Newark and Sherwood District Council
Cabinet, Tuesday 10 December 2024 at 6.00pm

Levelling Up Fund 3 Programme Update (Key Decision)

Noted Executive 2 papers

Cabinet noted this item on Tuesday 10 December 2024. Below is the council's own wording, with the papers it was decided on.

Item218

Resolved

AGRED that Cabinet: a) note the report, including the updates associated with the LUF 3 Programme; Ollerton Project b) approves a capital budget of £500,000, financed initially by borrowing, to be replaced by the LUF 3 grant when received, to enable essential project development works associated with the Ollerton scheme, prior to the Council receiving a Memorandum of Understanding, as detailed in section 1.6 of the report; Clipstone Project c) approves a capital budget of £200,000, financed by borrowing initially, to be replaced by LUF 3 grant when received, to enable essential project development associated with the Clipstone scheme (Phases 2 and 3), prior to the Council receiving a Memorandum of Understanding, as detailed in section 1.9 of the report; Memorandum of Understanding (MoU) d) approves an amendment to the existing delegation to the S151 Officer, Deputy Chief Executive & Director of Resources and Director of Planning and Growth, to include the acceptance of apartial (or full), LUF 3 grant of up to £20m, via an MoU, as detailed in sections 1.12 and 1.13 of the report; and e) notes the existing and proposed financial commitments immediately eligible for repayment by MHCLG, subject to a finalised partial, or full MoU, as detailed in section 1.13 of the report. To ensure Members are aware of the recent updates and developments associated with the LUF 3 programme, and to enable ongoing progression of both schemes for delivery within potential Government timescales. Without access to further funding, there is an elevated risk that both projects are unable to meet spend timescales detailed within this report. It is recommended that the Council enters into an initial MoU with MHCLG at the earliest opportunity, to enable existing upfront investment to be eligible for repayment from LUF 3 Grant, in turn reducing the level of financial exposure for the Council. Options Considered: It remains an option for the Council to refuse to accept any future LUF 3 grant or decide not to provide further forward funding. This approach is not recommended as it would represent a missed opportunity to deliver genuine and impactful transformative change in the communities of Ollerton and Clipstone. Without additional forward funding, risk is ... view the full minutes text for item 218.
Word for word from the decision Newark and Sherwood published for this meeting. Source: democracy.newark-sherwooddc.gov.uk

Follow this further

Built from Newark and Sherwood's papers

What the report saysPro

Report to Cabinet

Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
10.12.24: Levelling Up Fund 3 Programme Update: Supplemental ReportReport 614 KB DownloadRead as text
PDF
Levelling Up Fund 3 Programme Update (Key Decision)Decisions 583 KB Download

At this meeting

Whole meeting

Who was there

8 of 24 attended
PP
Councillor Paul PeacockChair, present
RC
Councillor Rowan CozensCommittee Member, present
SC
Councillor Susan CrosbyCommittee Member, present
LB
Councillor Lee BrazierCommittee Member, present
EO
Councillor Emma OldhamCommittee Member, present
CP
Councillor Claire PennyCommittee Member, present
PT
Councillor Paul TaylorCommittee Member, present
JK
Councillor Jack KellasCommittee Member, present
NH
Nigel HillSecretary, expected
MF
Matt FinchOfficer, expected
DK
Deborah K JohnsonOfficer, expected
SK
Sanjiv KohliOfficer, expected

All 24 on the meeting page

On this subject at Newark and Sherwood

Search all
  1. Levelling Up Fund 3 Programme Update (Key Decision)This decision
  2. Sherwood Levelling Up Fund (LUF) Programme Update (Key Decision)Approved
  3. Sherwood Levelling Up, Long Term Plan for Towns Fund and UKSPF / UKRPF Fund Update (Key Decision)Approved
  4. Levelling Up Fund 3 update (Key Decision)Agreed
  5. Sherwood Levelling Up Fund Update - Ollerton Town Centre and Mansfield Road, Clipstone (Key Decision)Agreed
  6. Levelling Up Submission and UK Shared Prosperity Fund (Key Decision)Agreed

More from Newark and Sherwood Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Budget Performance Report Quarter 1That Cabinet: (a) note the General Fund projected unfavourable outturn variance of £0.665m; (b) note the Housing Reve... Noted Open
15 Sep 2026 Community Plan Performance Report Quarter 1That Cabinet: a) review the Community Plan Performance Report attached as Appendix 1; b) review the compliance report... Decided Open
15 Sep 2026 Housing Compliance Assurance Report Quarter 1That Cabinet note: a) the exceptions to performance of the housing service compliance functions; b) interim arrangeme... Decided Open
15 Sep 2026 Annual Review of Exempt ItemsThat Cabinet note the report, with any items being released into the public domain if considered no longer being exempt. Noted Open
15 Sep 2026 Progress Towards Net ZeroThat Cabinet: a) notes the Council's 2025/26 corporate emissions position and progress towards the Net Zero 2035 targ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies