Newark Long Term Town Fund Update and Associated Feasibility Work

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 26 March 2024. Below is the council's own wording, with the papers it was decided on.

Item120

Resolved

AGREED that Cabinet approve a revenue budget of up to £145,000 from the Change Management Reserve to progress to the next stage of feasibility works for the St Marks Project.
Word for word from the decision Newark and Sherwood published for this meeting. Source: democracy.newark-sherwooddc.gov.uk

Follow this further

Built from Newark and Sherwood's papers

What the report saysPro

Report to Cabinet

Report to: Cabinet Meeting: 26 March 2024 Portfolio Holders: Councillor Paul Peacock, Strategy Performance & Finance Councillor Matthew Spoors – Sustainable Economic Development Director Leads: Matt Lamb, Director - Planning & Growth Sanjiv Kohli, Deputy Chief Executive and Director - Resources Lead Officers: Neil Cuttell – Business Manager - Economic Growth & Visitor Economy, Robert Ball, Major Capital Projects Delivery Manager (Corporate Property) Elaine Poon, Town Fund Programme Manager

Report Summary

Type of Report Open Report (with exempt appendix), Non-Key Decision

Newark Long Term Town Fund Update and Associated Report Title Feasibility Work To update Cabinet on the progress of the Newark Long-Term Purpose of Report Town Fund and seek approval of budget to progress feasibility work for the St Marks Project. That Cabinet approve a revenue budget of up to £145,000 from Recommendations the Change Management Reserve to progress to the next stage of feasibility works for the St Marks Project. Do Nothing Approach; It remains open for this Council and the Towns Board to decline the £20m grant available via the LTPfT fund. That is discounted on the basis that this is an opportunity to building upon the Town Investment Plan (2020) and its 9 Alternative Options priority projects and Levelling Up Fund 1 (Newark Southern Link Considered Road). St Marks has been identified as a site which could be repurposed for positive change in the TIP1, the emerging Newark Masterplan & Design Code, and discussions to date with the Newark Towns Board. To allow the Council to commence detailed feasibility and due Reason for diligence on future options to repurpose St Marks for the Recommendations benefit of the Town.

1.0Background and Update

1.1Members will be aware of the success of this Council in working with partners to deliver the Newark Towns Fund and Newark Levelling Up Fund 1, with £45m of grant funding unlocking many times that amount in private sector match. In November 2023 the Government informed Newark and Sherwood District Council that they had been selected as one of 55 Towns to be offered an additional £20m over a 10-year period for the regeneration of Newark. To receive this investment the Government requires Newark to.

 Develop a Long-Term Plan for Newark, comprising a Vision and at least 3-Year Investment Plan for the up to £20m available. The Vision and Investment Plan (referred to as the Town Investment Plan 2, TIP2, for ease) must demonstrate public consultation and support and be submitted to Government by 1 August 2024;  Establish a Town Boards that must develop, oversee, and delivery the Vison and TIP2. The membership of the Board must comprise a number of mandated parties including all tiers of government, community leaders, employers, local authorities, educators, and the local MP. All board members will now be required to complete various governance requirements and sign up to the standards of the Nolan principles.

1.2The Government have provided a financial profile of approximately £1.6m Capital funding and £0.4m Revenue Funding for each year up to 2033/34 and will require a further Investment Plan for 2027/28 onward.

1.3Members will be aware that the Newark Town Masterplan & Design Code (TCM) is already in development. This is the appropriate vehicle to capture and inform the LTPfT Vision. This TCM will be complete prior to 1 August LTPfT deadline, allowing it to set the strategic case for investment alongside a TIP2 that will be developed. The TCM and TIP2 will be subject to the approval of the Towns Board and this Council, as was the case for the original Towns Fund.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Newark Long Term Town Fund Update and Associated Feasibility WorkReport 638 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 20 attended
PP
Councillor Paul PeacockChair, present
RC
Councillor Rowan CozensCommittee Member, present
SC
Councillor Susan CrosbyCommittee Member, present
LB
Councillor Lee BrazierCommittee Member, apologies
KM
Councillor Keith MeltonCommittee Member, present
EO
Councillor Emma OldhamCommittee Member, present
MS
Councillor Matthew SpoorsCommittee Member, present
PT
Councillor Paul TaylorCommittee Member, present
RH
Councillor Rhona HollowayCommittee Member, present
NH
Nigel HillSecretary, expected
MF
Matt FinchOfficer, expected
DK
Deborah K JohnsonOfficer, expected

All 20 on the meeting page

On this subject at Newark and Sherwood

Search all
  1. Newark Long Term Town Fund Update and Associated Feasibility WorkThis decision
  2. Newark Long Term Plan for Towns Fund (Key Decision)Noted
  3. Manor Farm, Long Lane, Barnby In The Willows, Newark On Trent, NG24 2SG - 23/01490/FULAgreed

More from Newark and Sherwood Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Budget Performance Report Quarter 1That Cabinet: (a) note the General Fund projected unfavourable outturn variance of £0.665m; (b) note the Housing Reve... Noted Open
15 Sep 2026 Community Plan Performance Report Quarter 1That Cabinet: a) review the Community Plan Performance Report attached as Appendix 1; b) review the compliance report... Decided Open
15 Sep 2026 Housing Compliance Assurance Report Quarter 1That Cabinet note: a) the exceptions to performance of the housing service compliance functions; b) interim arrangeme... Decided Open
15 Sep 2026 Annual Review of Exempt ItemsThat Cabinet note the report, with any items being released into the public domain if considered no longer being exempt. Noted Open
15 Sep 2026 Progress Towards Net ZeroThat Cabinet: a) notes the Council's 2025/26 corporate emissions position and progress towards the Net Zero 2035 targ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies