025 Sale by long lease of Residential Units – June 2025
3.0Proposal/Details of Options Considered
3.1It is recommended that the Council’s Capital Program is increased to the Maximum Capital Budget as detailed in the Exempt Report, allowing officers to conclude procurement in order to appoint a contractor and deliver the scheme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget Performance Report Quarter 1That Cabinet: (a) note the General Fund projected unfavourable outturn variance of £0.665m; (b) note the Housing Reve...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.