AGREED that Cabinet support the emerging Long-Term Plan for Town Fund emerging proposals as detailed at paragraph 2.3 below and to delegate to the Portfolio holders for Strategy, Performance & Finance and Sustainable Economic Development endorsement of any final Long Term Plan for Town Investment Plan 2024-2027 following its ratification by Newark Towns Board for submission to Government before the requisite submission date. The recommendation is presented on the basis that the Long-Term Plan for Newark 3 Year Investment Plan has been developed with the Newark Town Board and based on evidence from consultation with the community through the Resident Survey, Newark Masterplan Consultation, and targeted consultation with under-represented groups. The Long-Term Plan for Newark 3 Year Investment Plan 2024-2027 aligns with the outlined objectives of the NSDC Community Plan. Options considered: It remains open for this Council to not engage with the Newark Towns Board or to contribute to its formulate and ultimate adoption and submission to Government, save for its role as the Accountable Body. This option has been discounted as the Council and its partners wish to continue to achieve the best for residents and business and securing almost £20m for Newark between now and 2034 would be a significant contribution towards this.
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
Report to: Cabinet : 23 July 2024 Portfolio Holder: Councillor Paul Peacock, Strategy, Performance & Finance Councillor Matthew Spoors, Sustainable Economic Development Director Lead: Matt Lamb, Director of Planning & Growth Lead Officer: Neil Cuttell, Business Manager (Economic Growth & Visitor Economy
Report Summary
Type of Report Key Decision, Open
Report Title Long Term Plan for Towns – Town Investment Plan 2024-2027 To support the emerging Newark Long-Term Plan for Town Purpose of Report Fund (LTPfT) Vision & Investment Plan by Newark Towns Board to Government before the 1st August 2024. To support the emerging Long-Term Plan for Town Fund emerging proposals as detailed at paragraph 2.3 below and to delegate to the Portfolio holders for Performance & Finance Report and Sustainable Economic Development endorsement of any Recommendations final Long Term Plan for Town Investment Plan 2024-2027 following its ratification by Newark Towns Board for submission to Government before the 1st August 2024. It remains open for this Council to not engage with the Newark Towns Board or to contribute to its formulate and ultimate adoption and submission to Government, save for its role as Alternative Options the Accountable Body. This option has been discounted as the Considered Council and its partners wish to continue to achieve the best for residents and business and securing almost £20m for Newark between now and 2034 would be a significant contribution towards this. The recommendation is presented on the basis that the Long- Term Plan for Newark 3 Year Investment Plan has been developed with the Newark Town Board and based on evidence Reason for from consultation with the community through the Resident Recommendations Survey, Newark Masterplan Consultation, and targeted consultation with under-represented groups. The Long-Term Plan for Newark 3 Year Investment Plan 2024-2027 aligns with the outlined objectives of the NSDC Community Plan. 1.0 Background
1.1In November 2023 an announcement was made by Government that Newark was one of 55 towns to be offered the opportunity to apply for a £20m Long Term Town Fund. This fund provides proportionate funding every year for 10 years through to 2033/34 to drive ambitious locally set visions for their Town. To secure this investment Newark Town Board, and Newark & Sherwood District Council as accountable body, are required develop a Long- Term Vision for the Town, based on the priorities of the community and put to local people for consultation. This will be accompanied by a 3-year Investment Plan for 2024-2027. A further Investment Plan would need to be created in 2026/27. The District Council are identified as accountable body for the funding programme.
1.2The Long Term Plan for Town guidance can be found here: https://www.gov.uk/government/publications/our-long-term-plan-for-towns/our-long- term-plan-for-towns
1.3As members will understand, it is important to collate data and opinion to understand Newark’s challenges therein creating the ‘why’ for a focus for future priorities. A data pack from Government has been provided (Long-Term Plan for Towns: data packs for 55 towns - GOV.UK (www.gov.uk)) which sits alongside the raft of data sets already captured through the Towns Fund-led Town Investment Plan 1, the Council’s Community Plan, Board Members own published priorities, and the aforementioned emerging Masterplan & Design Code work.
1.4The Town Investment Plan must contain the following:
The 10-year Vision A 3-year Investment Plan, including a financial and output annex and must also contain priorities for investment, narrative explaining the investment themes and the interventions the town intends to pursue in the first year of the programme
Once submitted to the Department for Levelling Up, Housing & Communities (DLUHC), it will be assessed prior to funding being released.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget Performance Report Quarter 1That Cabinet: (a) note the General Fund projected unfavourable outturn variance of £0.665m; (b) note the Housing Reve...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.