Sherwood Levelling Up Fund (LUF) Programme Update (Key Decision)

Approved Executive 1 paper

AI summaryCabinet approves extra budgets for Ollerton regeneration, including £1.33m to close scheme shortfall, and notes the LUF programme has been renamed the Local Regeneration Fund.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedForest Centre acquisition, RIBA 4 work, lease delegation
Money£1,330,000 shortfall being metPlus £682,746 for RIBA 4, £40,000 revenue
What happens nextPlanning application in October 2025Full report to Cabinet on 11 November 2025
Who it affectsOllerton and Clipstone communitiesPlus town council and trust partners

What was decided

Cabinet noted the LUF 3 programme has been renamed the Local Regeneration Fund, with no change to committed funding. Report 1.4

Cabinet approved a capital budget to buy the Forest Centre unit in 2025/26, funded by UKSPF and LUF 3 grant, before planning permission and Full Business Case are secured, plus £40,000 of revenue to retain it until demolition. Report 1.11, 1.12, 2.4

Cabinet approved £1,225,000 from the Change Management Reserve and £105,000 from Ollerton Hall Capital Receipts to close the scheme's £1,330,000 shortfall, and £682,746 of capital budget for RIBA 4 activities. Report 1.17, 1.18, 1.19, 1.20, 1.21, 2.5

Why

Nottinghamshire County Council withdrew from the scheme, leaving a projected shortfall of c£1,330,000 that must be met before the Full Business Case can be signed off. Report 1.6, 1.17, 1.20

LUF 3 grant (now Local Regeneration Fund) must be spent by March 2028, so the council is acting early to avoid delays to defrayal. Report 1.2, 1.20, 1.23

Forward-funding decisions are needed to prevent bottlenecks in legal sign-off and construction mobilisation. Report 1.15, 1.23

What happens next

Submit the Ollerton planning application in October 2025, following a community exhibition held on 11 September 2025 and a Member's Briefing Session on 14 October 2025. Report 1.5, 1.8, 1.9

Director of Planning and Growth to finalise and execute the Agreement for Lease with Ollerton and Boughton Town Council after Heads of Terms are agreed. Report 1.15, 1.16

Phase 1 Clipstone main construction contract tenders closed 26 September 2025, with site start programmed for January 2026; a full progress report goes to Cabinet on 11 November 2025. Report 1.26, 1.28, 1.29

The money

  • £1,330,000 Projected financial shortfall in the Ollerton Full Business Case, to be closed by council contribution Report 1.17, 1.20
  • £1,225,000 From the Change Management Reserve towards the Ollerton scheme Report 1.18, P26
  • £105,000 Ollerton Hall Capital Receipts towards the Ollerton scheme Report 1.18, P26
  • £682,746 Capital budget for RIBA Stage 4 works, financed by LUF 3 grant Report 1.21, 2.5
  • £40,000 Revenue budget to retain the Forest Centre unit until demolition Report 2.4
  • £1,206,559 Total revenue funding available for Ollerton up to RIBA 4 (NSDC reserves £23,255, third party £5,000, UKSPF £511,650, S106 £31,654, LUF Grant £635,000) Report 2.3, P45, P46
  • £607,377 Total revenue funding available for Clipstone Phases 2 and 3 (UKSPF £31,377, Capacity Funding £255,000, LUF Grant £321,000) Report 2.7, P52, P53
  • £20m Original LUF 3 grant award for the Shaping Sherwood's Revival scheme Report 1.1

Options considered

  • Rejected: Restrict the scheme further to cut costs. Would damage the core objective of transformational change and improved access to services Report 1.17
  • Rejected: Delay further scheme budgets until planning consent, FBC and land acquisition are complete. Would risk missing the March 2028 grant deadline Report 1.12, 1.20
  • Rejected: Delegate final lease sign-off only after planning application, as previously agreed. Change sought to mitigate further delays and prevent a legal bottleneck Report 1.15

Implications

  • Financial: Total scheme shortfall of c£1,330,000 now being met from Change Management Reserve and Capital Receipts; FBC cannot be signed off without this contribution. Report 1.17, 1.20, P42
  • Legal: A revised Memorandum of Understanding will be issued by the UK Government for the new Local Regeneration Fund, subject to legal review. Report 1.4, P39, 2.1
  • Risk: If the project does not progress, the council will need to find alternative uses for the Forest Centre and former Lloyds Bank units, with significant refurbishment costs. Assessed as low risk. Report 1.13

Who and where

  • Ollerton community and town centre users Report 1.5, 1.8, P4
  • Ollerton and Boughton Town Council (OBTC), taking space in the new public sector hub Report 1.14, 1.15, P19
  • Clipstone community and visitors to Vicar Water Country Park Report 1.25, 1.28, P33
  • Clipstone Miners Welfare Community Trust (CMWCT), delivery partner for Phase 2 sports scheme Report 1.27
  • Welbeck Estates, landowner involved in Clipstone land swap and VWCP lease Report 1.27, 1.28
  • Main construction contractors tendering for Clipstone Phase 1 (13 attended site visit) Report 1.26

Timeline

  • 2 September 2025: UK Government announced shift from LUF to Local Regeneration Fund Report 1.4
  • 11 September 2025: Final Ollerton design exhibition held at the Town Hall Report 1.8
  • 26 September 2025: Clipstone Phase 1 main construction tenders closed Report 1.26
  • October 2025: Ollerton planning application expected to be submitted Report 1.5
  • 14 October 2025: Member's Briefing Session to present final Ollerton plans Report 1.9
  • 11 November 2025: Next Cabinet report on LUF/Local Regeneration Fund programme Report 1.29
  • January 2026: Clipstone Phase 1 start on site programmed Report 1.26
  • Early 2026: Clipstone Phase 3 (Vicar Water Country Park) planning submission expected Report 1.28
  • Summer 2026: Clipstone Phase 3 development commencement expected Report 1.28
  • March 2028: Revised LUF 3/Local Regeneration Fund grant spend deadline Report 1.2, 1.20

Plain English for the jargon

  • LUF 3: Levelling Up Fund Round 3, the government's £20m grant to the council, now renamed Local Regeneration Fund
  • Local Regeneration Fund: New name announced 2 September 2025 consolidating Levelling Up Fund, Town Deals and the Pathfinder Pilot
  • FBC: Full Business Case, required before the grant can be drawn down
  • RIBA Stage 3 / 4: Royal Institute of British Architects design stages: Stage 3 is Developed Design, Stage 4 is Technical Design
  • OBTC: Ollerton and Boughton Town Council, partner taking space in the new public sector hub
  • UKSPF / REPF: UK Shared Prosperity Fund and Rural England Prosperity Fund
  • CMWCT: Clipstone Miners Welfare Community Trust, partner for the Clipstone sports scheme
  • VWCP: Vicar Water Country Park, the focus of Clipstone Phase 3
  • SME: Small and Medium Enterprises, space retained in the Ollerton design
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item309

Resolved

That Cabinet: a) notes the updates associated with the LUF 3 programme including the revised name of ‘Local Regeneration Fund’, as detailed in 1.4 of the report; Ollerton Project b) approves a budget to be added to the Council’s Capital Programme in 2025/26 to finance the acquisition of the Forest Centre unit, funded by UK Shared Prosperity Fund grant, and LUF 3 grant, in advance of securing planning permission and Full Business Case (FBC) approval, as noted in paragraphs 1.11 and 1.12 of the report. In addition, a revenue budget of £40,000 was required to retain the unit until demolition. The full costings are contained within the Exempt Appendix; c) to delegate the finalisation and execution of the Agreement for Lease (and any other associated legal contracts required) with Ollerton and Boughton Town Council, in advance of securing planning consent, but upon completion of Heads of Terms, to the Director - Planning & Growth, as noted in paragraph 1.15 and 1.16 of this report; d) approves a commitment to the Change Management Reserve of £1,225,000 and £105,000 from Capital Receipts towards the Ollerton Regeneration scheme, in accordance with paragraph 1.17; and e) approves a budget of £682,746 to be added to the Capital Programme in 2025/26, financed by LUF 3 grant, to fund RIBA 4 activities, in advance of securing planning consent and finalisation of legals, but following FBC approval, as noted further in paragraph 1.20.
Word for word from the decision Newark and Sherwood published for this meeting. Source: democracy.newark-sherwooddc.gov.uk

Follow this further

Built from Newark and Sherwood's papers

What the report saysPro

Report to Cabinet

Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Sherwood Levelling Up Fund (LUF) Programme Update (Key Decision)Decisions 523 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 21 attended
PP
Councillor Paul PeacockChair, present
RC
Councillor Rowan CozensCommittee Member, present
SC
Councillor Susan CrosbyCommittee Member, apologies
LB
Councillor Lee BrazierCommittee Member, present
SF
Councillor Simon FordeCommittee Member, present
CP
Councillor Claire PennyCommittee Member, present
PT
Councillor Paul TaylorCommittee Member, present
JK
Councillor Jack KellasCommittee Member, present
NH
Nigel HillSecretary, expected
MF
Matt FinchOfficer, expected
DK
Deborah K JohnsonOfficer, expected
SK
Sanjiv KohliOfficer, expected

All 21 on the meeting page

On this subject at Newark and Sherwood

Search all
  1. Sherwood Levelling Up Fund (LUF) Programme Update (Key Decision)This decision
  2. Sherwood Levelling Up, Long Term Plan for Towns Fund and UKSPF / UKRPF Fund Update (Key Decision)Approved
  3. Sherwood Levelling Up 3 - Update 2 - Ollerton and Clipstone (Key Decision)Approved
  4. Sherwood Levelling Up 3 Update - Ollerton and Clipstone (Key Decision)Agreed
  5. Sherwood Levelling Up Fund Update - Ollerton Town Centre and Mansfield Road, Clipstone (Key Decision)Agreed

More from Newark and Sherwood Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Budget Performance Report Quarter 1That Cabinet: (a) note the General Fund projected unfavourable outturn variance of £0.665m; (b) note the Housing Reve... Noted Open
15 Sep 2026 Community Plan Performance Report Quarter 1That Cabinet: a) review the Community Plan Performance Report attached as Appendix 1; b) review the compliance report... Decided Open
15 Sep 2026 Housing Compliance Assurance Report Quarter 1That Cabinet note: a) the exceptions to performance of the housing service compliance functions; b) interim arrangeme... Decided Open
15 Sep 2026 Annual Review of Exempt ItemsThat Cabinet note the report, with any items being released into the public domain if considered no longer being exempt. Noted Open
15 Sep 2026 Progress Towards Net ZeroThat Cabinet: a) notes the Council's 2025/26 corporate emissions position and progress towards the Net Zero 2035 targ... Decided Open