Members are requested to approve option three for the reasons cited within the contents of this report. This is recommended that given the prolonged lifespan of the more durable materials and the lower repair costs. On approval of option three an estimated budget cost of £333,499.67 + Vat will then be added to the capital programme. AGREED That Cabinet: a) approve repair option 3 to Upgrade the existing approach ramp with steel trays infilled with tarmacadam / hot rolled stone chippings to match the existing subject to approval by a structural engineer; and b) approve an estimated budget cost of £333,499.67 + Vat will then be added to the capital programme. To ensure the maintenance of the Jubilee Bridge is undertaken to provide safe use and enhancement of the area for local residents. Options Considered: Not completing the works would result in the eventual closure of the bridge and the detrimental impact to the area because of poorly maintained public infrastructure.
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
JOB NO: 12543-WMS-ZZ-ZZ-SH-B-10002-D2-P2 DATE: OCTOBER 2022 APPENDIX I
Contract: Jubilee Bridge, Newark on Trent
Document Title: Schedule of Works - Bridge Maintenance Works
Our Ref: 12543
Prepared by: Jeff Cook Date: December 2022
RECORD OF AMENDMENTS TO DOCUMENT
Ref Description Date
P2 Amended to reflect client comments. 13/12/2022
Verified by: Date: 14th December 2022 APPENDIX I
SCHEDULE OF WORK
Jubilee Bridge Newark on Trent APPENDIX I £ p
1.00Liaison & Permissions
1.01The contractor should allow for all costs / time (including any required applications / licences / closures etc.) associated with liaising with The Canal & River Trust, The Environment Agency, The Ramblers' Association and all other stake- holder agencies as required to undertake the works.
2.00Access & Security
2.01Allow here for hoarding/fencing required to prevent unau- thorised entry to the site, working areas and any scaffold.
2.02Allow for restricted access to the site and a small site com- pound on site.
N.B.: N&SDC do not own either the land on which the bridge sits on or the land which accesses the bridge location. Pro- posed site & location of site compound to be submitted with tender.
2.03Allow to cut down & remove all grass, weeds, elders, bram- bles & overgrowth etc. to allow for all proposed works to be undertaken. All waste to be removed and safely disposed of off-site.
2.04Allow here for all access requirements as required for the safe execution of the works. This may include mansafe an- choring, temporary edge protection, scaffold & fall arrest netting for the duration of the works. This should include all elements required to execute the works in compliance with site specific considered RAMS which must be submitted along with the contractor’s tender for consideration in the tender analysis. Full completion of a suitable Construction Phase H&S Plan for the works, incorporating the RAMS as submitted & agreed at tender stage, will subsequently be provided by the successful contractor in the project lead-in period.
2.05Allow here for specific rope access cost as required to carry out preparation & decoration of bridge towers/pylons [al- lowed for elsewhere].
To Collection £ Job No.: 12543 Page 4 of 20 APPENDIX I £ p
3.00Existing Lighting Removal
3.01To existing pedestrian deck lighting on approach ramps to East & West, remove all existing associated electrical sup- plies, conduit/trunking, deck light unit containment boxings and light units themselves, including all associated fixings – Estimated 14no. light units & containment boxings with circa 100m cable & trunking [Ph#01-02]. Any redundant brack- ets/mountings should be neatly cut/ground off prior to re- decoration works. Incoming supply should be safely termi- nated at consumer unit/isolator/distribution board in Eastern service room beneath walkway [Ph#03].
3.02To hard surfacing over main bridge span, squarely neat cut around and remove existing light units, then fill holes and fin- ish with suitable wearing tarmac, neatly bitumen sealed to margins. Remove all existing associated electrical supplies, conduit/trunking and deck light unit containment boxings, including all associated fixings – Estimated 8no. light units & containment boxings with circa 55m cable & trunking [Ph#04-05]. Any redundant brackets/mountings should be neatly cut/ground off prior to redecoration works. Incoming supply should be safely terminated at consumer unit/isola- tor/distribution board in Eastern service room beneath walk- way.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget Performance Report Quarter 1That Cabinet: (a) note the General Fund projected unfavourable outturn variance of £0.665m; (b) note the Housing Reve...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.