What was decided
Cabinet noted the LUF 3 programme has been renamed the Local Regeneration Fund, with no change to committed funding. Report 1.4
Cabinet approved a capital budget to buy the Forest Centre unit in 2025/26, funded by UKSPF and LUF 3 grant, before planning permission and Full Business Case are secured, plus £40,000 of revenue to retain it until demolition. Report 1.11, 1.12, 2.4
Cabinet approved £1,225,000 from the Change Management Reserve and £105,000 from Ollerton Hall Capital Receipts to close the scheme's £1,330,000 shortfall, and £682,746 of capital budget for RIBA 4 activities. Report 1.17, 1.18, 1.19, 1.20, 1.21, 2.5
Why
Nottinghamshire County Council withdrew from the scheme, leaving a projected shortfall of c£1,330,000 that must be met before the Full Business Case can be signed off. Report 1.6, 1.17, 1.20
LUF 3 grant (now Local Regeneration Fund) must be spent by March 2028, so the council is acting early to avoid delays to defrayal. Report 1.2, 1.20, 1.23
Forward-funding decisions are needed to prevent bottlenecks in legal sign-off and construction mobilisation. Report 1.15, 1.23
What happens next
Submit the Ollerton planning application in October 2025, following a community exhibition held on 11 September 2025 and a Member's Briefing Session on 14 October 2025. Report 1.5, 1.8, 1.9
Director of Planning and Growth to finalise and execute the Agreement for Lease with Ollerton and Boughton Town Council after Heads of Terms are agreed. Report 1.15, 1.16
Phase 1 Clipstone main construction contract tenders closed 26 September 2025, with site start programmed for January 2026; a full progress report goes to Cabinet on 11 November 2025. Report 1.26, 1.28, 1.29
The money
- £1,330,000 Projected financial shortfall in the Ollerton Full Business Case, to be closed by council contribution Report 1.17, 1.20
- £1,225,000 From the Change Management Reserve towards the Ollerton scheme Report 1.18, P26
- £105,000 Ollerton Hall Capital Receipts towards the Ollerton scheme Report 1.18, P26
- £682,746 Capital budget for RIBA Stage 4 works, financed by LUF 3 grant Report 1.21, 2.5
- £40,000 Revenue budget to retain the Forest Centre unit until demolition Report 2.4
- £1,206,559 Total revenue funding available for Ollerton up to RIBA 4 (NSDC reserves £23,255, third party £5,000, UKSPF £511,650, S106 £31,654, LUF Grant £635,000) Report 2.3, P45, P46
- £607,377 Total revenue funding available for Clipstone Phases 2 and 3 (UKSPF £31,377, Capacity Funding £255,000, LUF Grant £321,000) Report 2.7, P52, P53
- £20m Original LUF 3 grant award for the Shaping Sherwood's Revival scheme Report 1.1
Options considered
- Rejected: Restrict the scheme further to cut costs. Would damage the core objective of transformational change and improved access to services Report 1.17
- Rejected: Delay further scheme budgets until planning consent, FBC and land acquisition are complete. Would risk missing the March 2028 grant deadline Report 1.12, 1.20
- Rejected: Delegate final lease sign-off only after planning application, as previously agreed. Change sought to mitigate further delays and prevent a legal bottleneck Report 1.15
Implications
- Financial: Total scheme shortfall of c£1,330,000 now being met from Change Management Reserve and Capital Receipts; FBC cannot be signed off without this contribution. Report 1.17, 1.20, P42
- Legal: A revised Memorandum of Understanding will be issued by the UK Government for the new Local Regeneration Fund, subject to legal review. Report 1.4, P39, 2.1
- Risk: If the project does not progress, the council will need to find alternative uses for the Forest Centre and former Lloyds Bank units, with significant refurbishment costs. Assessed as low risk. Report 1.13
Who and where
- Ollerton community and town centre users Report 1.5, 1.8, P4
- Ollerton and Boughton Town Council (OBTC), taking space in the new public sector hub Report 1.14, 1.15, P19
- Clipstone community and visitors to Vicar Water Country Park Report 1.25, 1.28, P33
- Clipstone Miners Welfare Community Trust (CMWCT), delivery partner for Phase 2 sports scheme Report 1.27
- Welbeck Estates, landowner involved in Clipstone land swap and VWCP lease Report 1.27, 1.28
- Main construction contractors tendering for Clipstone Phase 1 (13 attended site visit) Report 1.26
Timeline
- 2 September 2025: UK Government announced shift from LUF to Local Regeneration Fund Report 1.4
- 11 September 2025: Final Ollerton design exhibition held at the Town Hall Report 1.8
- 26 September 2025: Clipstone Phase 1 main construction tenders closed Report 1.26
- October 2025: Ollerton planning application expected to be submitted Report 1.5
- 14 October 2025: Member's Briefing Session to present final Ollerton plans Report 1.9
- 11 November 2025: Next Cabinet report on LUF/Local Regeneration Fund programme Report 1.29
- January 2026: Clipstone Phase 1 start on site programmed Report 1.26
- Early 2026: Clipstone Phase 3 (Vicar Water Country Park) planning submission expected Report 1.28
- Summer 2026: Clipstone Phase 3 development commencement expected Report 1.28
- March 2028: Revised LUF 3/Local Regeneration Fund grant spend deadline Report 1.2, 1.20
Plain English for the jargon
- LUF 3: Levelling Up Fund Round 3, the government's £20m grant to the council, now renamed Local Regeneration Fund
- Local Regeneration Fund: New name announced 2 September 2025 consolidating Levelling Up Fund, Town Deals and the Pathfinder Pilot
- FBC: Full Business Case, required before the grant can be drawn down
- RIBA Stage 3 / 4: Royal Institute of British Architects design stages: Stage 3 is Developed Design, Stage 4 is Technical Design
- OBTC: Ollerton and Boughton Town Council, partner taking space in the new public sector hub
- UKSPF / REPF: UK Shared Prosperity Fund and Rural England Prosperity Fund
- CMWCT: Clipstone Miners Welfare Community Trust, partner for the Clipstone sports scheme
- VWCP: Vicar Water Country Park, the focus of Clipstone Phase 3
- SME: Small and Medium Enterprises, space retained in the Ollerton design